Patten & Davies Lumber Co. v. McConville

25 P.2d 429, 219 Cal. 161, 1933 Cal. LEXIS 368
CourtCalifornia Supreme Court
DecidedOctober 3, 1933
DocketDocket No. L.A. 12476.
StatusPublished
Cited by23 cases

This text of 25 P.2d 429 (Patten & Davies Lumber Co. v. McConville) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patten & Davies Lumber Co. v. McConville, 25 P.2d 429, 219 Cal. 161, 1933 Cal. LEXIS 368 (Cal. 1933).

Opinion

CURTIS, J.

The following statement of facts is taken from the opinion rendered in this action by the District Court of Appeal:

“This is an action brought against the contractors and the surety on a bond furnished by them, to recover for materials used in the erection of an apartment house. The complaint alleged that materials of the value of $31,282.61 were furnished between May 1, 1927, and September 27, 1927, in pursuance of a contract between the plaintiff and the defendant contractors; that the defendant contractors agreed to pay for the same; that only the sum of $3,138.37 has been paid; and that the balance unpaid is $28,144.24. It was also alleged that the defendant surety company entered into a bond or undertaking conditioned for the payment of labor and material claims which by its terms was made to inure to the benefit of labor and material claimants. The defendant surety company answered, denying all of the allegations of the complaint which are material here, and setting up several separate defenses, including one to the effect that the bond had been issued in connection with a contract providing for the erection of a building upon certain terms, while the building had been erected under another and different contract, and upon completely changed terms. As another defense, it was alleged that the entire transaction had been fraudulent, that the owner and contractors after entering into one form of agreement had later pretended to enter into another form of agreement for the purpose of obtaining a bond from this defendant, and that, thereafter, they had returned to the original form of agreement and proceeded in accordance therewith, all without the knowledge or consent of this defendant.
*164 ‘ ‘Four findings were made by the trial court. In finding number one it was found that the contractors ordered the materials as alleged in the complaint and agreed to pay for the same; that they were furnished for and used in the construction of the building; that their agreed value was $31,282.61; and that the balance due and unpaid was $28,144.24. In number two it was found that the defendant surety company entered into an undertaking conditioned upon the payment by the defendant contractors for all materials used in the erection of said building, and that this undertaking was by its terms made to inure to the benefit of all persons furnishing such materials. Finding number three is to the effect that while the defendant contractors had delivered to the plaintiff their promissory note in the sum of $37,500, this note was not delivered nor accepted in payment for materials to be delivered and did not estop the plaintiff from recovering in this suit. In finding number four it was found that all of the allegations of the defendant surety company’s second, third and fourth separate defenses are untrue. Judgment was entered against the defendant contractors and against the defendant surety company, from which judgment both have appealed.”

