Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc.

Court of Appeals of Minnesota·Decided July 18, 2016·No. A15-1892·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA

IN COURT OF APPEALS

A15-1892

Grefe Construction, Inc., Appellant,

vs.

Double J Concrete & Masonry, Inc., Respondent.

Filed July 18, 2016

Affirmed; motion denied

Stauber, Judge

Kandiyohi County District Court File No. 34-CV-14-367

Peter M. Waldeck, Lindsey J. Woodrow, Waldeck Law Firm, P.A., Minneapolis, Minnesota (for appellant)

William L. Davidson, Jason R. Prochnow, João C. Medeiros, Lind, Jensen, Sullivan & Peterson, P.A., Minneapolis, Minnesota; and

Jessica K. Allen, Pfefferle Kane, L.L.P., Minneapolis, Minnesota (for respondent)

Considered and decided by Johnson, Presiding Judge; Ross, Judge; and Stauber, Judge.

UNPUBLISHED OPINION

STAUBER, Judge In this action by appellant-contractor against respondent-masonry-subcontractor for negligent installation, appellant argues that the district court erred by granting

summary judgment to respondent because the controlling building code is subject to alternative interpretations. Appellant also contends that the district court abused its discretion by refusing to accept the late deposition of one of appellant’s experts. After the parties filed their briefs in this matter, respondent moved to strike portions of appellant’s principal brief and reply brief. We affirm the summary judgment in favor of respondent and deny the motion to strike as moot.

FACTS

In 2003, Daniel and Janet Costello hired appellant Grefe Construction to remodel and construct their lake home. Appellant subsequently contracted with respondent Double J Concrete & Masonry, Inc. to install stone-veneer siding to the home. It is undisputed that respondent installed a single layer of Grade 15 asphalt saturated felt paper (grade 15 felt) as the weather barrier between the stone veneer siding and the oriented strand board (OSB) wall sheathing. Specifically, respondent applied the felt over a layer of OSB sheathing, secured a lath to the felt, and applied a scratch coat of either plaster or mortar to the lath. Respondent then adhered the stone veneer siding to the scratch coat.

Construction on the home was completed in August 2004. The Costellos later observed signs of water/moisture intrusion in their home, which ultimately required replacement of all the stone-veneer siding on the home. The Costellos filed a demand for arbitration against appellant. Following arbitration in August 2012, the Costellos were awarded approximately $500,000 for the repairs, remediation, and forensic investigation incurred arising from the damage to their home, as well as approximately $50,000 in

costs, attorney fees, and expert-witness costs. The arbitration award allocated damages between appellant and respondent, apportioning to respondent approximately $300,000 in damages and approximately $30,000 in costs and fees.

In July 2014, appellant brought this action against respondent for contribution, alleging that respondent was negligent in the installation of the stone-veneer siding because the grade 15 felt installed behind the adhered stone veneer did not satisfy the applicable building code. Respondent moved for summary judgment, arguing that it was required to install the stone-veneer siding in compliance with International Residential Code (IRC) § R703.7 (2000), which requires that one layer of grade 15 felt be used when installing stone veneer siding. In response, appellant claimed that respondent was required to install the stone veneer siding in compliance with IRC § R703.6, which requires that two layers of building paper classified as “Grade D paper” be installed behind the adhered stone veneer.

The district court found that “[t]he only real issue to be determined . . . in this matter is which section of the [IRC] applied to the installation of the stone veneer siding, i.e. whether the use of the [g]rade 15 [f]elt . . . was appropriate under the [IRC].” Although appellant claimed that the “‘battle of experts’ on the issue of which [IRC] section applies creates an issue of fact,” the district court concluded that “what the experts believe the [IRC] says is not the issue” because a determination of the applicable [IRC] provision is solely an issue of statutory construction. The district court then found that section R703.7 governed, and specified that grade 15 felt be used during construction. Because there was no dispute that respondent used grade 15 felt in the

construction of the home, the district court granted respondent’s motion for summary judgment. This appeal followed.

DECISION

I.

