Water Works Supplies v. Grooms Constr. Co., Unpublished Decision (3-24-2003)

CourtOhio Court of Appeals
DecidedMarch 24, 2003
DocketNo. 01CA18.
StatusUnpublished

This text of Water Works Supplies v. Grooms Constr. Co., Unpublished Decision (3-24-2003) (Water Works Supplies v. Grooms Constr. Co., Unpublished Decision (3-24-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Water Works Supplies v. Grooms Constr. Co., Unpublished Decision (3-24-2003), (Ohio Ct. App. 2003).

Opinion

DECISION AND JUDGMENT ENTRY INC
{¶ 1} This is an appeal from a Highland County Common Pleas Court summary judgment in favor of Fidelity and Deposit Company of Maryland and Highland County Water Company, defendants below and appellees herein.

{¶ 2} Water Works Supplies, Inc., plaintiff below and appellant herein, raises the following assignments of error:

FIRST ASSIGNMENT OF ERROR:

"The trial court erroneously granted Fidelity and Deposit Co.'s motion for summary judgment."

SECOND ASSIGNMENT OF ERROR:

"The trial court erred by dismissing WWS' claims against Highland County Water."

{¶ 1} On March 7, 2000, Highland County Water Company (Highland County) entered into a contract with Grooms Construction Company, Inc.1 (Grooms) for a construction project known as the Phase VII-North Loop-Division A-Lines 100 and 200. Under the contract, Grooms was to serve as the general contractor.

{¶ 2} The contract required Grooms to post a surety bond. To that end, on March 7, 2000, Grooms signed a payment bond contract. The payment bond contract states that Grooms is the principal and that appellee Fidelity and Deposit Company of Maryland (FD) is the surety.

{¶ 3} The payment bond contract specifies that FD is "bound * * * unto all persons, firms, and corporations who or which may furnish labor, or who furnish materials to perform as described under the contract and to their successors and assigns in the total aggregate sum of * * *."

{¶ 4} The payment bond contract further provides:

"[The] surety for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of this contract or to the work or to the specifications."

{¶ 5} In March of 2000, Grooms contacted appellant to request that appellant provide materials for the construction project. When Grooms first contacted appellant, Grooms had an outstanding balance of $43,906.75 under an "open account agreement" that appellant and Grooms entered into on December 30, 1997. Initially appellant was hesitant, considering Grooms's outstanding balance, to provide further materials to Grooms. Grooms assured appellant, however, that it would pay the outstanding balance by the end of March 2000. Grooms also promised appellant that appellant would be Grooms's primary supplier on all future jobs. Appellant, armed with Grooms's assurances and with the knowledge that a payment bond had issued on the project, agreed to provide materials for the project under the terms of the parties' December 30, 1997 open account agreement.

{¶ 6} On April 24, 2000, Grooms presented appellant with a check in the amount of $396,095.24 that Highland County had issued. The check listed Grooms, appellant, and two other suppliers as payees. In exchange for appellant's endorsement of the check, Grooms paid appellant the amount of Grooms's outstanding balance, $43,906.75.

{¶ 7} On May 17, 2000, Grooms presented appellant with a second check that Highland County had issued in the amount of $471,997.23 that listed Grooms, appellant, and two other suppliers as payees. Appellant endorsed the check and Grooms paid appellant $91,432.05 as payment for supplies for the construction project.

{¶ 8} On July 21, 2000, Grooms presented appellant with a third check that Highland County had issued in the amount of $176,600.76 that listed Grooms, appellant, and one other supplier as payees. Grooms requested appellant to endorse the check and, in exchange, Grooms represented that it would pay appellant $300,000 by July 25, 2000. Appellant endorsed the check. Grooms did not, however, pay appellant the $300,000.

{¶ 9} On July 28, 2000, appellant notified FD of the amount Grooms owed appellant for materials supplied for the construction project. On August 14, 2000, appellant submitted to FD a formal claim on the payment bond. Appellant requested payment of $378,271 for materials supplied for the construction project.

