Schindler v. Green

87 P. 626, 149 Cal. 752, 1906 Cal. LEXIS 303
CourtCalifornia Supreme Court
DecidedOctober 1, 1906
DocketSac. No. 1260.
StatusPublished
Cited by6 cases

This text of 87 P. 626 (Schindler v. Green) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schindler v. Green, 87 P. 626, 149 Cal. 752, 1906 Cal. LEXIS 303 (Cal. 1906).

Opinion

*753 LORIGAN, J.

This action is brought by an original contractor against defendants as owners of a lot in the city of Sacramento, to foreclose a mechanics’ lien. A written contract was made by plaintiff with Annie and Maggie Green, daughters of defendants in the action, who lived on the premises with their parents, said defendants, to do the carpenter-work in making alterations and adding two rooms to the house in which defendants lived. The plastering of the rooms was to be done by another person, under a separate contract, with which plaintiff had nothing to do. There were no regular plans or specifications as to where the doors or windows in the rooms should be placed, the contract providing generally that there should be not to exceed six doors and not to exceed ten windows, and that the new addition should be built uniformly. The contract price was $403.50 for all materials and carpenter-work, of which plaintiff was paid one hundred dollars during the progress of the work.

Defendants refusing payment after the plaintiff claimed his contract was completed, the latter filed a lien on the premises, and in due time brought this action to foreclose it in the amount of $326.50; the twenty-three dollars over the unpaid contract price of $303.50 being claimed for extra work and material furnished beyond that provided for in the written contract.

At the trial plaintiff had judgment as prayed for, and this appeal is taken by defendants from the judgment and from an order denying their motion for a new trial.

There are many specifications of error in the transcript relative to the admission of evidence. We have given all of them careful consideration, and do not think any of them are well taken, or that particular reference to them is required.

Aside from such alleged errors,. the main point made by appellants for a reversal is as to the sufficiency of the evidence to sustain a finding of the lower court relative to two windows placed in the basement story of the house as built by plaintiff and the effect of such finding.

The court found as to the windows, ‘ ‘ That the two windows placed by plaintiff in the front portion of the basement story of said house were not directly beneath the two front windows of the upper portion of said house, which upper portion consisted of the old house after the same had been *754 raised, and that the placing of such windows in this manner was not workmanlike; and the court finds that the failure of plaintiff to place said windows in the basement in a direct line underneath the two windows of the upper portion of said house is a trivial imperfection.”

The only complaint made relative to the two windows so referred to was that they were not in alignment with the two front windows in the upper story. No other defect relative to them was complained of. This was what the lower court found to be a trivial imperfection, and, relative to it, further found that after the work had been completed' by plaintiff defendants caused the position of said two front windows to be changed, and had said windows placed directly underneath the two windows in the upper portion of said, house, for which they paid the sum of seven dollars and fifty cents, which the court finds was a reasonable amount to allow the defendants for making such change, and which it deducted from the amount for which the plaintiff sued.

It is insisted by appellants that the evidence does not support that portion of the finding that the failure of plaintiff to place said windows in a direct line with the windows in the upper portion of the house was a trivial imperfection. We do not think this point is well taken. In the last clause of section 1187 of the Code of Civil Procedure it is provided that any trivial imperfection in the work shall not prevent a lien. Whether an imperfection in the work for which a lien is sought is a trivial one or not is to be determined from the facts and circumstances of each particular case. No fixed or inflexible rule upon the point can be laid down. Upon this subject it is said in Bianchi v. Hughes, 124 Cal. 27, [56 Pac. 610]: “ ‘Trivial imperfection,’ as used in the code, relates to the question whether or not there has been an actual completion of the building. (Marble Lime Co. v. Lordsburg Hotel Co., 96 Cal. 332, [31 Pac. 164].) ‘What constitutes a “trivial imperfection” is a question of fact in each instance’ (Willamette etc. Co. v. Los Angeles College Co., 94 Cal. 229, [29 Pac. 629]); and the decision of the trial court thereon cannot be disregarded, unless the party complaining makes it clearly appear to be without any evidence in its support. (Harlan v. Stufflebeem, 87 Cal. 508, [25 Pac. 686].) The ‘trivial imperfections’ mentioned in the above *755 section (sec. 1187, Code Civ. Proc.) refer to imperfect or defective performance of the work upon a building which is claimed to have been'completed, and not to a case in which the building is admittedly uncompleted, and workmen are still engaged in constructing substantial portions thereof.” (See Santa Monica etc. Co. v. Hege, 119 Cal. 376, [51 Pac. 555].)

And in Harlan v. Stufflebeem, 87 Cal. 511, [25 Pac. 687]: “The performance of a contract need not in all cases be literal and exact, in order to entitle a party to compensation therefor. Especially is this the rule in contracts for labor by mechanics or artisans, where the quality of the work done, or the manner of its performance, is the sole matter in dispute, and is to be decided upon conflicting testimony. In contracts for the construction or repair of buildings, a substantial performance of his contract is sufficient to entitle the contractor to compensation for the work done by him under the contract. If there has been no willful departure from its provisions, and no omission of any of its essential parts, and the contractor has in good faith performed all of its substantive terms, he will not be held to have forfeited his right to a recovery by reason of trivial defects or imperfections in the work performed. If the omission or imperfection is so slight that it cannot be regarded as an integral or substantive part of the original contract, and the other party can be compensated therefor by a recoupment for damages, the contractor does not lose his right of action. . . . Whether the contract has been substantially performed is a question of fact which must be determined by the trial court in each instance from the facts and circumstances in that case, and the finding of the trial court upon that point is as conclusive as is its finding of any other fact.”

Now, applying these rules to the matter under review. It is not contended that the plaintiff omitted to put in any windows, which he agreed to place in the basement story, but only that they were placed some inches out of alignment with the windows in the upper story. The court found that this was unworkmanlike.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conrad v. Foerst
201 P. 795 (California Court of Appeal, 1921)
Hammond Lumber Co. v. Yeager
197 P. 111 (California Supreme Court, 1921)
Mott v. Wright
184 P. 517 (California Court of Appeal, 1919)
Simmons v. Firth
164 P.2d 807 (California Court of Appeal, 1917)
Seebach v. Kuhn
99 P. 723 (California Court of Appeal, 1908)
Hill v. Clark
95 P. 382 (California Court of Appeal, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
87 P. 626, 149 Cal. 752, 1906 Cal. LEXIS 303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schindler-v-green-cal-1906.