Post Bros. Construction Co. v. Yoder

569 P.2d 133, 20 Cal. 3d 1, 141 Cal. Rptr. 28, 1977 Cal. LEXIS 179
CourtCalifornia Supreme Court
DecidedSeptember 29, 1977
DocketL.A. 30750
StatusPublished
Cited by44 cases

This text of 569 P.2d 133 (Post Bros. Construction Co. v. Yoder) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Post Bros. Construction Co. v. Yoder, 569 P.2d 133, 20 Cal. 3d 1, 141 Cal. Rptr. 28, 1977 Cal. LEXIS 179 (Cal. 1977).

Opinion

*4 Opinion

CLARK, J.

Plaintiff Post Bros. Construction Co. (Post), appeals from judgment denying foreclosure of mechanic’s lien and recovery on a surety bond. We affirm the judgment.

In August 1973, defendant, Shapell Industries, Inc. (Shapell), owned subdivision Tract 8009 in Orange County. Shapell’s subsidiary, a general contractor, subcontracted with defendant West Pac Constructors, Inc. (West Pac), for the latter to perform grading work on Tract 8009 for an estimated maximum price of $70,000. The ultimate price was to be fixed on a unit basis per hour and per cubic yard. West Pac in turn retained Post, a lessor of grading equipment, to supply the necessary equipment. The aggregate rental charges by Post to West Pac approximated $33,000. Post also rented equipment to West Pac for other jobs, some on Shapell property.

Shapell’s subsidiary issued one check jointly naming West Pac and Post as payees and three other checks jointly to West Pac, Post and other materialmen who took part in grading Tract 8009. The subsidiary gave no instruction for division of the joint checks. The four checks totalled $54,000, the sum believed due on the contract. They were endorsed by each named payee, including Post, then deposited in West Pac’s bank account.

The agreed statement of facts stipulates the four checks to West Pac, Post and the others were for work performed only on Tract 8009.

Pursuant to an ongoing “gentlemen’s agreement” between Post and West Pac, West Pac would pay Post as soon as it received payment. Post kept a single ledger of invoices sent to West Pac. Although each invoice referred to a job site, they were not segregated by job sites. When West Pac sent a check to Post, the latter would credit West Pac’s earliest unpaid invoices unless West Pac directed otherwise.

West Pac delivered four checks to Post exceeding $27,000, Post crediting $15,487.03 to Tract 8009 and $12,000 to other West Pac jobs. According to Post’s books, $17,500 remained due for furnishing equipment on Tract 8009. Preliminary notice and mechanic’s lien were filed.

Prior to commencement of work, Shapell as principal and Safeco Insurance Company of America as surety executed a labor and material *5 bond covering improvements on Tract 8009 pursuant to Business and Professions Code section 11612. The bond provides in part that if the principal, contractor or subcontractor fails to pay for materials or labor, the surety will pay the amount due.

The trial court determined Post failed to protect its own interest by not securing its share of the joint checks for application to its Tract 8009 account, that Post’s claim against Shapell is fully paid, that Post is estopped from asserting mechanic’s lien upon Tract 8009, and that there being no money due Post from Shaped, Safeco is not liable on its bond. 1

The use of joint checks is wed established by custom and practice in the construction industry. (See, e.g., Moss, Joint Checks; Practices in the Construction Industry (1968) 43 State Bar J. 242; Miller & Starr, Current Law of Cal. Real Estate (1975) § 10.36; Cal. Mechanic’s Liens and Other Remedies (Cont.Ed.Bar 1972) §§ 6.38 and 7.29.)

When a subcontractor and his materialman are joint payees, and no agreement exists with the owner or general contractor as to allocation of proceeds, the materialman by endorsing the check will be deemed to have received the money due him. (J. S. Schirm Co. v. Rollingwood Homes Co. (1961) 56 Cal.2d 789, 795 [17 Cal.Rptr. 1, 366 P.2d 444]; Bohannan Bros. Inc. v. Lo Jean Dev. Co. (1969) 3 Cal.App.3d 200, 204-205 [82 Cal.Rptr. 922]; Rodeffer Industries, Inc. v. Chambers Estates, Inc. (1968) 263 Cal.App.2d 116, 118 [69 Cal.Rptr. 551]; Re-Bar Contractors, Inc. v. City of Los Angeles (1963) 219 Cal.App.2d 134, 136 [32 Cal.Rptr. 607]; Westwood Bldg. Materials Co. v. Valdez (1958) 158 Cal.App.2d 107, 109 et seq. [322 P.2d 79].) Inclusion of the materialman as payee makes clear that the maker of the check intends to discharge obligations owed the materialman.

