Aetna Casualty & Surety Co. v. Kemp Smith Co.

208 A.2d 737, 1965 D.C. App. LEXIS 175
CourtDistrict of Columbia Court of Appeals
DecidedApril 12, 1965
Docket3579
StatusPublished
Cited by12 cases

This text of 208 A.2d 737 (Aetna Casualty & Surety Co. v. Kemp Smith Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aetna Casualty & Surety Co. v. Kemp Smith Co., 208 A.2d 737, 1965 D.C. App. LEXIS 175 (D.C. 1965).

Opinion

HOOD, Chief Judge.

In November 1960, appellant Spencer, White & Prentis, Inc. entered into a contract, hereafter “the foundation contract,” with International Land Corporation which obligated appellant to perform certain foundation work in connection with the construction of an office building. Thereafter, Spencer, White & Prentis engaged W. H. Nicholson Associates, Inc. to undertake excavation work pertinent to the foundation construction, and Nicholson, in turn, on February 14, 1961, contracted with plaintiff-appellee Kemp Smith Co., Inc. for the performance of machine excavation at the job site.

*738 On March 17, 1961, pursuant to a separate contract entered into between International Land and appellant George A. Fuller Co., Inc., under which Fuller became the general contractor on the project, the foundation contract was assigned to Fuller with the consent of Spencer, White & Prentis. Subsequently, on March 27, 1961, appellant Fuller as principal and appellant Aetna Casualty & Surety Co. as surety executed a Labor and Material Payment Bond for the protection of International Land.

Appellee Smith completed its work on May 5, 1961, and on May 31, notified Aetna of its claim for payment, Nicholson having in the meanwhile defaulted on its contract with Spencer, White & Prentis. Smith then filed suit against Aetna, Fuller, and Spencer, White & Prentis, and a trial was had which resulted in the judgment appealed from. 1

THE CLAIM AGAINST SPENCER, WHITE & PRENTIS

Under Article 9 of the General Conditions attached to the foundation contract, Spencer, White & Prentis, as contractor, agreed that

“Unless otherwise stipulated, the Contractor shall provide and pay for all materials, labor, water, tools, equipment, light, power, transportation and other facilities necessary for the execution .and completion of the work.”

On this appeal, it is argued that that promise, running from Spencer, White & Pren-tis to International Land, will not support an action for payment by the appellee as a third party beneficiary. In support of that argument, appellant .contends that except where surety contracts are involved, the District of Columbia has not adopted the third party beneficiary doctrine, and that in any event, appellee is at most an incidental beneficiary, and would, accordingly, be without enforceable rights even in those jurisdictions where the doctrine prevails.

Our research reveals no case in this jurisdiction expressly adopting or rejecting the third party beneficiary rule. However, in Marranzano v. Riggs Nat. Bank of Washington, D. C., 87 U.S.App.D.C. 195, 196, 184 F.2d 349, 350 (1950), there was a recognition that there are exceptions “to the general rule that a stranger to a contract may not sue to enforce its terms or to recover damages for a violation thereof”; and there are other cases indicating that the third party beneficiary rule would be applied in a proper case. Hall v. Gardiner, 75 U.S.App.D.C. 226, 126 F.2d 227 (1942); Schwartz v. Brown, D.C.Mun.App., 64 A.2d 298 (1949). 2 In Guinn Company v. Mazza, 111 U.S.App.D.C. 319, 296 F.2d 441 (1961), the rule was recognized, but that case was controlled by the law of New York.

Turning to other jurisdictions we find that a large majority of the states have adopted the rule. “The great weight of authority recognizes a direct enforceable right, both at law and in equity, arising from a contract promising performance for either of the first two types of beneficiaries —the donee beneficiary and the creditor beneficiary * * 2 Williston, Contracts § 356 (3d ed. Jaeger 1959). 3 Re *739 statement, Contracts §§ 133-147 (1932) also recognizes the rule, and it has been said that the Restatement “is entitled to particular respect when authorities are in conflict * * Bailey v. Zlotnick, 80 U. S.App.D.C. 117, 118, 149 F.2d 505, 506 (1945). We perceive no reason why this jurisdiction should not adopt the rule followed by the majority of jurisdictions in this country.

