Westwood Bldg. Materials Co. v. Valdez

158 Cal. App. 2d 107
CourtCalifornia Court of Appeal
DecidedFebruary 28, 1958
DocketCiv. No. 22471
StatusPublished
Cited by13 cases

This text of 158 Cal. App. 2d 107 (Westwood Bldg. Materials Co. v. Valdez) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westwood Bldg. Materials Co. v. Valdez, 158 Cal. App. 2d 107 (Cal. Ct. App. 1958).

Opinion

158 Cal.App.2d 107 (1958)

WESTWOOD BUILDING MATERIALS COMPANY (a Corporation), Appellant,
v.
EDWARD L. VALDEZ et al., Defendants; IRVING M. LITZ, Respondent.

Civ. No. 22471.

California Court of Appeals. Second Dist., Div. Three.

Feb. 28, 1958.

George W. Burch, Jr., for Appellant.

Glen Behymer as Amicus Curiae on behalf of Appellant.

Alfred R. Meyers for Respondent. *108

PATROSSO, J. pro tem. [fn. *]

This is an appeal by plaintiff from a judgment in favor of the defendant Litz in an action to foreclose a mechanic's lien.

There is no dispute with respect to the facts. Defendant Litz, respondent here, as owner entered into a contract with Pelton and Zahler, whereby the latter agreed to construct 21 houses upon a tract owned by respondent. The general contractors in turn entered into a subcontract with defendant Valdez under which the latter agreed to furnish the labor and material necessary to perform all of the plastering and stucco work required under the general contract. Plaintiff, pursuant to an oral contract with Valdez under which the latter agreed to pay for the same by the 10th of the following month, furnished materials required by the subcontractor in the performance of his contract of the reasonable value of $10,637.55. Claiming a balance due thereon of $5,268.49, plaintiff filed a claim of mechanic's lien therefor and instituted this action to enforce the same.

During the course of the performance of the work, respondent paid to Valdez the total sum of $21,500 in full payment of all sums due under his subcontract. Such payment was made by the medium of eight checks of the respondent, the first four being made payable to Valdez alone and the last four being made payable jointly to Valdez and the appellant. The last four checks were in the sums of $2,500, $2,800, $2,000 and $5,580 respectively, and were delivered to Valdez who in turn delivered them to the appellant. The first three of these checks were endorsed by the appellant and by it returned to Valdez who endorsed and obtained payment thereon, no portion thereof being received by the appellant. The check for $5,580 was endorsed by Valdez and delivered to appellant which received payment thereof and in turn issued its check to Valdez for $580, the balance of $5,000 being credited by appellant to Valdez's account. These joint checks bore no endorsement or notation thereon to the effect that the proceeds thereof, insofar as necessary, were to be applied by appellant in payment of Valdez's indebtedness to it, and aside from the fact that the checks were payable jointly to Valdez and appellant, respondent did not communicate to appellant his intention with respect to the application of the proceeds thereof.

The trial court found that respondent paid to appellant a sum in excess of $10,637.55, the total value of materials furnished *109 by appellant; denied appellant a lien, and ordered judgment in favor of appellant against Valdez in the sum of $5,268.49. The sole question presented is whether the issuance of the four checks in question made payable jointly to Valdez and appellant operated to discharge respondent's liability to appellant or to bar appellant's right to claim a lien upon respondent's property.

[1] Appellant concedes that if respondent had made plain his intention that the proceeds of the checks were to be first applied to the satisfaction of Valdez's obligation for the materials furnished by appellant and used upon respondent's property, the appellant would have been under the duty to so apply such proceeds. Appellant insists, however, that in the absence of an express direction or notation to this effect upon the face of the checks or by a covering letter so stating, appellant was at liberty to apply the proceeds of the checks in such manner as it and its copayee might agree. We do not agree. However, we see no necessity for extended discussion as all of the appellant's arguments are effectively answered in the two California cases now to be noted.

