Expanded Metal Fire-Proofing Co. v. Noel Construction Co.

87 Ohio St. (N.S.) 428
CourtOhio Supreme Court
DecidedFebruary 25, 1913
DocketNo. 12907
StatusPublished

This text of 87 Ohio St. (N.S.) 428 (Expanded Metal Fire-Proofing Co. v. Noel Construction Co.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Expanded Metal Fire-Proofing Co. v. Noel Construction Co., 87 Ohio St. (N.S.) 428 (Ohio 1913).

Opinion

Johnson, J.

The circuit court, in entering its judgment, deducted from the judgment of the common pleas seven items for extras, which amounted, with interest thereon, to the sum of $20,376.36, and affirmed the balance of the judgment,- amounting to $21,506.10. It found that the common pleas court erred in its construction of Clause 6 of the contract between the Noel Company and the Expanded Company, and in charging the jury “that for the making of -the changes provided for in said sixth clause of the [432]*432contract between the Noel Company and the Expanded Metal Fire-Proofing Company, no written order or orders were required.” Clause 6 is as follows:

“The party of the second part further agrees that in the event of any changes being made by the architect or owner in the plans and specifications, affecting any of the work or materials herein agreed to be done, furnished and set in place, such changes shall be assented to and executed by the party of the second part, upon condition that party of the first part shall pay for same at the fair market price, if said changes add to the cost of the work, and if such changes decrease the cost of the work, a proportionate allowance shall be made to the party of the first part, without in any way invalidating, changing or avoiding this contract, and if such changes cause delay to the party of the second part, additional time to be extended by party of the first in which to perform the work.”

The preamble of the contract recites that the Noel Company had entered into a contract with the Cash Register Company for the construction of the building referred to, and provided “the said contract, together with the plans, drawings and specifications therein referred to, are made part hereof to the same extent as if herein fully written.”

In the third clause of the Cash Register contract with the Noel Company, it is provided as follows:

[433]*433“No alterations shall be made in said specifications or drawing's nor shall there be any deviation in the doing of the work or furnishing the material covered by this contract from the manner, character or quality designated and required by said drawings and specifications, unless such alterations or deviations be authorized or required upon the written order of said engineer of works, the extra amount to be paid by said owner or the credit to be allowed by said contractor on account of said alterations or deviations being stated therein. But should the owner and contractor not be able to agree as to such amount to be paid or allowed, the work shall go on under the order provided for, and the determination of said amount shall be referred for arbitration as provided for in paragraph fourteen (14) of this contract.”

The contention, substantially, of the Expanded Company is that, inasmuch as the sixth clause of its contract with the Noel Company does not specifically require that the changes provided for in said cause shall be ordered in writing, no such written order was necessary. That the provision in the preamble, that the Cash Register contract, with its plans, drawings and specifications, are made part of the Expanded Metal Company contract • cannot control in the matter of the extras, because the specific provision in the Expanded Company contract for extras is inconsistent with the provision in the Cash Register contract with reference thereto. That in such case, the actual contract between the parties must prevail.

[434]*434Under the sweeping provision that the entire Cash Register contract, with its plans, drawings and specifications, are made a part of the Expanded Metal Company contract, the former became part and parcel of the latter agreement, in so far as their provisions are consistent. No provision of a contract is to be disregarded as inconsistent with other provisions unless no other reasonable construction is possible. A special provision will be held to override a general provision only where the two cannot stand together.

It is clear that the purpose of Clause 6 of the sub-contract was to require the sub-contractor to “assent to and execute” the changes ordered by the owner, and to provide a plan by which the sub-contractor should be paid for the making of such changes. The principal contract provided for the fixing of the amount to be paid by the owner to the principal contractor for extras, and, in as much as the sub-contractor was not a party to such arrangement, it would not be fair to compel him to be bound by the price so fixed. Therefore, in justice to him, the provision was added that he should be paid the fair market price and should'not be subjected to claims for delay, if the changes caused delay. It must be noted that the Expanded Metal Company, in its contract, bound itself to “assent to and execute” any changes which the owner might make, but with knowledge that any such changes could be made by the owner only on a written order to the principal contractor, in which the amount to be [435]*435paid was provided for, thus protecting the interests of all concerned.

We think the “change being made by the owner,” referred to in Clause 6, and which the sub-contractor bound itself to assent to, is only such a change as the owner was entitled to make under its contract with the principal contractor, and which was made in writing in accordance therewith, the terms of which the sub-contractor had embodied in its own contract. Otherwise, the owner could order extras without reference to their value and without reference to the requirements of his contract with the principal contractor, and the sub-contractor could execute them and hold the principal contractor to payment for them without the former having been, in any way, a party to the arrangement. Clause 6 of the sub-contract is not inconsistent with Clause 3 of the principal contract, when the two are considered in view of the object each was to subserve.

A consideration of all of the provisions of the contract leads us to conclude that the parties intended that the owner could not order changes to which either the principal contractor or the subcontractor was bound to assent, or for which the sub-contractor would have a valid claim, unless the order was in writing, or unless this requirement was waived by the parties in some manner by which they were bound.

The circuit court found that the error of the common pleas, in construing the contract, affected [436]*436only the following items of extras, included in the verdict of the jury:

(3) For changes in corner columns, the sum of.................$ 327.60
(4) For extra steel in parapet walls in main building, the sum of.. 130.45
(5) For change in parapet walls of wings .................... 99.90
(6) For extra concrete parapet walls of wings................... 40.50
(7) For wrought iron pipes through the floor slabs.............. 980.00
(8) For tearing nine columns, first floor, and changing forms in connection with curtain walls. 4,000.00
(10) For extra rods in beams and extra size of beams......... 12,340.00

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norwood v. Lathrop
59 N.E. 650 (Massachusetts Supreme Judicial Court, 1901)
O'Keefe v. Corporation of St. Francis's Church
22 A. 325 (Supreme Court of Connecticut, 1890)
Campbell v. Kimball
127 N.W. 142 (Nebraska Supreme Court, 1910)
Board of Commissioners v. Gibson
63 N.E. 982 (Indiana Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
87 Ohio St. (N.S.) 428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/expanded-metal-fire-proofing-co-v-noel-construction-co-ohio-1913.