{¶ 10} By letter dated September 7, 2000, FD notified appellant that it would not pay under the bond. The letter states:

"The material facts revealed by FD's investigation are that from the outset of this project, the Highland County Water Company made direct payment to all material suppliers with checks payable jointly to Grooms Construction Co. and each material supplier. Highland County Water wrote each check beginning with the first check, date April 19, 2000 — in an amount sufficient to pay each supplier for all materials incorporated into the project or stored on-site. The checks were then delivered to each named payee for indorsement before being presented to the Water Company's Bank for payment."

{¶ 11} On January 18, 2001, appellant filed a complaint against Grooms, Highland County, and FD to recover the unpaid balance of $337.540.71. On March 1, 2001, FD filed a motion to dismiss or, in the alternative, a motion for summary judgment. FD argued that appellant's conduct "impaired the `suretyship status' of FD, as defined in Section 37 of Restatement (Third), Suretyship and Guaranty (1996)." FD claimed:

"By receiving three checks made payable by Highland [County] to [appellant], indorsing them and returning them to Grooms without receiving payment from Grooms for the materials supplied to the Highland Project, [appellant] impaired FD's rights and voluntarily released from any liability to [appellant] under the Payment Bond."

FD further contended that under the "joint check rule," it was not liable under the payment bond. FD argued that when a subcontractor endorses a joint check, a presumption arises that the subcontractor has received all sums then owed to him.

{¶ 12} In opposition, appellant argued that FD, as the surety on the payment bond, is primarily and jointly liable with Grooms for the amount owed. Appellant asserted that under the clear terms of the payment bond, FD must honor appellant's claim for payment. Appellant also disputed FD's claim that any suretyship defense is available and that the joint check rule applies. Appellant noted that no Ohio court has explicitly adopted either the Restatement's suretyship defenses or the joint check rule.

{¶ 13} On September 27, 2001, the trial court granted summary judgment in FD's favor. The trial court concluded:

"[A]s a matter of law[,] * * * [appellant] had fundamentally altered the risks imposed upon [FD] by agreeing to a modification of the duty of the principal obligor Grooms in a fashion amounting to a substituted contract thereby imposing risks on [FD] fundamentally different from the risks imposed upon said [FD] prior to the modification. As a consequence, the aforesaid modification or new agreement for payment by contractor Grooms to [appellant] discharged the surety [FD] from any unperformed duties of Grooms."

{¶ 14} The court also granted summary judgment in Highland County's favor. The trial court reasoned that Highland County had paid appellant the amounts owed, but that appellant failed to ensure that it received the payment it was due.

{¶ 15} Appellant filed a timely notice of appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Post Bros. Construction Co. v. Yoder
569 P.2d 133 (California Supreme Court, 1977)
Manor Care Nursing & Rehabilitation Center v. Thomas
704 N.E.2d 593 (Ohio Court of Appeals, 1997)
Morehead v. Conley
599 N.E.2d 786 (Ohio Court of Appeals, 1991)
Brown v. Scioto Cty. Bd. of Commrs.
622 N.E.2d 1153 (Ohio Court of Appeals, 1993)
Hopkins v. INA Underwriters Insurance
542 N.E.2d 679 (Ohio Court of Appeals, 1988)
G. F. Business Equipment, Inc. v. Liston
454 N.E.2d 1358 (Ohio Court of Appeals, 1982)
Anania v. Daubenspeck Chiropractic
718 N.E.2d 480 (Ohio Court of Appeals, 1998)
Troyer v. Horvath
468 N.E.2d 351 (Ohio Court of Appeals, 1983)
State v. Scherer
671 N.E.2d 545 (Ohio Court of Appeals, 1995)
Solon Family Physicians, Inc. v. Buckles
645 N.E.2d 150 (Ohio Court of Appeals, 1994)
St. Paul Fire & Marine Insurance v. Industrial Commission
506 N.E.2d 202 (Ohio Supreme Court, 1987)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)
Vahila v. Hall
674 N.E.2d 1164 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Water Works Supplies v. Grooms Constr. Co., Unpublished Decision (3-24-2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/water-works-supplies-v-grooms-constr-co-unpublished-decision-ohioctapp-2003.