Western Union Telegraph Co. v. Massman Construction Co.

402 A.2d 1275, 1979 D.C. App. LEXIS 399
CourtDistrict of Columbia Court of Appeals
DecidedJune 19, 1979
Docket13821
StatusPublished
Cited by38 cases

This text of 402 A.2d 1275 (Western Union Telegraph Co. v. Massman Construction Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Union Telegraph Co. v. Massman Construction Co., 402 A.2d 1275, 1979 D.C. App. LEXIS 399 (D.C. 1979).

Opinion

KERN, Associate Judge:

Appellant Western Union seeks reversal of the trial court’s ruling that its claim against appellees for recovery of damages is grounded in tort, not contract, and therefore must be dismissed as untimely filed under the applicable statute of limitations, D.C.Code 1973, § 12-301(3), which commenced in its view to run from the date of damage to appellant’s facilities. The court, in dismissing the complaint, rejected appellant’s theory that it was a third-party beneficiary of a contract to which appellees were promisors. Instead, the court found that appellant was merely an incidental beneficiary to the contract and therefore unable to assert rights under it.

The record reflects that in May 1972, the Washington Metropolitan Area Transit Authority (WMATA) contracted with appel-lees (operating as a joint venture under the name of Early-Massman) for the construction of part of the McPherson Square section of the Metro subway system. As part of the contract Early-Massman agreed to maintain, protect and restore those utilities affected by the construction, to perform the construction in such a manner as to keep existing utilities in operation and to repair at its expense all damage to utilities caused by its work. Among the utilities named in the contract were “Telegraph Company Facilities.” No work could begin until Early-Massman had located utility facilities and submitted its plans to appellant and other utility owners for approval. The contract further required collaboration between Early-Massman and all utility owners in preparation of schedules and working drawings that affected the utilities.

On June 20, 1973, Early-Massman struck and damaged appellant’s underground equipment. Appellant made temporary repairs on its facilities in order to maintain service and sent Early-Massman a bill on March 11, 1974 for $807.21. Early-Mass-man forwarded the bill to National Loss Control Service Corporation (NLCSC), 1 an insurance adjuster for Lumbermens Mutual Casualty Company which had issued a policy for liability insurance to WMATA with appellees named as the insured.

On April 5, 1974, appellant sent Early-Massman a second bill for $2,765.12, representing additional expenses incurred in repairing the damage to its equipment. By a letter of May 21, 1974, Early-Massman advised appellant that it had sent both bills to NLCSC and had requested expedited payment by the insurance carrier. A representative of NLCSC sent appellant a letter on December 10,1974, stating that the company would “take care” of the two bills but preferred to wait until final repairs were completed so as to pay all of the bills at one time. Six days later, appellant responded requesting immediate payment.

On April 22, 1975, appellant received a letter from NLCSC stating that Early-Massman was not legally responsible for the damage and that appellant would not be reimbursed for making repairs to its facilities. After further unsuccessful negotiations among the parties, appellant again demanded payment of NLSC in February 1977. NLCSC refused on March 7 stating that the statute of limitations had expired. Appellant filed suit on May 20, 1977, claiming $3,572.33 for Early-Massman’s negligent damage to its equipment. Appellees moved for judgment on the pleadings claiming that the three-year statute of limitations had already expired before the filing of the suit and hence precluded the claim. In late August appellant filed an amended complaint which included as its theory of recovery that it was a third-party beneficiary to *1277 the WMATA-Early-Massman contract and claimed $19,186.48 in damages ($3,752.33 plus $15,614.15 for final repairs). 2

The trial court held that appellant was, at best, only an incidental beneficiary to the WMATA-Early-Massman contract concerning construction of part of the Metro system and therefore had no right to recover as a third-party beneficiary. Finding the suit grounded on tort, the court dismissed appellant’s complaint as untimely filed under D.C.Code 1973, § 12-301(3).

