Tally v. Parsons

63 P. 833, 131 Cal. 516, 1901 Cal. LEXIS 1164
CourtCalifornia Supreme Court
DecidedFebruary 11, 1901
DocketL.A. No. 984.
StatusPublished
Cited by16 cases

This text of 63 P. 833 (Tally v. Parsons) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tally v. Parsons, 63 P. 833, 131 Cal. 516, 1901 Cal. LEXIS 1164 (Cal. 1901).

Opinion

COOPER, C.

This action was tried before the court, findings filed, and judgment entered for plaintiff. Appellant Gan-, ahl has appealed from the judgment on the judgment-roll. The only question necessary to be determined is as to whether the findings entitled the plaintiff to judgment against appellant. It appears from the findings that plaintiff’s assignor entered into a written contract with defendant Parsons, under the terms of which Parsons agreed to build a dwelling-house for said assignor upon the premises described in the complaint for the sum of two thousand three hundred and forty-four dollars to be paid in certain installments. The contract provided that in case the said Parsons should fail to prosecute the work with diligence, or in the performance of his agreement in any respect, the owner (plaintiff’s assignor) shall be at liberty to terminate the employment, enter upon the premises and complete the building. It further provided that in case of the failure of Parsons to complete the building according to the contract, the owner should have the right to employ any other person or persons to finish the work and provide the materials therefor, and contained the following clause: “The expense incurred by the owner as hereinbefore provided, either for furnishing materials or finishing the work, and any damage incurred through such default, shall be audited and certified by *518 the architects, whose certificate thereof shall be conclusive between the parties.” At the time of the execution of the contract the contractor executed and delivered to the owner his bond in the sum of eight hundred dollars, with appellant as one of the sureties thereon, conditioned that the contractor should faithfully perform all the terms and conditions of the contract and complete the building according to the plans and specifications, and when completed deliver the same up to the owner free from all liens. After the commencement of said building, and the payment of various amounts, the contractor, without any just cause, refused to complete the building and abandoned the contract. The owner thereupon took possession, employed men, purchased materials, completed the building, and necessarily expended in its completion, according to the plans and specifications, the sum of five hundred and thirteen dollars and thirty-three cents, over and above the contract price, for which sum plaintiff recovered judgment. The court found that the architects “never did audit and certify to the costs and expenses for materials and labor for the completion of said building by said Mary" A. Tally and that said architects: never did audit or certify to any or all of the expenses for the completion of said building.....That said architects were never called upon or asked by said Mary A. Tally, or by any other person, to audit and certify, or audit or certify, to the expenses for material and labor for the completion of said building.”

The court further found that, immediately after the abandonment of the contract by Parsons, the owner discharged the architects on the ground that they were careless, dishonest, and incompetent and never afterward employed them.

Appellant was surety for the faithful performance of the contract by Parsons. He was bound only by the express terms, of his contract, and to the extent, and in the manner, and under the circumstances, pointed out in his bond and the building contract to which it referred and no further. He was entitled to stand on its precise terms. (Pierce v. Whiting, 63 Cal. 543; Carter v. Mulrein, 83 Cal. 169. 1 ) It was a part of the terms and conditions of his contract that if the owner, by de *519 fault of the contractor, should he compelled to furnish labor and materials and finish the building, any damage incurred through such default should he audited and certified by the architects. This was a condition precedent and was inserted for the protection of the contractor and the sureties. Thn architects were named in the contract, and were the agents of both parties. The sureties agreed to the contract, as to the selection of the architects therein named. It was competent for the parties to agree that, in case of loss, expense, or damage to the owner, such loss should be audited by a tribunal of their own selection. They did make such agreement and selected such tribunal, and, unless some valid reason is shown, the auditing by such tribunal is a condition precedent to plaintiff’s recovery.

In Smith v. Briggs, 3 Denio, 73, the defendant had covenanted with the plaintiff for doing the carpenter work of certain houses and to pay him when he should receive from the architect his certificate that the work was fully and completely finished according to the specification annexed to the contract. It was held that giving the certificate by the architect was a condition precedent, the performance of which must be averred in an action brought to recover payment for such work.

In Smith v. Brady, 17 N. Y. 173, 2 the contractor was to he paid the balance “when all the work should he completed and certified by the architects to that effect.” It was held that the certificate was a condition precedent, and in the opinion it is said: “The parties have seen fit to make the production of such a certificate a condition precedent to the payment. The plaintiff is as much hound by this part of his contract as any other. It is not enough for him to bring his action and say that he has completed the work which he undertook to do. He has agreed that the architects named should decide whether the work is completed or not.” (See, also, Delaware etc. Canal Co. v. Pennsylvania Coal Co., 50 N. Y. 250; United States v. Robeson, 9 Pet. 328; Wolf v. Michaelis, 27 Ill. App. 336; De Mattos v. Jordan, 15 Wash. 378.) In the latter case the action was upon the bond of a contractor and is in many respects similar to the case at bar. The clause in the contract was: *520 “The expense incurred by the owner as herein provided either for furnishing materials or finishing the work shall be audited and certified by the architect and his certificate thereof shall be conclusive upon the parties.” In the opinion it is said: “We deem it proper to observe that appellant can, under the terms of the contract, only recover such of the expenses incurred by him for furnishing materials or finishing the work as shall have been audited and certified by the architect..... The purpose of this provision was to protect the sureties against excessive and Unjust charges for work and material, and it was agreed that the certificate of the architect should be conclusive as to the amount of expenses incurred hy the owner.”

This court has held that where a contract provides for the payment of such sum as may be determined by arbitrators, that the submission to arbitrators and procuring an award is a condition precedent to recovery. (Holmes v. Richet, 56 Cal. 307 3 ; Scammon v. Denio, 72 Cal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massachusetts Bonding & Insurance v. Osborne
233 Cal. App. 2d 648 (California Court of Appeal, 1965)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Patten & Davies Lumber Co. v. McConville
25 P.2d 429 (California Supreme Court, 1933)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Michelin Tire Co. v. Bentel
193 P. 770 (California Supreme Court, 1920)
Savannah Lighting Co. v. Fidelity & Deposit Co.
95 S.E. 113 (Court of Appeals of Georgia, 1918)
First Congregational Church of Christ v. Lowrey
165 P. 440 (California Supreme Court, 1917)
Collins Bros. v. Georgia Hotel Co.
83 S.E. 660 (Supreme Court of Georgia, 1914)
Shriner v. Craft
51 So. 884 (Supreme Court of Alabama, 1910)
Elmore & Womble v. Thaggard
61 S.E. 726 (Supreme Court of Georgia, 1908)
Coplew v. Durand
95 P. 38 (California Supreme Court, 1908)
Davisson v. East Whittier Land & Water Co.
96 P. 88 (California Supreme Court, 1908)
Tally v. Ganahl
90 P. 1049 (California Supreme Court, 1907)
Henry Smith & Sons v. Jewell
65 A. 6 (Court of Appeals of Maryland, 1906)
Huber v. St. Joseph's Hospital
83 P. 768 (Idaho Supreme Court, 1905)
County of Glenn v. Jones
80 P. 695 (California Supreme Court, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
63 P. 833, 131 Cal. 516, 1901 Cal. LEXIS 1164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tally-v-parsons-cal-1901.