Santa Cruz Portland Cement Co. v. Snow Mountain Water & Power Co.

274 P. 617, 96 Cal. App. 615, 1929 Cal. App. LEXIS 53
CourtCalifornia Court of Appeal
DecidedFebruary 5, 1929
DocketDocket No. 6578.
StatusPublished
Cited by1 cases

This text of 274 P. 617 (Santa Cruz Portland Cement Co. v. Snow Mountain Water & Power Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Cruz Portland Cement Co. v. Snow Mountain Water & Power Co., 274 P. 617, 96 Cal. App. 615, 1929 Cal. App. LEXIS 53 (Cal. Ct. App. 1929).

Opinion

BURROUGHS, J., pro tem.

These are consolidated mechanic’s lien cases all arising out of the construction of the respondent Snow Mountain Water and Power Company’s Scott Dam in Lake County. Said Snow Mountain Water *617 and Power Company will be hereinafter referred to as the Power Company.

A contract for the construction of said dam was entered into on December 15, 1919, between the Power Company, as owner, and the defendant W. A. Kraner, as contractor. In accordance with the provisions of section 1183 of the Code of Civil Procedure, a bond was entered into between said Kraner, as principal, and the appellant Fidelity and Deposit Company of Maryland, as surety. The contract, plans, and specifications, and the surety bond were all filed and recorded in the office of the county recorder as required by said section 1183, supra, before any work under the contract was performed. Kraner started work under the contract, established camp, built roads, hired and bought machinery and necessary supplies and continued the work of building said dam until the morning of July 1, 1921, when all work on the dam ceased. Certain controversies had theretofore arisen between the Power Company and Kraner, and one of the questions here presented is whether Kraner abandoned the contract.

In Snow Mountain Water & Power Co. v. Kraner, 191 Cal. 312 [216 Pac. 589], wherein the said defendant Kraner was appellant, the very question here presented was before the supreme court of this state for hearing and determination. The evidence passed upon in that appeal is substantially the same as presented here.

After a careful analysis of the law and the facts bearing upon the point presented, the supreme court held that Kraner abandoned said contract and that the Power Company was justified under the terms thereof in taking over the work of completing the dam. To set forth in this opinion the evidence would be a repetition of that contained in Snow Mountain Water & Power Co. v. Kraner, supra, and from which we would logically reach the same conclusion. We therefore adopt that opinion upon the question of abandonment as the opinion of this court and hold that Kraner abandoned his contract.

The trial court found that at the time Kraner abandoned the work under the contract there was no fund in the hands of the Power Company available for the payment of any of the lien claimants. Appellants attack this finding as not sustained by the evidence. The contract *618 price for all work, material and supplies for the erection of¡ said dam is a lump sum of $1,122,350, with additional provisions in said contract for alterations or changes which might be ordered by the Power Company in accordance therewith. H. D. Pillsbury, vice-president of the Power Company, testified that at the time Kraner abandoned the contract he had been paid the sum of $884,938.75 for work, materials, and supplies furnished under the lump sum contract price. That he was paid for labor and materials which were furnished outside the lump sum price the additional sum -of $182,020.91. Kraner admitted having received these sums from the Power Company. Witness J. B. Reddick, who was the resident engineer of the Power Company during the entire period of the construction of the dam, testified that when Kraner quit work on the dam he left unfinished within the lump sum contract price 15,461 yards of concrete unpoured, 2,700 cubic yards of excavation at the north end of the dam and between 1,500 and 2,000 yards at the south end; excavation for a cut-off wall under section 14 and filling of same with concrete; excavation for southern diversion wall; placing of sluice gateway and needle and butterfly valves on outlet pipe; construction of trash racks in front of gate; placing of doors and drainage tunnel; placing of impervious hydraulic fill to prevent the seepage of water under dam; placing of fill on downstream foundation of dam to protect foundation; removal of forms along crest of dam; filling of openings in dam; filling of recesses in upstream face of dam; removal of trestle and concrete bunkers and clearing the camp; removal of railroad track and construction equipment. Comparing the amount of work done by Kraner with the work left unperformed, the net result of the testimony of this witness was to the effect that the dam at the time Kraner abandoned work was 75 per cent completed, with possibly one or two per cent one way or the other. S. L. Shuffleton, an engineer of wide experience in the construction of hydroelectric and steam power plants, and also in the construction of concrete dams, testified in detail concerning the amount of work which Kraner had completed and the amount left unfinished, and by comparison he placed the dam as 78.2 per cent completed. It also appears from the evidence that had Kraner completed the portion of the dam yet to be completed, and .within the *619 line of the lump sum contract price, it would have cost him $245,961.41. As against this evidence Kraner testified that he was never paid more than 85 per cent of the amount earned by him monthly. He also testified that the total yardage of cement to be poured was 86,172 yards. That the contract price was $1,122,350, which would give a figure of thirteen dollars plus per cubic yard for concrete poured by him. Figuring on the basis of the testimony of this last witness, it is claimed by appellants that as Kraner poured, according to his own figures, 73,279 cubic yards of cement at the price of $13,025 per yard, he had earned $954,458.98, and having been paid only $884,938.75, there is still a balance due him in the hands of the Power Company of $69,520.23, which last-named sum is available for the satisfaction of the liens of appellants. The fallacy of this position becomes apparent upon reading the contract and the testimony of Reddick and Shuffleton. If the contract of Kraner with the Power Company was merely to pour the concrete, no doubt these figures would be a proper basis for the computation of the amount earned by Kraner, but the argument of the appellants fails to take into consideration there were some 52,000 cubic yards of excavation to be removed within the contract, and as heretofore stated in the testimony of witness Reddick, many other things to be performed beside the cement work itself. Under these circumstances the trial court was justified in accepting a figure of 78 per cent as the basis for its computation of the amount of work done by Kraner. (Sec. 1183, Code Civ. Proc.; McDonald v. Hayes, 132 Cal. 490 [64 Pac. 850]; Hoffman-Marks Co. v. Spires, 154 Cal. 111 [97 Pac. 152]; Pacific Portland Cement Co. v. Hopkins, 174 Cal. 251 [162 Pac. 1016].) Based upon this calculation, the finding of the court that there was no fund in the hands of the Power Company available for the payment of appellants’ claims is fully sustained by the evidence. Appellants further claim that the Power Company was indebted to Kraner, the contractor, for work done and materials and supplies furnished during the months of May and June, 1921. This contention is based on the theory that the Power Company, prior to said time, had breached the contract and therefore all labor performed and all materials and supplies furnished by the contractor were not a part *620

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hayward Lumber & Investment Co. v. American National Bank
123 P.2d 56 (California Court of Appeal, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
274 P. 617, 96 Cal. App. 615, 1929 Cal. App. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-cruz-portland-cement-co-v-snow-mountain-water-power-co-calctapp-1929.