AAA Cabinets & Millwork, Inc. v. Accredited Surety & Casualty Co.

130 P.3d 887, 132 Wash. App. 202
CourtCourt of Appeals of Washington
DecidedMarch 23, 2006
DocketNo. 24364-8-III
StatusPublished
Cited by2 cases

This text of 130 P.3d 887 (AAA Cabinets & Millwork, Inc. v. Accredited Surety & Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AAA Cabinets & Millwork, Inc. v. Accredited Surety & Casualty Co., 130 P.3d 887, 132 Wash. App. 202 (Wash. Ct. App. 2006).

Opinion

Schultheis, J.

¶1 — General contractor Lydig Construction, Inc., made payments by joint-payee checks to a subcontractor and two lower-tier subcontractors and received an assignment of the lower-tier subcontractors’ rights against the subcontractor. In the name of the assignors, Lydig then demanded payment from Accredited Surety & Casualty Co., Inc., which had issued the subcontractor’s license bond. Accredited refused payment, arguing that Lydig was not a valid beneficiary of the bond. On summary judgment, the trial court awarded Lydig one-half of the license bond as well as sizable attorney fees and costs.

¶2 Accredited challenges the judgment on appeal, contending Lydig has no valid claim against the bond and is not entitled to attorney fees and costs in excess of the amount of the bond. We conclude that issues of fact regarding the subcontractor’s liability to the lower-tier subcontractors defeat summary judgment. Accordingly, we reverse.

FACTS

¶3 Lydig was hired as general contractor on the Wilmer Davis Dining Hall Renovation Project at Washington State University. In July 2003, Lydig entered into a subcontract with Spokane Woodworking to build and install cabinets and other fixtures. Woodworking in turn hired the lower-tier subcontractors AAA Cabinets & Millwork, Inc., and Koch Sheet Metal, Inc. Pursuant to RCW 18.27.040, Woodworking posted a registration bond for $12,000, issued by Accredited.

¶4 Throughout the project, Lydig issued joint checks payable to Woodworking and Woodworking’s lower-tier subcontractors, including AAA and Koch. A “Payment Recap Sheet” of Lydig’s payments to Woodworking from July 2003 to April 27, 2004 indicates that joint-payee checks to Woodworking and AAA totaled $9,190.65 and joint-payee checks to Woodworking and Koch totaled $8,900.00, with $1,539.00 still owed to Koch. Clerk’s Papers (CP) at 85. According to Lydig, although it had no contractual duties to [206]*206the lower-tier subcontractors, these payments were made to avoid possible claims by the lower-tier subcontractors against Lydig’s chapter 39.04 RCW payment bond.

¶5 In April 2004, over two weeks after the last joint-payee check to Woodworking and AAA, Lydig obtained a release from AAA of all claims against Lydig and an assignment of all claims AAA had against Woodworking. The consideration supporting this release and assignment was payment by Lydig “of certain Subcontractor/Supplier balances in the amount of $9,190.65.” CP at 265. That same month, Lydig — on behalf of AAA and Jacobs Upholstery (another alleged lower-tier subcontractor) — demanded from Accredited the entire $12,000 of Woodworking’s license bond. Accredited responded informally with an “initial reaction” that Lydig was not a proper beneficiary to the statutory bond under Washington law. CP at 267.

¶6 Lydig filed a complaint in August 2004 seeking foreclosure on the bond in the name of AAA and Jacobs Upholstery.1 Eventually realizing that Jacobs Upholstery had no contract with Woodworking, Lydig obtained an order of nonsuit dismissing that claim. Lydig then obtained an assignment of Koch’s rights against Woodworking in September 2004 and in October 2004 filed an amended complaint' seeking foreclosure of the bond in the names of AAA and Koch, further alleging a violation of the Consumer Protection Act, chapter 19.86 RCW.2 In Accredited’s answer to Lydig’s amended complaint, it argued in part that the assignments were void due to lack of consideration and that it was liable for no more than one-half of the bond pursuant to RCW 18.27.040.

¶7 Lydig filed a motion for summary judgment in January 2005. Accredited responded with a motion to dismiss on [207]*207the ground that the plaintiffs (AAA and Koch) were not the real parties in interest and with a motion to substitute Lydig as the real party in interest. In addition to the defenses already raised, Accredited argued that Woodworking had paid AAA and Koch and that Lydig actually owed Woodworking additional funds. The trial court denied Lydig’s motion for summary judgment and Accredited’s motions by order dated April 1, 2005.3

¶8 On March 25, 2005, Lydig filed a motion for partial summary judgment, seeking at least one-half of the license bond and attorney fees and costs. The trial court granted partial summary judgment on June 23, 2005, awarding Lydig $6,000 plus $20,500 in attorney fees and costs. Accredited’s motion for reconsideration was denied. The parties stipulated to dismissal of the Consumer Protection Act claim and Accredited timely appealed.

Joint-Payee Rights Against the Surety Bond

¶9 A surety is liable only if its principal is liable and may plead any defense the principal might have used. McChord Credit Union v. Parrish, 61 Wn. App. 8, 13-14, 809 P.2d 759 (1991). Accredited contends it is not liable to Lydig because its principal, Woodworking, paid AAA and Koch in full under their contracts by endorsing the joint-payee checks and delivering them to AAA and Koch.4 At a minimum, Accredited argues, there is an issue of fact regarding [208]*208Woodworking’s liability to AAA and Koch that defeats summary judgment.

¶10 Because this is a review of a summary judgment, we engage in the same inquiry as the trial court and consider the facts in the light most favorable to the nonmoving party. Labriola v. Pollard Group, Inc., 152 Wn.2d 828, 832-33, 100 P.3d 791 (2004). Summary judgment is appropriate only when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Id.

¶11 All contracts are assignable unless prohibited by statute or public policy. Puget Sound Nat’l Bank v. Dep’t of Revenue, 123 Wn.2d 284, 288, 868 P.2d 127 (1994). Generally, an assignee steps into the shoes of the assignor and acquires whatever rights the assignor had prior to the assignment. Id. at 292-93. Although an upper-tier contractor such as Lydig is not a beneficiary — in its own right — of a lower-tier contractor’s surety bond, the upper-tier contractor may claim against the bond as an assignee of a beneficiary’s rights. Int’l Commercial Collectors, Inc. v. Mazel Co., 48 Wn. App. 712, 718, 740 P.2d 363 (1987). In International, the general contractor paid the amount of a judgment obtained against the subcontractor, received an assignment of the judgment creditor’s rights against the subcontractor, and proceeded against the subcontractor’s bond. Id. at 713-14. Here, AAA and Koch assigned to Lydig in writing all claims, demands, and causes of action related to the project that AAA and Koch had against Woodworking. Unlike in International, these claims had not been reduced to a judgment. The question then becomes whether and to what extent AAA and Koch had assignable claims against Woodworking at the time of the assignments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
130 P.3d 887, 132 Wash. App. 202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aaa-cabinets-millwork-inc-v-accredited-surety-casualty-co-washctapp-2006.