Fraters Glass & Paint Co v. Sw. Construction Co.

254 P. 1097, 200 Cal. 688, 1927 Cal. LEXIS 589
CourtCalifornia Supreme Court
DecidedMarch 16, 1927
DocketDocket No. L.A. 7732.
StatusPublished
Cited by13 cases

This text of 254 P. 1097 (Fraters Glass & Paint Co v. Sw. Construction Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fraters Glass & Paint Co v. Sw. Construction Co., 254 P. 1097, 200 Cal. 688, 1927 Cal. LEXIS 589 (Cal. 1927).

Opinion

CURTIS, J.

This action was instituted for the purpose of foreclosing certain materialmen and mechanics’ liens. The only cause of action with which we are concerned on this appeal is that on behalf of Praters Glass and Paint Company, a corporation, the appellant herein. This company sought a judgment against the sureties on the bond given by the contractor to the owner in compliance with the provisions of section 1183 of the Code of Civil Procedure. E. B. Rivers, as the owner of the real property on which the building was constructed, entered into a contract with the Southwestern Construction Company, a corporation, for the construction of said building at an agreed price of $91,000. The contractor gave a bond as required by section 1183 of the Code of Civil Procedure, with the defendants Henry S. Patten and P. W. Patten as sureties, in the sum of $45,500, being fifty per cent of the contract price of said building. There is no claim but that this bond met all the requirements of said section 1183. Under the contract for the construction of said building the appellant, Praters Glass and Paint Company, furnished glass which was actually used in the construction 'of said building, the reasonable market value of which was the sum of $5,135.34, no part of which has been paid. Appellant’s complaint herein set forth the foregoing facts and asked for judgment against respondents, the said sureties, for the sum of $5,135.34. The respondents in their answer make no denial of the allegations of the complaint, but as a special defense alleged that as a part of the consideration for executing said undertaking and as an inducement to them to execute the same, the appellant prior to the signing of said bond by the sureties executed and delivered to the sureties the following writing: “April 26, 1921. Mr. Henry Patten, Patten & Davies Lumber Co., Los Angeles, California. Dear Sir: In *690 connection with the contract between the Southwestern Construction Company, and E'. B. Rivers, for a building at Seventh and Central, we agree to furnish glass as arranged with Harry E. Martin, to cost approximately $4000.00, and to wait thirty-five days after completion of said building for payment of same, waiving our lien rights. We are doing this, of course, to help Mr. Martin in this deal and are confident that it will be carried to a successful completion. Very truly yours, Fraters Glass & Paint Co. By J. A. Fraters, Pres.” Mr. Martin was the president of said construction company.

Respondents further allege in their answer that it was the intent and purpose of said plaintiff, the appellant herein, by the execution of said writing to relieve said respondents of the burden of said undertaking to the extent of $4,000, and that had it not been for the execution of said writing by the appellant, respondents would not have become sureties upon said undertaking. The trial court found the allegations of respondents’ special defense to be true, and rendered judgment accordingly.

On this appeal the appellant attacks these findings as unsupported by any evidence. Appellant contends that by this writing it did nothing more than waive its right to a lien against the building for which it furnished said material, and that this waiver did not extend to nor include its right to proceed against said sureties on said bond for the amount unpaid on its claim. In this connection appellant contends that as a materialman furnishing materials to be used and which were actually used in the construction of said building, it was given under the statute the right to a lien against said building and the land upon which it was constructed, together with a convenient space about the same, and also a right in case of the nonpayment of its claim to proceed against the sureties on said bond for the amount unpaid on its claim; that these two rights are separate, distinct, and independent of each other, and that by waiving its right to a lien against the real property it in no manner impaired its right of action against the sureties on the bond to recover the amount remaining unpaid upon its claim. In support of this contention, appellant relies upon the case of General Elec. Co. v. American Bonding Co., 180 Cal. 675 [182 Pac. 444]. That action was instituted by the plaintiff therein *691 against the surety upon a bond given in compliance with section 1183 of the Code of Civil Procedure to recover for the value of materials furnished and which were actually used in the construction of the building referred to in said bond. As a defense to said action the surety set up in its answer the failure of plaintiff therein to file any claim of lien under the provisions of section 1187 of the Code of Civil Procedure, and that during the time within which such a claim of lien might have been filed a large sum of money was due from the owner to the contractor, and which should and would have been applied to plaintiff’s claim if the lien had been formally asserted. To this defense the trial court sustained a demurrer and granted a motion to strike it out. Upon appeal this court sustained the action of the trial court and held:

“Section 1197 of the same chapter clearly contemplates suits which may be maintained without the previous filing of liens, for it provides that: ‘Nothing contained in this chapter shall be construed to impair or affect the right of any person to whom any debt may be due for work done or materials furnished to maintain a personal action to recover said debt against the person liable therefor; . . . but the judgment, if any, obtained by the plaintiff in such personal action shall not be construed to impair or merge any lien held by said plaintiff under this chapter; provided, only, that any money collected on said judgment shall be credited on the amount of such lien in any action brought to enforce the same, in accordance with the provisions of this chapter.’ The bond by its terms creates a direct obligation on the part of the surety to pay for materials used in the construction of the building and the right of action on such bond is preserved by said section 1197 as well as by section 1183.
“It can no doubt be persuasively argued that the bond which must ‘be also conditioned for the payment in full of the claims of all persons performing labor upon or furnishing materials to be used in the work’ relates to claims of lien filed within time. But it seems to us that this is a strained interpretation. The mere use of the word ‘claim,’ which is as apt a description of the demand of the individual who has filed no claim of lien as it is of one who has filed such claim, is not persuasive.
*692 “It is to be noted also that the portion of the section (and of the bond which follows its terms), by which the rights of materialmen are safeguarded, does not use the word ‘claims’ but the bond is made to ‘inure to the benefit of any and all persons who . . . furnish materials to be used in the work described’ in the contract.
“But there is another and a very strong reason for rejecting the theory that section 1187 of the Code of Civil Procedure restricts the terms of section 1183 of the Code of Civil Procedure and makes thorn applicable only to those persons who have filed liens, and that reason is found in the history of the two sections and in the decisions of this court relating thereto. ’ ’ '

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Casualty & Surety Co. v. United States
655 F.2d 1047 (Court of Claims, 1981)
Post Bros. Construction Co. v. Yoder
569 P.2d 133 (California Supreme Court, 1977)
Bonded Products Co. v. R. C. Gallyon Construction Co.
228 Cal. App. 2d 186 (California Court of Appeal, 1964)
Ferry v. Ohio Farmers Insurance
211 Cal. App. 2d 651 (California Court of Appeal, 1963)
Crow v. PEG Construction Co., Inc.
319 P.2d 47 (California Court of Appeal, 1957)
Kesterson Lumber Corp. v. Friesleben Estate Co.
251 P.2d 945 (California Supreme Court, 1953)
Brant v. California Dairies, Inc.
48 P.2d 13 (California Supreme Court, 1935)
Giant Powder Co. v. Fidelity & Deposit Co.
7 P.2d 1023 (California Supreme Court, 1932)
Kennedy v. National Surety Co.
295 P. 359 (California Court of Appeal, 1931)
Fraters Glass & Paint Co. v. Southwestern Construction Co.
290 P. 45 (California Court of Appeal, 1930)
Luke v. Southern Surety Co.
286 P. 490 (California Court of Appeal, 1930)
Santa Cruz Portland Cement Co. v. Snow Mountain Water & Power Co.
274 P. 617 (California Court of Appeal, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
254 P. 1097, 200 Cal. 688, 1927 Cal. LEXIS 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fraters-glass-paint-co-v-sw-construction-co-cal-1927.