“ ‘If it may reasonably be said . . . that a material dealer . . . could be so naive as to fail to understand the purpose and intention of an owner in making checks payable jointly to it and his subcontractor, [the material-man] was at least under the duty of inquiring ... as to his intention with respect to the application of the funds represented by the checks. This [the materialman] failed to do, and it may not now be heard to say that respondent should bear the loss which it sustained as a result of its own imprudence.’ ” (Re-Bar Contractors, Inc. v. City of Los Angeles, supra, 219 Cal.App.2d 134, 136.)

*6 The material man may protect himself by simply refusing to endorse the check until assured by escrow of other arrangement that he will recover his rightful share of the check. Because the materialman is positioned to demand immediate payment in exchange for his endorsement, the custom and use of joint checks is beneficial to materialmen.

The joint check rule is likewise beneficial to owner and general contractor. They have contracted with the subcontractor—not the materialman—and are usually unaware of the nature and size of the materialman’s claim against the subcontractor. The joint check rule provides a simple yet expeditious method for owner and general contractor to pay their debts to the person with whom they have contracted while eliminating the risk the subcontractor will not pay the person with whom he has contracted.

While the above cited cases involve only two payees, the joint check rule logically applies when there are more than two. Each payee is well aware of the owner’s or general contractor’s intent to discharge his obligations throughout the construction pyramid. Post may not reasonably contend the joint check was executed to give the payees a right to divide the proceeds as they saw fit without regard to the owner’s or general contractor’s intent. Again, any payee may refuse to endorse unless assured his proper share of the proceeds. While division may become more burdensome as payees increase, disbursement can be accomplished by simple escrow.

Post contends the joint check rule should not apply when there are multiple job sites. However, the number of jobs should not change the materialman’s need to determine his share of any joint check. When there is a single job and a joint check, the materialman, before he can determine his share, must determine whether all of the job is covered by the joint check or whether it is merely a progress payment. In short, his burden is to determine what the joint check is for. Performance of this burden will also establish which of the multiple jobs should be credited.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

(HC) Rodriguez v. Fisher
S.D. California, 2022
Contreras v. American Family Mutual Insurance
135 F. Supp. 3d 1208 (D. Nevada, 2015)
In re: Sie Khalil
Ninth Circuit, 2015
People v. Rodriguez
California Court of Appeal, 2014
Granite Construction v. Bond Safeguard Ins. CA3
California Court of Appeal, 2014
Plains Builders, Inc. v. Steel Source, Inc.
408 S.W.3d 596 (Court of Appeals of Texas, 2013)
Fort Bragg Unified School District v. Colonial American Casualty & Surety Co.
194 Cal. App. 4th 891 (California Court of Appeal, 2011)
SFR, INC. v. Comtrol, Inc.
2008 UT App 31 (Court of Appeals of Utah, 2008)
AAA Cabinets & Millwork, Inc. v. Accredited Surety & Casualty Co.
130 P.3d 887 (Court of Appeals of Washington, 2006)
McWane, Inc. v. Fidelity & Deposit Co. of Maryland
372 F.3d 798 (Sixth Circuit, 2004)
Crystaplex Plastics, Ltd. v. Redevelopment Agency
92 Cal. Rptr. 2d 197 (California Court of Appeal, 2000)
Henry Products Inc. v. Tarmu
967 P.2d 444 (Nevada Supreme Court, 1998)
Board of Education ex rel. Bertolino v. Vince Kelly Construction Co.
963 S.W.2d 331 (Missouri Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
569 P.2d 133, 20 Cal. 3d 1, 141 Cal. Rptr. 28, 1977 Cal. LEXIS 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/post-bros-construction-co-v-yoder-cal-1977.