American-Hawaiian Engineering & Construction Co. v. Butler

133 P. 280, 165 Cal. 497, 1913 Cal. LEXIS 450
CourtCalifornia Supreme Court
DecidedMay 28, 1913
DocketS.F. No. 5888.
StatusPublished
Cited by48 cases

This text of 133 P. 280 (American-Hawaiian Engineering & Construction Co. v. Butler) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American-Hawaiian Engineering & Construction Co. v. Butler, 133 P. 280, 165 Cal. 497, 1913 Cal. LEXIS 450 (Cal. 1913).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 499

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 500

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 501

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 502 The defendant Butler, appeals from the judgment and from an order denying her motion for a new trial. The following statement of the case and discussion of the first question presented are taken from the opinion prepared by Mr. Justice Henshaw, upon which the case was decided in department:

"Plaintiff's complaint is in the form of a common count for the value of labor and material furnished defendant. Defendant's answer is by denial, by certain affirmative defenses and by counterclaim. To the end that complete equity might be done, the court ordered the respondent, the Western Expanded Metal and Fireproofing Company, a corporation, and a subcontractor of plaintiff, to be brought in. This was done under a cross-complaint filed by defendant. The purpose of so bringing in the Metal and Fireproofing Company was that there might be made by the court an apportionment to it of such share of the judgment awarded to the plaintiff as might be just, so that the defendant might not be subjected to further litigation and perhaps compelled to pay a double judgment. The judgment was in favor of plaintiff in the sum *Page 503 of $67,326.43, of which the Metal and Fireproofing Company, as a subcontractor, was awarded $21,373.68.

"The plaintiff had been engaged in the construction of a building for defendant under a written contract. Defendant, contending that plaintiff had violated the terms of the contract, completed the building at her own expense, and her counterclaim is composed of the items of liquidated damages, of the excess which she was obliged to pay for the completion of plaintiff's contract over and above the contract price and of lost rents. The contractor, upon the other hand, insists that defendant first breached the contract, and that by reason of this breach he was justified in rescinding, as in fact he did rescind, and therefore is entitled to recover in his action of quantum meruit andvalebat the value of the labor and material which he had bestowed upon and placed in defendant's building. This, in skeleton form, presents the general controversy between the parties. As one of the specific defenses, defendant set up the contract, pleaded the failure and neglect of plaintiff for more than the period of two years to supply the sufficiency of workmen and material and a failure to prosecute the work with promptness and diligence, pleaded the certificate of the architect authorizing the defendant to terminate the employment of plaintiff, and that accordingly `on or about the 12th of September, 1907, the defendant terminated the employment of the plaintiff as mentioned in said notice, and attempted by her agents and servants to enter upon the premises'; that the entry of her agents and servants was resisted and `thereafter, on or about the fourteenth day of September, A.D. 1907, the defendant, because of such resistance and because of the continued failure and neglect of the plaintiff to supply a sufficient number of workmen and of materials, and the continued failure of the plaintiff to prosecute the work, wholly terminated the employment of the plaintiff for the said work provided in the said contract, and thereafter, on or about the seventeenth day of September, A.D. 1907, the plaintiff quit work on the said building and left the said building in an unfinished condition,'

"The contract between these parties is in the form approved by the Architects' Association and is in general use throughout the United States and Canada. The terms of this contract *Page 504 pertinent to the questions under consideration are the following:

"By paragraph one the contractor agreed that it would `well and sufficiently perform and finish, under the direction and to the satisfaction' of the architects all work agreed by the contractor to be performed by it.

"By paragraph seven time is declared to be of the essence of the contract.

"By paragraph eight the contractor agreed to prosecute the work with diligence and to complete it according to the plans on or before September 1, 1906. The contractor agreed to pay $200 a day as liquidated damages for every day after the date fixed for completion on which the contract stood uncompleted.

"By paragraph ten provision is made for extending the time for the completion of the contract when delay was caused by the owner or by the act of God but extensions were not to be recognized unless a claim were presented in writing by the contractor at the time of the delay whereupon the architects were to ascertain and certify the amount of additional time to be allowed.

"Paragraph sixteen is as follows: `Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements on his part herein contained, such refusal, neglect or failure being certified by the architects, the owner shall be at liberty, after three days' written notice to the contractor, to provide any such labor and materials, and to deduct the costs thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architects shall certify that such refusal, neglect or failure is sufficient grounds for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work and enter upon the premises and take possession of all materials thereon, and to employ any other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor, he shall not be entitled to receive any further payment under this contract until the said work shall be wholly *Page 505 finished at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor, but if such expense shall exceed the unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner, as herein provided, either for furnishing materials or for finishing the work and any damage incurred through such default shall be audited and certified by the architects.'

"By paragraph seventeen payments of monthly installments were to be made to the contractor. These payments were to be seventy-five per cent of the value of the workmanship and materials incorporated by the contractor in the building during the previous month. No progress payments were to be made until the architects certified in writing that all the work upon the performance of which the payment is to become due had been done to their satisfaction, and until satisfactory evidence was produced that the premises were free from liens and claims chargeable to defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Plainfield v. Paden Engineering Co.
943 N.E.2d 904 (Indiana Court of Appeals, 2011)
MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
M & W Masonry Construction, Inc. v. Head
562 P.2d 957 (Court of Civil Appeals of Oklahoma, 1977)
n.sidney Nyhus v. Travel Management Corporation
466 F.2d 440 (D.C. Circuit, 1972)
Call v. Alcan Pacific Co.
251 Cal. App. 2d 442 (California Court of Appeal, 1967)
MacOmber v. State of California
250 Cal. App. 2d 391 (California Court of Appeal, 1967)
Integrated, Inc. v. Alec Fergusson Electrical Contractor
250 Cal. App. 2d 287 (California Court of Appeal, 1967)
A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)
C. J. Wood, Inc. v. Sequoia Union High School District
199 Cal. App. 2d 433 (California Court of Appeal, 1962)
London Guarantee & Accident Co. v. Las Lomitas School District
191 Cal. App. 2d 423 (California Court of Appeal, 1961)
Lucas v. Quigley Motor Co.
191 Cal. App. 2d 152 (California Court of Appeal, 1961)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Wilson v. Wilson
352 P.2d 725 (California Supreme Court, 1960)
Powell v. Cannon
260 P.2d 202 (California Court of Appeal, 1953)
Oden Const. Co. v. HELTON
65 So. 2d 442 (Mississippi Supreme Court, 1953)
Chin Ott Wong v. Title Insurance & Trust Co.
200 P.2d 541 (California Court of Appeal, 1948)
Kinkle v. Fruit Growers Supply Co.
146 P.2d 8 (California Court of Appeal, 1944)
Consolidated Engineering Co. v. United States
35 F. Supp. 980 (W.D. Washington, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
133 P. 280, 165 Cal. 497, 1913 Cal. LEXIS 450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-hawaiian-engineering-construction-co-v-butler-cal-1913.