General Electric Co. v. American Bonding Co. of Baltimore

182 P. 444, 180 Cal. 675, 1919 Cal. LEXIS 540
CourtCalifornia Supreme Court
DecidedJuly 5, 1919
DocketL. A. No. 5781.
StatusPublished
Cited by15 cases

This text of 182 P. 444 (General Electric Co. v. American Bonding Co. of Baltimore) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Co. v. American Bonding Co. of Baltimore, 182 P. 444, 180 Cal. 675, 1919 Cal. LEXIS 540 (Cal. 1919).

Opinion

THE COURT.

—Action on a bond given by a contractor to secure payment of claims for labor and material to be furnished in the construction of a building. Defendant appeals from a judgment in favor of plaintiff, a corporation that supplied certain materials for use in the building.

The bond in question had at its beginning the following words: “This bond is required by section 1183 of the Code of Civil Procedure, as amended in 1911, and must be equal to fifty per cent of the contract price; bond to laborers, materialmen, etc.” By the terms set forth in the body of the instrument it is “expressly made to inure to the benefit of any and all persons who perform labor upon or furnish materials to be used in the work described” in the building contract. There is a further provision as follows: “Any and all such persons shall have and are given a right of action to recover upon this bond against the said principal and surety, or either of them, in any suit brought to foreclose mechanics’ liens, which may be filed by such persons, or any *677 of them, upon the property mentioned in said contract, or in a separate suit brought upon this bond, and may recover in such action or actions, the value of such labor done or materials furnished, or both.” (The italics are ours.)

Defendant sets forth in its answer a special defense based upon the failure of respondent to file any claim of lien under the provisions of section 1187 of the Code of Civil Procedure.

' It was alleged that during the time within which a claim of lien might have been filed a large sum of money was due from the owner to the contractor which could and would have been applied to respondent’s claim if the lien had been thus formally asserted. The court sustained a demurrer to this special defense and also on motion ordered it stricken out. These rulings are specified as erroneous. The question for this court to decide, therefore, is whether or not a material-man may sue on a bond, conditioned as is the one which is the basis of this action, without first duly filing a claim of lien.

Appellant insists that this is strictly a statutory bond, and that no liability arises upon it as a common-law obligation. The learned district court of appeal of the second appellate district agreed with appellant’s view and reversed the judgment upon the authority of Miles v. Baley, 170 Cal. 151, [149 Pac. 45], Hubbard v. Jurian, 35 Cal. App. 757, [170 Pac. 1093], and Crane Co. v. Maryland Casualty Co., 37 Cal. App. 87, [173 Pac. 494],

The first of these eases arose not under section 1183 of the Code of Civil Procedure, but under an act to secure the payment of the claims of materialmen, etc., employed upon public work. By the terms of the act it was made the duty of the contractor before entering upon the performance of the work to file the prescribed bond binding the sureties to pay for materials or labor, up to the amount specified therein, in case of the contractor’s default “provided that such claims shall be filed” as thereafter required.

It appears in Miles v. Baley that the verified statement prescribed by section 2 of the act (Stats. 1897, p. 201) as a condition precedent to the maintenance of a suit upon the bond had not been filed by the claimant. Therefore the sureties on the bond were held not to be liable. Said section 2, after requiring that the materialman or laborer must file a verified statement of claims within thirty days from the time *678 when the work is completed, provides that “At any time within ninety days after the filing of such claim,” the materialman or laborer “may commence an action against the sureties.” This is the fundamental and essential difference between Miles v. Baley and the case at bar. In that case the materialman under the plain terms of the statute governing the performance of the public work and the remuneration therefor was required to file his claim before and as a precedent condition to the maintenance of a suit on the bond. The section governing the materialmen in the case at bar (Code Civ. Proc., see. 1183), contains no such restriction. Miles v. Baley, therefore, is not authority sustaining defendant’s theory in the case at bar. Hubbard v. Jurian distinctly holds, however, that only those claimants who have duly perfected their liens within the statutory time are entitled to recover upon the bond given by section 1183 of the Code of Civil Procedure. Crane Co. v. Maryland Casualty Co., 37 Cal. App. 87, [173 Pac. 494], follows Hubbard v. Jurian without discussion of the principles involved. In Richardson & Fisher Co. v. Chicago Bonding and Surety Co., 35 Cal. App. 650, [170 Pac. 856], decided a few days before Hubbard v. Jurian, the court held that filing of a lien as prescribed by section 1187 of the Code of Civil Procedure was a prerequisite to a suit on the bond given in accordance with section 1183 of the Code of Civil Procedure. In Hubbard v. Jurian, there were petitions for transfer of the cause to this court and said petitions were denied. Unless, therefore, we are prepared to overrule the three decisions last cited, we must reach the some conclusion at which the learned district court of appeal arrived in this case. [1] We are of the opinion that the cited cases were improperly decided so far as they held that a bond like the one before us is incapable of enforcement unless the claimants seeking to bind the sureties have filed their liens within the prescribed time. The rationale of these decisions appears clearly from the following language in the opinion in Hubbard v. Jurian, supra (35 Cal. App. at page 770, [170 Pac. 1098]): “The bond in suit was executed in response to the requirements of the statute. It is therefore a statutory bond in the strictest sense, and under the familiar and well-settled rule parties claiming the benefit of the obligation of'the bond must show a substantial compliance with the conditions of the statute under Which the" bond was given. *679 Section 1183 of the Code of Civil Procedure, under which the bond was given, is part and parcel of title IV, chapter 2, of that code, which relates exclusively to ‘liens of mechanics and others upon real property; ’ and section 1187 of the same code and chapter requires that every person claiming the benefits of the provisions of the designated chapter must file a verified lien within the time specified by that section.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leeds & Northrup Co. v. Interkiln-Salgo Engineering Co.
341 P.2d 21 (Appellate Division of the Superior Court of California, 1959)
Pneucrete Corp. v. United States Fidelity & Guaranty Co.
46 P.2d 1000 (California Court of Appeal, 1935)
Giant Powder Co. v. Fidelity & Deposit Co.
7 P.2d 1023 (California Supreme Court, 1932)
Santa Cruz Portland Cement Co. v. Snow Mountain Water & Power Co.
274 P. 617 (California Court of Appeal, 1929)
Fraters Glass & Paint Co v. Sw. Construction Co.
254 P. 1097 (California Supreme Court, 1927)
Dodd v. Maddox
238 P. 130 (California Court of Appeal, 1925)
Evans v. Shackelford
222 P.2d 846 (California Court of Appeal, 1923)
Heberling v. Day
209 P. 908 (California Court of Appeal, 1922)
Standard Iron Works v. Maryland Casualty Co.
206 P. 136 (California Court of Appeal, 1922)
Fuller Co. v. Chatham
200 P. 293 (California Court of Appeal, 1921)
W. P. Fuller & Co. v. Chatham
53 Cal. App. 800 (California Court of Appeal, 1921)
Hubbard v. Jurian
190 P. 1052 (California Court of Appeal, 1920)
Purington v. Olsten
188 P. 288 (California Court of Appeal, 1920)
Crocker Wheeler Co. v. American Bonding Co.
187 P. 928 (California Court of Appeal, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
182 P. 444, 180 Cal. 675, 1919 Cal. LEXIS 540, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-co-v-american-bonding-co-of-baltimore-cal-1919.