Hubbard v. Jurian

170 P. 1093, 35 Cal. App. 757, 1917 Cal. App. LEXIS 433
CourtCalifornia Court of Appeal
DecidedDecember 31, 1917
DocketCiv. No. 2150.
StatusPublished
Cited by18 cases

This text of 170 P. 1093 (Hubbard v. Jurian) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hubbard v. Jurian, 170 P. 1093, 35 Cal. App. 757, 1917 Cal. App. LEXIS 433 (Cal. Ct. App. 1917).

Opinions

These are consolidated actions for the foreclosure of several liens, claimed for labor and materials furnished in the erection and construction of a building upon the premises of the defendants Odell and Jurian.

The facts are as follows: On the twenty-third day of September, 1912, the defendants Odell and Jurian entered into a written contract with one H. A. Spreen for the erection by the latter of a one-story concrete building upon the premises of said defendants for the contract price of $5,260, payable in four installments, as follows: First payment of $1,315 when the first floor joists were in place and wall one-half story high; second payment of $1,315 when the plastering was completed on the inside; third installment of $1,315 thirty-five days after completion of the building. The contract further provided that the building should be constructed under the supervision of an architect, and payments made upon certificates from him.

In connection with this contract, a bond was executed by the contractor, Spreen, as principal, with the defendant Maryland Casualty Company as surety, in the sum of $2,630 (being one-half of the contract price), conditioned for the faithful performance of the contract on the part of the contractor, and for payment in full of claims for labor and materials furnished in the construction of the building, and further stipulating that if the act of the legislature of 1911, amending the lien laws, should be held invalid, then the bond should remain in full force and effect for the protection of the obligee.

This bond was attached to the contract and by its terms refers to and makes said contract a part thereof. Said contract and bond were duly filed on the 30th of September, 1912. Work was commenced under this contract about the middle of October, 1912.

On the tenth day of December, 1912, while said building was in course of construction, the defendants Odell and Jurian entered into a further contract with the contractor, Spreen, for the construction of a second story to be "added to the building [then] in course of construction." The contract price for this second story was three thousand six hundred dollars, payable in four equal installments of nine hundred dollars each as the work progressed. In connection with this contract a bond was executed by the contractor, Spreen, *Page 760 with the defendant Maryland Casualty Company as surety for the sum of one thousand eight hundred dollars (being one-half the contract price) and containing provisions substantially the same as the first bond. This supplemental contract and bond were filed in the office of the county recorder of Santa Clara County on the 26th of December, 1912.

It appeared from the evidence that the defendants, Odell and Jurian, paid, on November 25, 1912, the contractor the first installment of $1,315 called for by the original contract, and on February 26, 1913, the second installment of $1,315 called for by said contract. They paid the first installment of nine hundred dollars called for by the contract for the erection of the second story on or about the 30th of December, 1912.

All of these payments were made upon certificates of the architect to the effect that they were due and payable, and no contention is made on the part of the lien claimants as to the propriety of any of these payments, except as to the second payment of $1,315 upon the original contract on February 26, 1913, which payment the lien claimants contend, and the trial court found, "was prematurely made."

The court further found that on the first day of March, 1913, the contractor, Spreen, abandoned work upon the building and ceased labor thereon for more than thirty days thereafter. On April 21, 1913, the defendants Odell and Jurian began the work of completing the building and did complete it about the 16th of June, 1913, at an expenditure of $4,744.59, which the court found to be the reasonable cost of such completion. The court also found that there was extra work upon the building amounting to $362.60, thus making the amount of the contract price actually remaining in the hands of the owners, Odell and Jurian, including the amount due for extras, $948.01.

The court charged the account of said defendants with the $1,315 paid as the second installment upon the first contract, upon the theory that such payment had been prematurely made, and determined that the lien claimants were entitled to personal judgment against said Odell and Jurian in the sum of $2,263, with interest, "to be ratably distributed among them according to their respective claims."

