Simmons v. Firth

164 P.2d 807, 164 P. 807, 33 Cal. App. 187, 1917 Cal. App. LEXIS 141
CourtCalifornia Court of Appeal
DecidedMarch 8, 1917
DocketCiv. No. 2213.
StatusPublished
Cited by1 cases

This text of 164 P.2d 807 (Simmons v. Firth) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simmons v. Firth, 164 P.2d 807, 164 P. 807, 33 Cal. App. 187, 1917 Cal. App. LEXIS 141 (Cal. Ct. App. 1917).

Opinion

SHAW, J.

In this action plaintiffs as original contractors sued to enforce a mechanic’s lien for an unpaid balance alleged to be due them upon a contract made with Emil Firth, pursuant to which they constructed a concrete reservoir at an agreed price of $5,995. The defendants other than Firth filed answers and cross-complaints whereby they sought judgment against plaintiffs, and the enforcement of liens upon the same property for materials furnished to plaintiffs as such original contractors for use and used in the construction of the reservoir. After a demurrer interposed by Firth to the complaint was overruled, he filed an answer thereto, which, among other things, contained a counterclaim against plaintiffs for a sum in excess of the amount of plaintiffs’ alleged lien, and also -filed answers to the cross-complaints. Upon the issues thus joined a trial was had which resulted in a judgment in favor of plaintiffs and against Firth for a balance of $2,259:61, which was declared a lien upon the property described in the complaint, all as prayed for therein, and gave judgment against plaintiffs in. favor of cross-complainants, payment of which was ordered to be made from the proceeds of the judgment so rendered in favor, of plaintiffs and against defendant Emil Firth.

From the judgment so entered, Firth, adopting the alternative method in presenting the record, has appealed.

Conceding the court erred in overruling defendant Firth’s demurrer to the complaint for uncertainty (Wyman v. *189 Hooker, 2 Cal. App. 36, [83 Pac. 79]), in that it failed to make any reference to the engineer’s certificate of completion of the reservoir required by the contract as a prerequisite condition to plaintiffs’ right to final payment, or allege any excuse for not producing the same (Coplew v. Durand, 153 Cal. 278, [16 L. R. A. (N. S.) 791, 95 Pac. 38], and eases there cited), nevertheless, since it appears from the evidence received without objection that the engineer refused such certificate upon the ground that plaintiffs had not, as alleged by them, completed the reservoir in accordance with the terms of the contract and performed all the conditions thereof, the substantial rights of defendant were not prejudiced by the ruling, without which this court should not reverse the judgment. (Code Civ. Proc., sec. 475; Const., art. VI, see. 4½.) The issue presented to the court for trial was whether or not plaintiffs in constructing the reservoir had complied with the contract, since if they had, the withholding of the certificate as evidence thereof was unwarranted and want thereof could not be urged as a defense to plaintiffs’ right to recover.

Appellant attacks the finding of the court to the effect that, notwithstanding the fact that five items called for by the specifications of the aggregate cost of $62.85 (which the court held to be trivial and an allowance for which was made), were omitted, the reservoir was substantially completed on November 8, 1912, and on November 9th it was occupied and thereafter continually used by Firth. Section 1187 of the Code of Civil Procedure, provides that trivial imperfections in the construction of a building, improvement, or structure shall not be deemed such á lack of completion as to prevent the filing of a lien; and in Schindler v. Green, 149 Cal. 752, [87 Pac. 626], it is said: “If the omission or imperfection is so slight that it cannot be regarded as an integral or substantive part of the original contract, and the other party can be compensated therefor by a recoupment for damages, the contractor does not lose his right of action.” The question is one of fact to be determined by the trial court in each instance from the evidence and circumstances in the case. Compared with the entire structure called for by the contract, it cannot be said upon the evidence presented by the record that these items were other than as found by the court to be trivial omissions for which defendant could be and was compensated in damages. To the same effect are: Harlan v. *190 Stufflebeem, 87 Cal. 508, [25 Pac. 686], and Perry v. Quackenbush, 105 Cal. 299, [38 Pac. 740], It is also claimed that the reservoir was defective in that it was not impervious to water, but constantly leaked; that the roof thereon constructed by plaintiffs was defectively constructed, by reason of which fact a large part thereof was blown off by the wind some time in December. It appears from the record that at the trial not only the specifications, but detail plans for the construction of the roof were offered in evidence. These plans and details of construction, however, are not brought up in the record, and without them some of the specifications are incomplete. The contention of respondents is that not only the walls of the reservoir, but the roof constructed thereon, were in strict accordance with the plans and specifications, and there is evidence disclosed by the record which clearly tends to sustain such contention. That the walls of the reservoir were not impervious to water, is conceded; but the evidence of experts introduced on behalf of plaintiffs is to the effect that such leakage was due, not to faulty construction, but to the fact that the walls of the reservoir as called for by the specifications were not such as were calculated to render the reservoir impervious to water without the interior thereof being plastered, and that no reservoir built in accordance with the specifications furnished by defendant’s engineer would hold water without more or less leakage. That the evidence sustains this contention admits of no doubt. The same observations are true with reference to the alleged defective construction of the roof, which it seems did not blow off until after the completion of the structure and use thereof by defendant. The evidence tends to show that it was constructed in accordance with the detailed plans, not before us, and specifications furnished therefor by defendant’s engineer, and that its failure to withstand the force of the wind was due to faulty specifications which did not provide for proper anchorage, and not to failure on the part of the contractors to construct the same in accordance therewith. One of the omissions claimed to exist was the alleged fact that plaintiffs did not install check-valves in accordance with specifications. The specifications refer to detail No. 1 for method of outlet and inlet, and while this detail of plan is not incorporated in the record, we gather from the opinion of the trial judge it described the device as “a 10-inch check-valve or flap-valve.” *191 At all events, plaintiffs called upon the engineer for a design of valve to be used, and he drew a sketch and delineation of a valve the use of which he authorized and in accordance with which plaintiffs had the two valves made and installed the same. These valves, by reason of the leather cushion becoming hard and dry, though constructed as required by the engineer, leaked. But here, again, in the absence of any specifications therefor, plaintiffs appear to have followed the detailed drawing furnished them by the engineer, and having done so, they should not be held responsible for such defect.

Appellant strenuously contends that the evidence was insufficient to justify the finding that the owner occupied and used the reservoir from November 9, 1912.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
164 P.2d 807, 164 P. 807, 33 Cal. App. 187, 1917 Cal. App. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simmons-v-firth-calctapp-1917.