Summary judgment is appropriate when the admissible evidence presents no genuine issue of material fact and one party is entitled to judgment as a matter of law. Fabio v. Bellomo, 504 N.W.2d 758, 761 (Minn. 1993). This court reviews summary judgment de novo to determine whether the district court properly applied the law and if genuine issues of material fact exist to preclude summary judgment. Riverview Muir Doran, LLC v. JADT Dev. Grp., LLC, 790 N.W.2d 167, 170 (Minn. 2010). In doing so, any conflicting evidence is considered in the light most favorable to the party who opposes summary judgment. Fabio, 504 N.W.2d at 761.

Appellant challenges the district court’s grant of summary judgment to respondent, arguing that summary judgment was inappropriate because evidence was presented demonstrating that the IRC “is subject to alternative interpretations as applied to the facts of this case.” Specifically, appellant argues that the district court erred by (1) concluding that section R703.7 was the applicable section of the IRC; (2) refusing to consider or defer to the building official’s interpretation of the IRC; and (3) refusing to consider expert testimony on the applicable standard of care. Appellant further argues that summary judgment was inappropriate because there are issues of material fact as to whether grade 15 felt is equivalent to two layers of Grade D paper.

A. Applicable section of the IRC The State Building Code governs the construction, reconstruction, alteration, and repair of buildings. Minn. Stat. § 326B.101 (2014). The purpose of the code is to “provide basic and uniform performance standards, establish reasonable safeguards for health, safety, welfare, comfort, and security of the residents of this state and provide for the use of modern methods, devices, materials, and techniques which will in part tend to lower construction costs.” Id. To effectuate this legislative purpose, the statute instructs the commissioner of labor and industry to establish by administrative rule “a code of standards for the construction, reconstruction, alteration, and repair of buildings, governing matters of structural materials, design and construction, fire protection, health, sanitation, and safety.” Minn. Stat. § 326B.106, subd. 1 (2014).

In 2003, the “2000 edition of the [IRC] as promulgated by the International Code Council . . . [was] incorporated by reference and made part of the Minnesota State Building Code except as qualified by the applicable provisions of the Minnesota Rules, chapter 1300.” Minn. R. 1309.010, subp. 1 (2003). It is undisputed that IRC § R703, entitled “Exterior Covering,” applies here. Section R703.1 provides that “[e]xterior walls shall provide the building with a weather-resistant exterior wall envelope,” and that this wall envelope “shall be designed and constructed in such a manner to prevent the accumulation of water within the wall assembly by providing a water-resistive barrier behind the exterior veneer as required by [s]ection R703.2.” IRC § R703.1. Section R703.7, which is entitled “Stone and masonry veneer, general,” requires that “[a]ll stone and masonry veneer shall be installed in accordance with this chapter,” including Figure

Free access — add to your briefcase to read the full text and ask questions with AI

Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc., (Mich. Ct. App. 2016).

Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc. (Grefe Construction, Inc. v. Double J Concrete & Masonry, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Drewitz v. Motorwerks, Inc.
728 N.W.2d 231 (Supreme Court of Minnesota, 2007)
City of Eveleth v. Ruble
225 N.W.2d 521 (Supreme Court of Minnesota, 1974)
Lee v. State, Department of Natural Resources
478 N.W.2d 237 (Court of Appeals of Minnesota, 1991)
State v. Arkell
672 N.W.2d 564 (Supreme Court of Minnesota, 2003)
Miller v. Colortyme, Inc.
518 N.W.2d 544 (Supreme Court of Minnesota, 1994)
Admiral Merchants Motor Freight, Inc. v. O'Connor & Hannan
494 N.W.2d 261 (Supreme Court of Minnesota, 1992)
Fabio v. Bellomo
504 N.W.2d 758 (Supreme Court of Minnesota, 1993)
Braith v. Fischer
632 N.W.2d 716 (Court of Appeals of Minnesota, 2001)
J.D. Donovan, Inc. v. Minnesota Department of Transportation
878 N.W.2d 1 (Supreme Court of Minnesota, 2016)
Riverview Muir Doran, LLC v. JADT Development Group, LLC
790 N.W.2d 167 (Supreme Court of Minnesota, 2010)
Christianson v. Henke
831 N.W.2d 532 (Supreme Court of Minnesota, 2013)