Appellant urges that the court erred in its determination that appellant was not a third-party beneficiary to the WMATA-Early-Massman contract, and that since it did have rights under this contract the statute of limitations would not preclude suit because either (1) no breach occurred until the NLCSC letter to appellant of April 22, 1975, and that the three-year statute of limitations, D.C.Code 1973, § 12-301(7), may only begin to run from that date, or (2) NLCSC’s (Early-Massman’s agent’s) letter of December 10, 1974, to appellant was an acknowledgment of a debt from which time the statute began to run anew under D.C. Code 1973, § 28-3504. We conclude that appellant was a third-party beneficiary and that the breach of contract did not occur until, at the earliest, April 22,1975. Hence, appellant’s suit was timely filed. 3

One who is not a party to a contract nonetheless may sue to enforce its provisions if the contracting parties intend the third party to benefit directly thereunder. Moran v. Audette, D.C.App., 217 A.2d 653, 654 (1966); Aetna Casualty & Surety Co. v. Kemp-Smith Co., D.C.App., 208 A.2d 737, 738-39 (1965). We will read the contract as a whole to determine whether the third party’s benefit under the contract is intended or incidental. Moran v. Audet,te, supra at 654. Consequently, the absence of the third party’s name from the contract is not fatal to his claim, especially when the surrounding circumstances tend to identify the third-party beneficiary. Id. (Only one person was entitled to a commission as broker.) The contract before us does not mention appellant by name, although in enumerating the various types of utilities contemplated in the contract it includes appellant under the rubric “Telegraph Company.” We note that the contract, even though it is written open-endedly, does not contemplate all telegraph companies or even all the enumerated types of utilities. Rather, it must be read to refer to those utilities whose cables, wires, and other equipment ran through the underground area that was the job-site under the contract. Further, the contract contemplates appellant’s role as an active participant in the work to be performed under the contract rather than as a total stranger to the contract who, by chance, enjoys an occasional benefit. Finally, the contract provides specifically that appellee should maintain and support the underground equipment of the various utilities in addition to undertaking all repairs for any damage caused. Quite clearly, this contract does more than merely indemnify WMATA for any liabilities arising out of appellees’ performance. We hold, therefore, on the basis of all of these factors, that appellant was an intended beneficiary under the WMATA-Early-Massman contract and was entitled to sue to enforce its provisions.

We turn now to the statute of limitations issue. D.C.Code 1973, § 12-301(7) begins to run when a contract is breached. In Dillard v. Travelers Insurance Co., D.C. App., 298 A.2d 222

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reinhardt v. Guidehouse, Inc.
District of Columbia, 2025
Colella v. Androus
District of Columbia, 2021
Williams v. Aviles
District of Columbia, 2020
Howad B. Silverberg v. Joanne S. Becker
191 A.3d 324 (District of Columbia Court of Appeals, 2018)
Sakyi v. Estee Lauder Companies, Inc.
District of Columbia, 2018
Sakyi v. Estée Lauder Cos.
308 F. Supp. 3d 366 (D.C. Circuit, 2018)
ABU NASER HOSSAIN v. JMU PROPERTIES, LLC
147 A.3d 816 (District of Columbia Court of Appeals, 2016)
Intelect Corporation v. Cellco Partnership Gp
160 F. Supp. 3d 157 (District of Columbia, 2016)
Ellis v. Holy Comforter Saint Cyprian Community Action Group
153 F. Supp. 3d 338 (District of Columbia, 2016)
Kamal Jahanbein v. The Ndidi Condominium Unit Owners Association, Inc.
85 A.3d 824 (District of Columbia Court of Appeals, 2014)
Estate of Millie Ann McDaniels v. Liberty Mutual Group Inc.
888 F. Supp. 2d 185 (District of Columbia, 2012)
Akers v. Windward Capital Corp. (In Re Akers)
445 B.R. 1 (District of Columbia, 2011)
Ficken v. AMR Corp.
578 F. Supp. 2d 134 (District of Columbia, 2008)
St. James Mutual Homes v. Andrade
951 A.2d 766 (District of Columbia Court of Appeals, 2008)
Monument Realty LLC v. Washington Metropolitan Area Transit Authority
535 F. Supp. 2d 60 (District of Columbia, 2008)
Sidibe v. Traveler's Insurance
468 F. Supp. 2d 97 (District of Columbia, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
402 A.2d 1275, 1979 D.C. App. LEXIS 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-union-telegraph-co-v-massman-construction-co-dc-1979.