In Nash Engineering Co. v. Marcy Realty Corporation, 222 Ind. 396, 54 N.E. 2d 263 (1944), it was held that Article 9, as quoted above, afforded unnamed ma-terialmen a remedy as third party beneficiaries against the contractor. As the Maryland court stated in a case reaching a similar result under the same provisions:

“We find the obligation assumed by the general contractor in the case before us was just what he wrote that it would be, read literally, namely, to pay for all of the materials necessary for the doing of the job.” Kirby v. Board of Ed. of Cecil County, 210 Md. 383, 123 A.2d 606, 610 (1956).

Save for the fact that materials were furnished rather than labor, in both the cases cited the plaintiffs stood in precisely the same position vis a vis the contractor as the appellee here. It follows that appellee is entitled to recover for the work it performed, and the judgment against Spencer, White & Prentis is, accordingly, affirmed. 4

THE CLAIM AGAINST GEORGE A. FULLER CO., INC.

Appellee seeks to support the judgment against appellant Fuller on two grounds. It argues first that when Fuller accepted the benefits of the foundation contract under the assignment, it came under a duty to perform that contract according to the conditions and terms as provided therein. Second, it argues that Fuller became liable, like Spencer, White & Prentis, as general contractor under Article 9 of the General Conditions which attached to its contract of March 17, 1961, with International Land.

We find that neither theory has merit. Certainly Fuller did, under the assignment, come under a duty to perform pursuant to the terms of the foundation contract, but that duty was merely to pay Spencer, White & Prentis upon the satisfactory completion of the foundation work, precisely the duty originally assumed by International Land.

It is equally clear that Fuller, by virtue of its undertaking under Article 9, could have become liable to laborers and ma-terialmen having no contractual relationship with either Fuller or International. Land. We do not think, however, that that doctrine, utilized to support the judgment against Spencer, White & Prentis, can be extended to permit recovery against Fuller. When Fuller assumed the status of general contractor in March 1961, the other agreements relevant here had already been executed. Fuller, therefore, had no opportunity to exercise any control over the selection of sub- and sub-sub-contractors, nor to secure itself against the possibility of default by requiring a sub-contractor’s bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berlin Steel Construction Co. v. Salah & Pecci Leasing Co.
5 A.3d 608 (Supreme Court of Delaware, 2010)
Casanova v. Marathon Corporation
District of Columbia, 2010
Casanova v. Marathon Corp.
715 F. Supp. 2d 35 (District of Columbia, 2010)
Monument Realty LLC v. Washington Metropolitan Area Transit Authority
535 F. Supp. 2d 60 (District of Columbia, 2008)
Fields v. Tillerson
726 A.2d 670 (District of Columbia Court of Appeals, 1999)
General Insurance Co. of America v. Interstate Service Co.
701 A.2d 1213 (Court of Special Appeals of Maryland, 1997)
Bay General Industries, Inc. v. Johnson
418 A.2d 1050 (District of Columbia Court of Appeals, 1980)
Western Union Telegraph Co. v. Massman Construction Co.
402 A.2d 1275 (District of Columbia Court of Appeals, 1979)
Honey v. George Hyman Construction Co.
63 F.R.D. 443 (District of Columbia, 1974)
Home Indemnity Co. v. Daniels Construction Co.
228 So. 2d 824 (Supreme Court of Alabama, 1969)
Shea v. Jackson
245 A.2d 120 (District of Columbia Court of Appeals, 1968)
Moran v. Audette
217 A.2d 653 (District of Columbia Court of Appeals, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
208 A.2d 737, 1965 D.C. App. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aetna-casualty-surety-co-v-kemp-smith-co-dc-1965.