Coplew v. Durand

95 P. 38, 153 Cal. 278, 1908 Cal. LEXIS 453
California Supreme Court·Decided March 24, 1908·No. L.A. No. 1999.·Published·Cited by 11 cases

Opinion

HENSHAW, J.

Plaintiff had entered into a contract with defendants to do the painting, polishing, enameling—in short the “finishing” of the woodwork and floors of defendants’ house. By the terms of the contract, progress payments were to be made, seventy-five per cent of the contract price to be paid on completion, and twenty-five per cent thirty-six days after final completion. The progress payments were made as in the contract provided, and this action is brought to recover the twenty-five per cent final payment which defendants refused to make.

*279 The contract provided that the work was to be “strictly first class and to be done to the entire satisfaction of the owner and the architect”; as to the payments, “that in each of said cases a certificate be obtained and signed by the said architect.” Defendants’ refusal to pay was based upon the declaration of the architect that the work was not first class and was not done to his satisfaction.

Where work is to be done to the satisfaction of a person, evidenced by a certificate to that effect, the production of such a certificate is a condition precedent to a right of action upon the contract. This proposition is too well established to be questioned, and indeed is not questioned in this case. (Holmes v. Richet, 56 Cal. 307, [38 Am. Rep. 54] ; Loup v. California etc. Co., 63 Cal. 97 ; Cox v. McLaughlin, 63 Cal. 196 ; Tally v. Parsons, 131 Cal. 516, [63 Pac. 833] ; Kihlberg v. United States, 97 U. S. 398 ; Wangler v. Smith, 90 N. Y. 38, 9 Cyc. 618.)

To make his case, in the absence of such certificate, the contractor pleaded and the court found that the work was done to the entire satisfaction of the owner and the architect, and that the refusal to issue the completion certificate was wrongful and was due to plaintiff’s refusal to do certain repair work which was not required of him.by the contract.

The evidence, while conflicting, established to the satisfaction of the trial court the following facts: Under the terms of the contract plaintiff was to be paid $2165. The -work consisted of the finishing of the woodwork of the doors .and walls and the finishing of the hardwood floors. The hardwood floors were naturally the last woodwork to be put in place and the last to be finished by the contractor. The •contractor proceeded with his work upon the doors and walls, receiving partial payments. In the early part of August he had completed all this work and nothing remained for him to do under his contract but to finish the floors, which were not as yet ready for him. The architect .asked the plaintiff what would be the value of the work which he had yet to do upon the floors and plaintiff replied, .about two hundred dollars. The architect then stated that he would allow him the full seventy-five per cent of the confract price, deducting the value of the separate work yet fo be done upon the floors, and did so, the architect himself *280 testifying that he knew that' he had paid precisely seventy-five per cent of the entire contract price, excepting two-hundred dollars, the cost or the value of the work upon, the floors. It is in evidence on behalf of the plaintiff that at the time of the completion of all this woodwork, excepting the-floors, the architect and owner both expressed themselves, satisfied with it.

This condition of affairs obtained from August 8, 1904,. when the last payment amounting to seventy-five per cent was made, until January 22, 1905, when plaintiff finally-completed the work upon the floors. The delay was through, no fault of his. Meantime, decorators had been called in. and in doing their work they had injured the work done by-plaintiff. This is not disputed, and a separate contract was; entered into by defendants with plaintiff to repair the-damage so occasioned by the decorators. This work, in turn, he did to the apparent satisfaction of the defendants. At least he was paid in full therefor. It is not satisfactorily explained why at this time he should have been employed at a special price to do this repair work if, as. defendants’ architect contends, he was at that time insisting that the original work was incomplete, unsatisfactory,, and poor. The floors were clone by plaintiff, as the court: finds, in a satisfactory and workmanlike manner. Then when in due course plaintiff demanded his final payment,, the architect refused to give him a final certificate, stating that the woodwork had been damaged by water, panels and joists were cracked and would have to be replaced, and that he looked to the plaintiff to finish these damaged panels and joists,- to which plaintiff replied that he could' not be expected to do the work twice when he was paid but. once for it. In fact it was necessary to replace panels to-the number of about sixty, and those panels in turn had to-be “finished.”

Free access — add to your briefcase to read the full text and ask questions with AI

Coplew v. Durand, 95 P. 38, 153 Cal. 278, 1908 Cal. LEXIS 453 (Cal. 1908).

95 P. 38 (Coplew v. Durand) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

No.
Colorado Attorney General Reports, 1975
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
McSherry v. the Market Corporation
18 P.2d 776 (California Court of Appeal, 1933)
Barris v. Atlas Rock Co.
5 P.2d 670 (California Court of Appeal, 1931)
Tiffany v. Pacific Sewer Pipe Co.
182 P. 428 (California Supreme Court, 1919)
Roebling Construction Co. v. Doe Estate Co.
165 P.2d 547 (California Court of Appeal, 1917)
Simmons v. Firth
164 P.2d 807 (California Court of Appeal, 1917)
Ahlgren v. Walsh
158 P. 748 (California Supreme Court, 1916)
Connell v. Higgins
150 P. 769 (California Supreme Court, 1915)
Norman v. Hall
136 P. 720 (California Court of Appeal, 1913)
American-Hawaiian Engineering & Construction Co. v. Butler
133 P. 280 (California Supreme Court, 1913)