O'Keefe v. Corporation of St. Francis's Church

22 A. 325, 59 Conn. 551, 1890 Conn. LEXIS 54
CourtSupreme Court of Connecticut
DecidedDecember 15, 1890
StatusPublished
Cited by35 cases

This text of 22 A. 325 (O'Keefe v. Corporation of St. Francis's Church) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Keefe v. Corporation of St. Francis's Church, 22 A. 325, 59 Conn. 551, 1890 Conn. LEXIS 54 (Colo. 1890).

Opinion

Carpenter, J.

This is an action to recover for materials furnished and labor performed in the construction of a church edifice. The complaint contains only the common counts.

The first defense is a denial of the allegations in the complaint. The second sets up a written contract under which the labor and materials were furnished. The third alleges a disagreement of the parties as to extra compensation, a submission of that matter to the arbitrament of the architect, and an award by him that the plaintiff was not entitled to compensation for extras, etc. The fourth defense is that [555]*555under the contract the plaintiff is liable to a forfeiture of twenty-five dollars per day for three hundred and fifteen days, in- consequence of a failure to complete the contract within the time stipulated. The fifth is that the defendant paid to the plaintiff over forty-six thousand dollars. The sixth sets up the payment of over three thousand dollars to one Patrick Maher, a sub-contractor, for labor performed by him. The seventh alleges that the plaintiff neglected certain work, etc., and that by direction of the architect the defendant caused said work to be done at an expense of over two thousand dollars.

The plaintiff replied to the answer in substance as follows :—To the second, fourth and seventh defenses, that the contract therein referred to had been abandoned; the third defense was denied; the fifth was denied except as admitted by the credits given ; and all the paragraphs of the sixth defense were denied. The defendant denied all the allegations in the plaintiff’s replication.

The case was tried to the jury, and a verdict rendered for the plaintiff. The defendant has appealed.

The first reason of appeal is “ that the court erred in admitting parol evidence to prove that the excavations for the foundation walls were made deeper than shown on the plans, and that changes were made in the foundation, for the purpose of showing that the written contract had been rescinded or abandoned.”

For the purpose of proving that the contract was abandoned by the parties, the plaintiff relied upon the acts and conduct of the parties subsequent to the execution of the contract and during the progress of the work, and upon the circumstances under which the work was done ; and during the trial he offered a variety of evidence touching such acts, conduct and circumstances. Included in the evidence so offered was evidence that various changes were made in the plan and construction of the building from that contemplated by the contract, and of how those changes were ordered. Such evidence was objected to by the defendant and admitted by the court.

[556]*556The evidence so objected to and received was—1st. That the foundation walls were carried to a much greater deptli than intended in the original plan or called for in the specifications and contract; that they were so carried under directions from the authorized agent of the defendant, and under a promise by him to pay therefor.—2d. That granite instead of brick was used for building the basement walls.—3d. That granite instead of brown stone trimmings was used throughout the building.—4th. That North Haven brick instead of Springfield brick was used in the construction of the walls.—5th. That slate instead of galvanized iron was used upon portions of the roof.

The objection to this evidence was that the contract provided for changes and extras, and therefore that it did not tend to prove an abandonment of the contract. As to the foundation walls there was a further objection, namely, that the contract itself required that the foundations should be dug down until a proper and suitable bed should be reached; so that what was done in that respect was strictly in performance of the contract, notwithstanding the direction of the agent and an express promise by him to pay. Among the requirements of the contract relative to alterations and extra work are the following:—“ The architect may require any alterations in the work shown or described in the drawings or specifications, and in every such case the price hereby agreed to be paid for the said work shall be increased or diminished as the case may require, according to a fair and reasonable valuation of the work added or omitted.”—“ The contractor shall make no claim for extra work unless the same shall be done in pursuance of a written order from the architect, and all such claims shall be made to the architect in writing, before the next ensuing payment, or shall be considered abandoned by the contractor.”

Clearly the performance of a contract according to its terms is no evidence that the contract was abandoned; on the contrary it is cogent evidence that it was not abandoned. If therefore the defendant could have shown such a performance it would have put an end to this contention of the-[557]*557plaintiff; and this is true of deviations from the contract, if such deviations are provided for and made in the manner prescribed. It was therefore incumbent on the plaintiff, in order to make such evidence available, to show not only that the contract was departed from, but also that the contract was not followed in making such departure. Strictly speaking, the first step in the proof was to show the deviation, and the next to show that it was not under the contract. The first was admissible as a preliminary step, or as laying the foundation for the second. If, under the second branch there was any evidence for the jury to consider, the plaintiff was entitled to the first, and the evidence was properly received.

There were several particulars in which it was claimed that the contract had been departed from. The number of such variations was a circumstance which the jury might properly consider. If changes were made in the plan of specifications with respect to the material used, or the style and quality of the work, without taking the steps pointed out in the contract, as there were in some instances, the manner of making such changes was some evidence that the parties did not regard the contract as still in force. Numerous instances are referred to in the supplemental finding. It is there found that evidence was offered by the plaintiff to show that all the various alterations in the building were made without any requirement therefor from the architect as provided in paragraph five of the contract, but by the parties, and at the request of the defendant; that the parties never recognized the written order of the architect as a basis of a claim for extra work as specified in paragraph fourteen of the contract, but wholly ignored this requirement from first to last; that the parties wholly disregarded the provision of paragraph fourteen that no claim for extra work would be recognized unless made to the architect in writing before the next ensuing payment; that the parties ignored the provision in the contract as to date and penalty for completion, as provided in paragraph eleven of the contract, and the provisions of paragraph twelve as to the mode of obtaining [558]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Menard, Inc. v. DiPaolo Indus. Dev., L.L.C.
2023 Ohio 1188 (Ohio Court of Appeals, 2023)
Karas v. Liberty Ins. Corp.
335 Conn. 62 (Supreme Court of Connecticut, 2019)
State v. Brelsford
587 A.2d 1062 (Connecticut Appellate Court, 1991)
In re Manuel R.
543 A.2d 719 (Supreme Court of Connecticut, 1988)
Frantz v. Van Gunten
521 N.E.2d 506 (Ohio Court of Appeals, 1987)
In re Juvenile Appeal (1983-3)
39 Conn. Supp. 400 (Connecticut Superior Court, 1983)
Gordon v. Indusco Management Corp.
320 A.2d 811 (Supreme Court of Connecticut, 1973)
Clark v. Hughes
97 A.2d 114 (Supreme Court of Connecticut, 1953)
Iowa Electric Light & Power Co. v. Hopp
866 N.W. 512 (Supreme Court of Iowa, 1936)
Bjerkeseth v. Lysnes
22 P.2d 660 (Washington Supreme Court, 1933)
Ault v. Shepherd
8 La. App. 595 (Louisiana Court of Appeal, 1928)
Spaulding v. American Realty Co.
118 A. 322 (Supreme Judicial Court of Maine, 1922)
F. B. Fountain Co. v. Stein
118 A. 47 (Supreme Court of Connecticut, 1922)
Douglass & Varnum v. Village of Morrisville
95 A. 810 (Supreme Court of Vermont, 1915)
American-Hawaiian Engineering & Construction Co. v. Butler
133 P. 280 (California Supreme Court, 1913)
Expanded Metal Fire-Proofing Co. v. Noel Construction Co.
87 Ohio St. (N.S.) 428 (Ohio Supreme Court, 1913)
Headley v. Cavileer
82 A. 908 (Supreme Court of New Jersey, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
22 A. 325, 59 Conn. 551, 1890 Conn. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/okeefe-v-corporation-of-st-franciss-church-conn-1890.