Perry v. Quackenbush

38 P. 740, 105 Cal. 299, 1894 Cal. LEXIS 1154
CourtCalifornia Supreme Court
DecidedDecember 31, 1894
DocketNo. 14497
StatusPublished
Cited by44 cases

This text of 38 P. 740 (Perry v. Quackenbush) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perry v. Quackenbush, 38 P. 740, 105 Cal. 299, 1894 Cal. LEXIS 1154 (Cal. 1894).

Opinion

Temple, C.

This is an appeal from the judgment and upon the judgment-roll.

The complaint shows that plaintiffs own a described tract of land; that on the 21st of January, 1887, they entered into a contract with the defendant, whereby defendant agreed, in consideration of the sum of three thousand dollars, to construct and build a house on said lot. As part of said contract plaintiffs executed and delivered to defendant their promissory note for the sum [303]*303of three thousand dollars, and a mortgage to secure the same on the described real estate. The note and mortgage are recited at length in the complaint.

Thereupon the defendant commenced the construction of the house, but in building the same did not furnish the quantity and quality of materials provided for in the contract.

That he did not construct said building in a good and workmanlike manner, and did not construct the building according to the contract, and has not performed his agreement.

Plaintiffs specify as defects:' He agreed in the construction of the foundations to use good, hard brick and lay seven courses,«and to construct twelve piers of brick laid in six courses. In violation of the agreement he used old, second-hand brick of poor quality, that had been used in other buildings, and laid the same in courses in five and six instead of seven, and constructed only six piers of brick of the same kind laid in three courses.

2. He agreed to use in the construction of the frame of said building the best kind of lumber; contrary to his agreement he used only second-class lumber and second-hand and refuse lumber that had been used in other buildings.

3. He agreed to use in the construction of the roof the best quality of shingles; contrary to his agreement he used second-hand lumber and second-class shingles.

4. He agreed to paint the building with two coats of metallic paint, but used no metallic paint at all, but cheap and inferior paint.

5. In divers other respects he disregarded and failed to carry out the agreement. That there is one thousand dollars difference in the value of the house as constructed and as called for under the agreement.

The answer denies all the allegations of the complaint in respect to the failure to perform the contract, and avers that the building was accepted by plaintiffs after a careful examination.

[304]*304The action was brought to have the note and mortgage canceled. Upon the issues made by the pleading the court found: That the construction of the building was completed before the commencement of this action; that in constructing said building defendant did not furnish the quantity and quality of materials provided for in said contract; that defendant did not construct said building in a good and workmanlike manner; that defendant did not perform said contract nor construct said building according to said agreement. There are, then, findings specifying defects as in the complaint, and finding all in favor of plaintiffs as alleged, except that as to the roof it finds that the shingles were of the quality agreed upon; and as to the painting, that defendant did not agree to use metallic paint, but in painting the building he used cheap and inferior material, contrary to his agreement.

After these specific findings is the following finding: “ That in divers other respects defendant disregarded his said specifications and failed to carry out his agreement.”

It was then found that “ there is three hundred and fifty dollars difference in value of said building as actually constructed and as it should have been constructed under said agreement pursuant to said specifications.”

It was found that the note and mortgage if left outstanding may cause serious injury to plaintiffs. That the building was never accepted or received by the plaintiffs in full or part satisfaction of the contract, but plaintiffs took possession of the building under protest, and with notice to the defendant that they were dissatisfied with it, and would not accept it, and offered “to deliver up to defendant said building if defendant would cancel said note and mortgage.”

As conclusion of law from these facts the court found that plaintiffs were entitled to judgment; that three hundred and fifty dollars be deducted from the amount secured by the note and mortgage, and that, as to the residue, the note and mortgage were adjudged valid. [305]*305A judgment was entered in accordance with the conclusion of law.

From this judgment plaintiffs have appealed, claiming that it is not supported by the findings of fact.

This contention must be sustained. The issues were whether the building had been constructed according to contract, and, if it had not been so constructed, whether it had been accepted by the plaintiffs as performed. On both these issues the court found for the plaintiffs.

