Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc.

CourtCourt of Appeals of Minnesota
DecidedJuly 18, 2016
DocketA15-1892
StatusUnpublished

This text of Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc. (Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc., (Mich. Ct. App. 2016).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A15-1892

Grefe Construction, Inc., Appellant,

vs.

Double J Concrete & Masonry, Inc., Respondent.

Filed July 18, 2016 Affirmed; motion denied Stauber, Judge

Kandiyohi County District Court File No. 34-CV-14-367

Peter M. Waldeck, Lindsey J. Woodrow, Waldeck Law Firm, P.A., Minneapolis, Minnesota (for appellant)

William L. Davidson, Jason R. Prochnow, João C. Medeiros, Lind, Jensen, Sullivan & Peterson, P.A., Minneapolis, Minnesota; and

Jessica K. Allen, Pfefferle Kane, L.L.P., Minneapolis, Minnesota (for respondent)

Considered and decided by Johnson, Presiding Judge; Ross, Judge; and Stauber,

Judge.

UNPUBLISHED OPINION

STAUBER, Judge

In this action by appellant-contractor against respondent-masonry-subcontractor

for negligent installation, appellant argues that the district court erred by granting summary judgment to respondent because the controlling building code is subject to

alternative interpretations. Appellant also contends that the district court abused its

discretion by refusing to accept the late deposition of one of appellant’s experts. After

the parties filed their briefs in this matter, respondent moved to strike portions of

appellant’s principal brief and reply brief. We affirm the summary judgment in favor of

respondent and deny the motion to strike as moot.

FACTS

In 2003, Daniel and Janet Costello hired appellant Grefe Construction to remodel

and construct their lake home. Appellant subsequently contracted with respondent

Double J Concrete & Masonry, Inc. to install stone-veneer siding to the home. It is

undisputed that respondent installed a single layer of Grade 15 asphalt saturated felt

paper (grade 15 felt) as the weather barrier between the stone veneer siding and the

oriented strand board (OSB) wall sheathing. Specifically, respondent applied the felt

over a layer of OSB sheathing, secured a lath to the felt, and applied a scratch coat of

either plaster or mortar to the lath. Respondent then adhered the stone veneer siding to

the scratch coat.

Construction on the home was completed in August 2004. The Costellos later

observed signs of water/moisture intrusion in their home, which ultimately required

replacement of all the stone-veneer siding on the home. The Costellos filed a demand for

arbitration against appellant. Following arbitration in August 2012, the Costellos were

awarded approximately $500,000 for the repairs, remediation, and forensic investigation

incurred arising from the damage to their home, as well as approximately $50,000 in

2 costs, attorney fees, and expert-witness costs. The arbitration award allocated damages

between appellant and respondent, apportioning to respondent approximately $300,000 in

damages and approximately $30,000 in costs and fees.

In July 2014, appellant brought this action against respondent for contribution,

alleging that respondent was negligent in the installation of the stone-veneer siding

because the grade 15 felt installed behind the adhered stone veneer did not satisfy the

applicable building code. Respondent moved for summary judgment, arguing that it was

required to install the stone-veneer siding in compliance with International Residential

Code (IRC) § R703.7 (2000), which requires that one layer of grade 15 felt be used when

installing stone veneer siding. In response, appellant claimed that respondent was

required to install the stone veneer siding in compliance with IRC § R703.6, which

requires that two layers of building paper classified as “Grade D paper” be installed

behind the adhered stone veneer.

The district court found that “[t]he only real issue to be determined . . . in this

matter is which section of the [IRC] applied to the installation of the stone veneer siding,

i.e. whether the use of the [g]rade 15 [f]elt . . . was appropriate under the [IRC].”

