Walter v. Hangen

71 A.D. 40, 75 N.Y.S. 683
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 15, 1902
StatusPublished
Cited by6 cases

This text of 71 A.D. 40 (Walter v. Hangen) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walter v. Hangen, 71 A.D. 40, 75 N.Y.S. 683 (N.Y. Ct. App. 1902).

Opinion

Ingraham, J. :

The plaintiff in this action sought to recover the damages sustained by reason of a breach of a contract by which the defendant agreed to rebuild two buildings known as Hos. 20 and 22 Clinton place in the city of Hew York. The amount of damages demanded in the complaint was $10,000 and interest, and the jury found a [41]*41verdict for the plaintiff for $7,700; and from the judgment entered upon that verdict and from an order denying a motion for new trial the defendant appeals.

By the contract between the parties the defendant was “ to alter, erect and rebuild the buildings upon the premises known as Numbers 20 and 22 Clinton Place in the City of New York, agreeably to certain drawings and specifications made by John H. Brown, architect * * * in a good, workmanlike and substantial manner, and also to find and provide such good, proper and sufficient material of all kinds whatsoever as shall be sufficient for the completing and finishing of all the work on said buildings provided for and mentioned in the said, plans and specifications, all for the above-mentioned sum of twenty thousand eight hundred dollars.’ The complaint alleges that the defendant did not fulfill his part of the agreement or comply with the conditions of the said plan and specifications, and that by and through the negligence, unskillfulness and failure of the defendant to comply with the terms and conditions of the said agreements, plans and specifications, and not erecting the buildings as therein provided, the plaintiff has sustained damages in the sum of $10,000.- A bill of particulars was furnished By the plaintiff in which was specified the instances in which the defendant failed to comply with the plans and specifications. Upon the trial the plaintiff gave evidence which tended to show that the defendant had not complied with the contract. By the contract the plaintiff was to pay the defendant the sum of $20,800 for the work and material by executing, acknowledging and delivering to the defendant a bond secured by a mortgage upon the premises for the sum of $21,000, payable in five years from the 1st of June, 1896, with interest; and it is alleged and not disputed that that bond secured by a mortgage was given by the plaintiff to the defendant and accepted by him.

The most serious question presented on this appeal is as to the measure of damages adopted by the learned trial judge in submitting the case to the jury. It appears that one Harft, a real estate agent, had been the plaintiff’s agent in respect to these buildings, and acted as her agent in negotiating the contract with the defendant. He signed the contract as agent of the plaintiff, and the plaintiff testified that he was her agent; that he notified the defendant of [42]*42some of the defects in the buildings as they developed; that he went with her from time to time to the buildings; that he took possession of them for her in October, and that he represented the plaintiff in taking possession of the buildings. It also appeared that plaintiff had been in possession of the buildings since October, 1896; had rented these buildings to tenants, and had been in receipt of the rents;

Harft, who appears to have been a real estate broker, was called as a witness for the plaintiff, and testified as to visiting the buildings during their construction, and as to various particulars in which it was claimed that there was a violation of the contract by the defendant. The witness then was asked whether he could tell with rear sonable certainty what it would cost to repair these defects. This - was objected to on the ground that he was not an expert. This-, objection was overruled, and the counsel for the defendant asked that he be allowed to cross-examine the witness as to his competency as an expert, which was refused, the court stating that the defendant’s counsel could cross-examine afterwards, to which counsel for the defendant excepted. "Wé do not think that this ruling can be sustained. The witness was not a builder. He had testified that as a part of his real estate business he had built for himself and others, and had superintended repairs of buildings during the forty years he had been in business, but there is no evidence that he had any knowledge of the cost of building at this time. The witness answered that it could not be done for less than $10,000, and that some of the defects could not be repaired at all. The witness was then asked whether, if the buildings had been finished according to - the terms and conditions of the contract, he could have leased some of these floors or the entire building. This was objected to, but the objection was overruled and the witness answered “ yes.” As there was no claim made in the complaint or bill of particulars for loss of rent, it is difficult to see how this testimony was competent. The witness was. subsequently allowed to testify as to the amount of rents he would have received for the building if completed according to the terms of the contract. The court charged the jury that they could give no damages for delay, but the evidence was not stricken ; out nor were the jury instructed that they could not allow-the plaintiff for the rents that the witness had testified lie could have receivéd ' if the buildings had been completed- as required by the contract. [43]*43After the plaintiff took possession of the buildings, no repairs were made to the walls and nothing was done in relation to rebuild^ ing them. On October 1, 1896, the plaintiff took possession of the buildings, rented them and has continued in possession since that time. After the plaintiff took possession of the property there was-submitted to the defendant certain specified instances in which he had failed to comply with the contract; and in these particulars the contract was complied with by the defendant. Two witnesses were then called by the plaintiff as experts who had examined the buildings, and testified as to the cost of rebuilding so that the building would comply with the contract. One of these experts testified that the cost would be $9,686.51 for Mo. 20 and $5,106.63 for Mo. 22, aggregating more than half the contract price that the. defendant had received for tearing down the old buildings and building the new. The other witness testified that the full amount necessary to build Mo. 20, according to the plans and specifications, was $7,340.51, aiid to rebuild Mo. 22, $2,731.62. These estimates were based entirely upon an examination of the buildings made by these two witnesses in 1900, nearly five years after the buildings were completed and accepted by the plaintiff. The estimates were not based upon the difference in the value of the buildings as they existed, and the buildings as they would have been if completed according to the contract; but were based upon an estimate of the present cost of tearing down the buildings, so far as they were not completed as required by the contract and in rebuilding in accordance with its provisions and supplying all the other defects which are now shown, to exist five years after the completion and acceptance of the buildings in a way that would make them substantially new buildings.

The contract requires that the defendant “ Lath all ceilings, partitions and exposed or outside walls, and the cellar ceiling with wire lath; plaster three coats, scratch brown and a hard finish.” It appears to be conceded that this provision of the contract was not complied with and that wood lath was used instead of wire lath.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mount Sinai Hospital v. Borg-Warner Corp.
527 F. Supp. 922 (S.D. New York, 1981)
Webster v. Culver Roadways, Inc.
79 Misc. 2d 256 (New York Supreme Court, 1974)
Shell v. Schmidt
330 P.2d 817 (California Court of Appeal, 1958)
Bellizzi v. Huntley Estates, Inc.
1 A.D.2d 683 (Appellate Division of the Supreme Court of New York, 1955)
Mesler v. Cozzolino
208 Misc. 54 (New York County Courts, 1955)
Morris v. Fox
135 N.E. 663 (Indiana Court of Appeals, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
71 A.D. 40, 75 N.Y.S. 683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walter-v-hangen-nyappdiv-1902.