In Edwards v. Curry (1957) (hearing by Supreme Court denied), 152 Cal.App.2d 726 [313 P.2d 613], plaintiff Edwards was a roofing subcontractor on a school job for the defendant Curry, the general contractor. Cross-defendant Schirm Company was the material dealer supplying Edwards. At the request of Schirm defendant made all payments due Edwards under his subcontract, payable to Schirm and Edwards jointly. These checks as issued from time to time were endorsed by the payees and deposited in Schirm's bank account and a portion of one check was credited to an account of Edwards for material furnished on another job. Also pursuant to an agreement between the payee and unknown to Curry, a portion of the proceeds of these checks was by Schirm returned to Edwards for the payment of labor employed by him and for his living expenses. The joint checks would have fully paid the bill for materials furnished on the school job if Schirm had not returned a portion of the proceeds thereof to Edwards for other purposes. After the completion of the job Schirm filed a stop notice with the school district alleging that $5,109.95 of its account with Edwards had not been paid and by reason thereof the district retained this amount under its contract with Curry. In the litigation which ensued, Curry filed a cross-complaint in declaratory relief asking, among other things, that it be adjudged that he was not indebted to Schirm *110 and that Schirm was not entitled to the amount withheld by the school district. The trial court held that as between Curry and Schirm the latter had been paid in full for material furnished to Curry on the school job and that Curry was entitled to a release of the stop notice, or upon Schirm's failure to release the notice that Curry have judgment against Schirm for the amount withheld by virtue of the notice. In affirming the judgment and answering contentions similar to those advanced by the appellant here, the court said (page 730):

"It is Schirm Company's contention that under section 1192.1 et seq. of the Code of Civil Procedure the general contractor, Curry, is liable to it for materials furnished Edwards which went into the school building; that Curry must have known that the checks made payable to Schirm and Edwards jointly were not intended to be solely applied to the payment of Schirm's bill; and that the laborers must be paid from these payments; that since Curry consented to this joint check arrangement he impliedly agreed to whatever application of the funds was made by Edwards and Schirm, and the fund due from the school district to Curry is liable for the unpaid material bill of Edwards and Schirm, citing Modesto Lbr. Co. v. Wylde, 217 Cal. 421 [19 P.2d 238]; and Hollywood Wholesale Elec. Co. v. John Baskin, Inc., 121 Cal.App.2d 415 [263 P.2d 665]. In the Modesto case the check was made payable solely to the materialman. The court held that the contractor's orders to apply the funds to accounts other than the one intended was (sic) without authority. In the instant case Schirm Company claims a check made payable jointly to the subcontractor and the materialman would not operate as a payment of the account of the materialman."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anchor Concrete Co. v. Victor Savings & Loan Ass'n
664 P.2d 396 (Supreme Court of Oklahoma, 1983)
Phillips Construction Co. v. Argonaut Insurance
77 Cal. App. 3d 575 (California Court of Appeal, 1978)
Post Bros. Construction Co. v. Yoder
569 P.2d 133 (California Supreme Court, 1977)
Feldman Construction Co. v. Union Bank
28 Cal. App. 3d 731 (California Court of Appeal, 1972)
Bohannan Bros. v. Lo Jean Development Co.
3 Cal. App. 3d 200 (California Court of Appeal, 1969)
Rodeffer Industries, Inc. v. Chambers Estates, Inc.
263 Cal. App. 2d 116 (California Court of Appeal, 1968)
Re-Bar Contractors, Inc. v. City of Los Angeles
219 Cal. App. 2d 134 (California Court of Appeal, 1963)
Savage v. Nee
212 Cal. App. 2d 417 (California Court of Appeal, 1963)
Western Specialty Co. v. Clairemont Construction Co.
204 Cal. App. 2d 532 (California Court of Appeal, 1962)
B. & J. Construction Co. v. Spacious Homes, Inc.
204 Cal. App. 2d 216 (California Court of Appeal, 1962)
J. S. Schirm Co. v. Rollingwood Homes Co.
366 P.2d 444 (California Supreme Court, 1961)
Petaluma Building Materials, Inc. v. Foremost Properties, Inc.
180 Cal. App. 2d 83 (California Court of Appeal, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
158 Cal. App. 2d 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westwood-bldg-materials-co-v-valdez-calctapp-1958.