Although appellant claimed that the “‘battle of experts’ on the issue of which [IRC]

section applies creates an issue of fact,” the district court concluded that “what the

experts believe the [IRC] says is not the issue” because a determination of the applicable

[IRC] provision is solely an issue of statutory construction. The district court then found

that section R703.7 governed, and specified that grade 15 felt be used during

construction. Because there was no dispute that respondent used grade 15 felt in the

3 construction of the home, the district court granted respondent’s motion for summary

judgment. This appeal followed.

DECISION

I.

Summary judgment is appropriate when the admissible evidence presents no

genuine issue of material fact and one party is entitled to judgment as a matter of law.

Fabio v. Bellomo, 504 N.W.2d 758, 761 (Minn. 1993). This court reviews summary

judgment de novo to determine whether the district court properly applied the law and if

genuine issues of material fact exist to preclude summary judgment. Riverview Muir

Doran, LLC v. JADT Dev. Grp., LLC, 790 N.W.2d 167, 170 (Minn. 2010). In doing so,

any conflicting evidence is considered in the light most favorable to the party who

opposes summary judgment. Fabio, 504 N.W.2d at 761.

Appellant challenges the district court’s grant of summary judgment to

respondent, arguing that summary judgment was inappropriate because evidence was

presented demonstrating that the IRC “is subject to alternative interpretations as applied

to the facts of this case.” Specifically, appellant argues that the district court erred by

(1) concluding that section R703.7 was the applicable section of the IRC; (2) refusing to

consider or defer to the building official’s interpretation of the IRC; and (3) refusing to

consider expert testimony on the applicable standard of care. Appellant further argues

that summary judgment was inappropriate because there are issues of material fact as to

whether grade 15 felt is equivalent to two layers of Grade D paper.

4 A. Applicable section of the IRC

The State Building Code governs the construction, reconstruction, alteration, and

repair of buildings. Minn. Stat. § 326B.101 (2014). The purpose of the code is to

“provide basic and uniform performance standards, establish reasonable safeguards for

health, safety, welfare, comfort, and security of the residents of this state and provide for

the use of modern methods, devices, materials, and techniques which will in part tend to

lower construction costs.” Id. To effectuate this legislative purpose, the statute instructs

the commissioner of labor and industry to establish by administrative rule “a code of

standards for the construction, reconstruction, alteration, and repair of buildings,

governing matters of structural materials, design and construction, fire protection, health,

sanitation, and safety.” Minn. Stat. § 326B.106, subd. 1 (2014).

In 2003, the “2000 edition of the [IRC] as promulgated by the International Code

Council . . . [was] incorporated by reference and made part of the Minnesota State

Building Code except as qualified by the applicable provisions of the Minnesota Rules,

chapter 1300.” Minn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drewitz v. Motorwerks, Inc.
728 N.W.2d 231 (Supreme Court of Minnesota, 2007)
City of Eveleth v. Ruble
225 N.W.2d 521 (Supreme Court of Minnesota, 1974)
Lee v. State, Department of Natural Resources
478 N.W.2d 237 (Court of Appeals of Minnesota, 1991)
State v. Arkell
672 N.W.2d 564 (Supreme Court of Minnesota, 2003)
Miller v. Colortyme, Inc.
518 N.W.2d 544 (Supreme Court of Minnesota, 1994)
Admiral Merchants Motor Freight, Inc. v. O'Connor & Hannan
494 N.W.2d 261 (Supreme Court of Minnesota, 1992)
Fabio v. Bellomo
504 N.W.2d 758 (Supreme Court of Minnesota, 1993)
Braith v. Fischer
632 N.W.2d 716 (Court of Appeals of Minnesota, 2001)
J.D. Donovan, Inc. v. Minnesota Department of Transportation
878 N.W.2d 1 (Supreme Court of Minnesota, 2016)
Riverview Muir Doran, LLC v. JADT Development Group, LLC
790 N.W.2d 167 (Supreme Court of Minnesota, 2010)
Christianson v. Henke
831 N.W.2d 532 (Supreme Court of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/grefe-construction-inc-v-double-j-concrete-masonry-inc-minnctapp-2016.