The findings of the court having been in favor of ' the plaintiff, the evidence must be construed most strongly against the appellant and in favor of the respondent. All evidence tending to establish the correctness of the findings as made must be accepted as true and the prevailing party must be given the benefit of all inferences which might reasonably have been drawn by the trial court. Every substantial conflict in the evidence must, under the rule which has always prevailed in this court, be resolved in favor of the finding. (Bancroft-Whitney Co. v. McHugh, 166 Cal. 140, 142 [134 Pac. 1157].) Reviewing the evidence in the light of this well-established rule, the facts in this ease may be fairly stated as follows: S. E. Bancroft was the owner of a certain piece of real property upon which she desired to erect an apartment house, and throughout this transaction her husband, Dr. Bancroft, acted for her under a written power of attorney. The Bancrofts had previously had dealings with the defendants McConville and Perryman, who were contract builders, and they desired this firm to erect the apartment house which they then had decided to búild. *165 Some preliminary negotiations were had between the Ban-crofts and these contractors regarding the construction of said apartment house upon a cost plus basis. "While there may have been a vague understanding between the parties that the building might be constructed under such a contract, the trial court found upon evidence which we think was amply sufficient, that no such contract was at that time entered into between the Bancrofts and said contractors. While these parties had the matter of constructing said building under consideration, they called upon a Mr. Case-beer, a bond and insurance broker, to inquire regarding a contractor’s labor and material bond in connection with the construction of said building, and were informed by Mr. Casebeer that no such bond could be obtained where the building was constructed on a cost plus basis, and in order to obtain such a bond it would be necessary for them to enter into a contract for the construction of said building at a fixed price. This conference with Casebeer took place on March 5, 1927. A second meeting was held with him on March 7th or 8th, at which Dr. Bancroft and Mr. McConville were present. At this meeting Mr. Casebeer secured for them the information necessary for “the underwriting of the labor and material bond”, such as the money available for the construction of the building, the methods of payment and the incidental expenses. He asked Bancroft and McConville for the contract but it had not yet been drawn up. Later he was asked by them to prepare such a contract for the construction of the building, which they executed on March 10th. This was a straight builder’s contract for a specific price of $100,000. Casebeer then took up with the Globe Indemnity Company the application of McConville and Perryman for a labor and material bond, and the bond involved herein was on March 18th, issued by the Globe Indemnity Company and delivered by Casebeer to Patten & Davies Lumber Company, the plaintiff herein. Prior, however, to this last-named date, Dr. Bancroft and said contractors had approached the plaintiff regarding the furnishing of lumber and other building material for the construction of said building. The result of their negotiations with the plaintiff was that the plaintiff agreed to furnish said building materials to the extent of $37,500 upon the condition that the contractors would furnish a *166 labor and material bond which would guarantee payment of said materials and that plaintiff would be further secured by a promissory note in the sum of $37,500, executed by McConville and Perryman and Mrs. Bancroft and secured by an assignment of a promissory note for $60,000 executed by Dr. Bancroft and wife to McConville and Perryman and secured by a trust deed on said real property. There was a prior trust deed on said property given to secure the sum of $100,000. These terms were agreed to by the Bancrofts and MeConville and Perryman and in accordance with this agreement the labor and material bond, involved herein, was delivered to plaintiff, as stated above, on or about March 18, 1927. Later the $37,500 promissory note in favor of plaintiff was executed by said contractors and Mrs. Bancroft, and one Max Royer, and the $60,000 note in favor of said contractors and said trust deed to secure said last-named note were also executed by Dr. and Mrs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green v. Green
215 Cal. App. 2d 31 (California Court of Appeal, 1963)
Powers Regulator Co. v. Seaboard Surety Co. of New York
204 Cal. App. 2d 338 (California Court of Appeal, 1962)
Burke v. Chrostowski
296 P.2d 545 (California Supreme Court, 1956)
Clewett v. Clewett
289 P.2d 512 (California Court of Appeal, 1955)
Linehan v. Linehan
285 P.2d 326 (California Court of Appeal, 1955)
Carvalho v. McCoy
276 P.2d 21 (California Court of Appeal, 1954)
Epley v. Hiller
274 P.2d 696 (California Court of Appeal, 1954)
Wilkman v. Banks
269 P.2d 33 (California Court of Appeal, 1954)
Richards v. Plumbe
253 P.2d 126 (California Court of Appeal, 1953)
Hartzell v. Myall
252 P.2d 676 (California Court of Appeal, 1953)
Dodds v. Stellar
175 P.2d 607 (California Court of Appeal, 1946)
Markulics v. Maico Co., Inc.
168 P.2d 35 (California Court of Appeal, 1946)
Roselip v. Raisch
166 P.2d 340 (California Court of Appeal, 1946)
Wuest v. Wuest
164 P.2d 32 (California Court of Appeal, 1945)
Buckhantz v. R. G. Hamilton & Co.
163 P.2d 756 (California Court of Appeal, 1945)
People v. Sipper
142 P.2d 960 (California Court of Appeal, 1943)
Lentz v. Hartman
111 P.2d 404 (California Court of Appeal, 1941)
Bardeen v. Commander Oil Co.
104 P.2d 875 (California Court of Appeal, 1940)
Chronister v. Brennan
81 P.2d 479 (California Court of Appeal, 1938)
Boteler v. Conway
72 P.2d 208 (California Court of Appeal, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
25 P.2d 429, 219 Cal. 161, 1933 Cal. LEXIS 368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patten-davies-lumber-co-v-mcconville-cal-1933.