Respondent .contends that what he calls the old rule upon the subject of performance has been relaxed, and now a more liberal rule, which only requires a substantial performance instead of a literal compliance with all the provisions of the contract, prevails. But, conceding this, the rule still is that the contract must be substantially performed.

The court here did not find that what was done, though not a literal compliance, amounted to a substantial performance, or that the failure was only in trivial matters. Upon every material issue the facts are found for the plaintiffs, and unless their complaint was demurrable, which is not claimed, they ar$ entitled to the judgment demanded.

Respondent’s" counsel claims that the ultimate fact found of nonperformance is a conclusion from the probative facts found, and that the finding" of probative facts being more specific must control. This point cannot be maintained, for several reasons:

1. Findings of probative facts will not, in general, control, limit, or modify the finding of the ultimate fact. The province of the trial court is to find the ultimate facts, and not probative facts. If, from a consideration of the probative facts, this court should determine that they did not justify the finding of the ultimate fact it would determine that the evidence was insufficient to justify the decision. This, it has been repeatedly held, cannot be done in this mode.

In Smith v. Acker, 52 Cal. 217, the court said: “ It has been held that where -facts are found from which [306]*306the existence of the ultimate fact must be conclusively-inferred the finding is sufficient as a finding of the ultimate fact. But, when the ultimate fact is found, no finding of probative facts, which may tend to establish that the ultimate fact was found against the evidence, can overcome the principal finding.” And it is said: This point could only have been made on motion for a new trial, or on appeal on a statement or bill of exceptions specifically pointing out the deficiencies in the evidence.” In other words the opposing party must be allowed to show what the evidence was, and is not concluded by the finding of probative facts.

This decision was expressly affirmed by this court in Gill v. Driver, 90 Cal. 72. See, also, Pico v. Cuyas, 47 Cal. 174; Barrante v. Garratt, 50 Cal. 112; Jones v. Clark, 42 Cal. 180; Mathews v. Kinsell, 41 Cal. 512; Downing v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hohenshelt v. Superior Court
California Supreme Court, 2025
People v. Hecker
179 Cal. App. 2d 823 (California Court of Appeal, 1960)
Miller v. Smith
179 Cal. App. 2d 114 (California Court of Appeal, 1960)
Shell v. Schmidt
330 P.2d 817 (California Court of Appeal, 1958)
Garrison v. Edward Brown & Sons
154 P.2d 377 (California Supreme Court, 1944)
Fitzpatrick v. Underwood
112 P.2d 3 (California Supreme Court, 1941)
Riggle v. Janss Inv. Corp.
88 F.2d 111 (Ninth Circuit, 1937)
United States Pipe & Foundry Co. v. City of Waco
100 S.W.2d 1099 (Court of Appeals of Texas, 1936)
Ross v. McDougal
55 P.2d 574 (California Court of Appeal, 1936)
Vila v. Brovelli
39 P.2d 855 (California Court of Appeal, 1935)
Morel v. Simonian
284 P. 694 (California Court of Appeal, 1930)
Zachary v. Chapman
284 P. 703 (California Court of Appeal, 1930)
Shumway v. Woolwine
257 P. 898 (California Court of Appeal, 1927)
Enterprise Foundry Co. v. Polly
238 P. 722 (California Court of Appeal, 1925)
Culver v. Miller
202 P. 338 (California Court of Appeal, 1921)
Banducci v. Sresovich
199 P. 72 (California Court of Appeal, 1921)
Thomas Haverty Co. v. Jones
197 P. 105 (California Supreme Court, 1921)
Joseph Musto Sons-Keenan Co. v. Pacific States Corp.
292 P. 138 (California Court of Appeal, 1920)
Simmons v. Firth
164 P.2d 807 (California Court of Appeal, 1917)
Potts v. Paxton
153 P. 957 (California Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
38 P. 740, 105 Cal. 299, 1894 Cal. LEXIS 1154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perry-v-quackenbush-cal-1894.