The evidence showed, and the court found, that the several claims of lien involved in the consolidated actions were filed *Page 761 upon the dates following, viz.: The claim of O'Brien Lumber Co., June 25, 1913; the claim of Hubbard Carmichael, July 2, 1913 (embraced in the Hubbard action); the claims of G. J. Guth, Fred L. Peterson, Dudfield Lumber Co., and McDonald and Burke (embraced in the suit of G. J. Guth), April 1, 1913; the several claims involved in the suit of Walter G. Mathewson (Ayrer, Peterson, Graybill, Conti, Judson, McDaniel, and Taylor) were filed partly on the 28th and partly on the 29th of March, 1913; the claim of E. C. Power, July 19, 1913, and the claim of Charles C. Minton, July 23, 1913.

From the findings made the trial court deduced the conclusion of law that the several parties plaintiff were entitled to judgment foreclosing their respective claims of lien in the following amounts, viz.: T. B. Hubbard, $1,972.28; E. C. Power, $125; G. J. Guth, $627.55; W. G. Mathewson, $678.60; C. C. Minton, $337.90. It was further adjudged that the several parties plaintiff were entitled to interest upon their respective claims of lien from the tenth day of April, 1913.

Judgment was also entered against the defendant Maryland Casualty Company for the full amount of each and all of the claims with interest, which aggregated the sum of $2,522.27, and the judgment provided that the liens should be first satisfied to the extent of that sum by sale of the premises, and that execution should thereupon issue against the surety for the deficiency, if any, remaining.

The appeal is from the judgment and from the order denying motion for a new trial by the defendants Odell and Jurian, as owners, and the Maryland Casualty Company, as surety.

The contention made upon behalf of the owners, Odell and Jurian, that the judgment is against law in so far as it charges the owners, defendants Odell and Jurian, with the sum of $1,315 found to have been "prematurely" paid to the contractor in advance of the time stipulated therefor in the contract and after notice to withhold payment had been served upon the defendants, is based upon the fact that section 1184 of the Code of Civil Procedure does not now, as it did prior to its amendment in 1911 (Stats. 1911, p. 1315), expressly make it "the duty of the person who contracted with the contractor to . . . withhold from his contractor . . . sufficient money due, or that may become due to such contractor, *Page 762 to answer" the claim of any person and any lien that might be filed therefor for labor or material, or both, furnished to the contractor, when such claim was evidenced by a written notice to the owner showing the character and value of the material or labor furnished the contractor. Instead of making it the duty of the owner upon receipt of such notice to withhold a sufficient sum out of the money due or to become due to the contractor to satisfy the claim, the statute now provides that "upon such notice being given it shall be lawful

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Mountain View Savings & Loan Ass'n
238 Cal. App. 2d 644 (California Court of Appeal, 1965)
Greenblatt v. Goldin
94 So. 2d 355 (Supreme Court of Florida, 1957)
Stanislaus Lumber Co. v. Pike
124 P.2d 190 (California Court of Appeal, 1942)
Fontaine v. Storrie
45 P.2d 361 (California Court of Appeal, 1935)
Haupenthal v. Bert L. Perry, Inc.
31 P.2d 1088 (California Court of Appeal, 1934)
Patten & Davies Lumber Co. v. McConville
25 P.2d 429 (California Supreme Court, 1933)
San Mateo Planing Mill Co. v. Davenport Realty Co.
24 P.2d 787 (California Supreme Court, 1933)
Simpson v. Bergmann
13 P.2d 531 (California Court of Appeal, 1932)
Sudden Lumber Co. v. Singer
284 P. 477 (California Court of Appeal, 1930)
Western Brick Co. v. Smith
271 P. 356 (California Court of Appeal, 1928)
Pioneer Lumber Co. v. Binckley
2 Cal. Super. Ct. 78 (California Superior Court, 1926)
Dodd v. Maddox
238 P. 130 (California Court of Appeal, 1925)
Hubbard v. Jurian
190 P. 1052 (California Court of Appeal, 1920)
General Electric Co. v. American Bonding Co. of Baltimore
182 P. 444 (California Supreme Court, 1919)
Klimm v. Henry Cowell Lime & Cement Co.
175 P. 908 (California Court of Appeal, 1918)
Hornlein v. Bohlig
174 P. 697 (California Court of Appeal, 1918)
Crane Co. v. Maryland Casualty Co.
173 P. 494 (California Court of Appeal, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
170 P. 1093, 35 Cal. App. 757, 1917 Cal. App. LEXIS 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hubbard-v-jurian-calctapp-1917.