J. S. Schirm Co. v. Rollingwood Homes Co.

366 P.2d 444, 56 Cal. 2d 789, 17 Cal. Rptr. 1, 1961 Cal. LEXIS 338
CourtCalifornia Supreme Court
DecidedNovember 16, 1961
DocketL. A. 25991
StatusPublished
Cited by10 cases

This text of 366 P.2d 444 (J. S. Schirm Co. v. Rollingwood Homes Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. S. Schirm Co. v. Rollingwood Homes Co., 366 P.2d 444, 56 Cal. 2d 789, 17 Cal. Rptr. 1, 1961 Cal. LEXIS 338 (Cal. 1961).

Opinion

SCHAUER, J.

Plaintiff appeals from an adverse judgment in its suit to foreclose a claimed lien for materials furnished to certain houses constructed for defendant on the latter’s land. For reasons which will appear we have concluded that the trial court erred in its determination that plaintiff had been paid in full for such materials, and that the judgment should be reversed.

Defendant Rollingwood Homes Company, hereinafter called Rollingwood, owner and developer of 127 lots of land (known as tract 21269) in Los Angeles County, contracted with Walter R. Sant and Sons (hereinafter sometimes called Sant or general contractor) as general contractor to construct 127 houses on such lots. To finance the construction costs defendant secured a loan from Pioneer Savings and Loan Association (hereinafter called Pioneer), under arrangements whereby Pioneer disbursed the construction funds on successive “orders” which were to be prepared by the general contractor and which would direct Pioneer to disburse varying amounts.

The general contractor and Frank Horpel, as subcontractor, entered into a subcontract whereby Horpel agreed to furnish and install wallboard in the houses. The subcontract provided that 50 per cent of the wallboard contract price for each house was payable to Horpel on completion of hanging the wallboard in the subject house and the remaining 50 per cent was payable upon completion of the wallboard installation in that house.

Between January 2, 1957, and July 1, 1957, plaintiff de *791 livered building material to defendant’s land for use by Horpel in performance of the subcontract. During this period the method used in making payment to Horpel and to plaintiff was as follows: Approximately each week Horpel would submit a statement to the general contractor for work completed during the preceding week. The statement would include a “first billing” (i.e., 50% of contract price) covering the initial hanging of wallboard in houses on certain lots, and a “second billing” (the remaining 50% of contract price) covering the completion of wallboard installation in houses on other lots. The information on such statement would then be used by the general contractor or by an employe of Pioneer in preparing a proposed order directing Pioneer to pay a certain amount to Horpel and plaintiff jointly. The order was prepared by writing the information in the blank spaces of a printed form, which may be described generally as follows; The blank order (of the approximate size of a bank check) is set out at the top of the form. Below the order all of the lot numbers are listed, with a blank space opposite each lot number for filling in the amount payable for labor and materials charged to that lot. This part of the form will be called the schedule. The amount payable on each of the lots covered by Horpel’s weekly billing would be stated on the schedule, together with the billing total, and the order to pay would be made out in the total amount.

On the back of the form is a blank release of lien rights for material and labor furnished to the lots designated on the front of the form. After the appropriate data had been placed in the blanks of the form, Horpel obtained signatures to the proposed order and proposed release of lien rights, including the signature of plaintiff materialman. The order portion of the form was signed on a line described as “Signature of Owner,” as follows: “Rollingwood Homes Co. George R. Sant.” Sant was a partner in the firm which was general contractor; he was also a representative of defendant owner, Rollingwood. The signed order and release were then submitted to Pioneer, which would thereupon issue a check in the amount of the order, payable to plaintiff and Horpel jointly.

The above procedure was followed consistently from lot one through the first billing on lots 116 through 120. 1 However, *792 neither .payment orders nor releases of lien rights were presented to Pioneer or signed by plaintiff covering a second billing on lots 116 through 120 or for either the first or second billing on lots 120 through 127, and the joint check method of payment was terminated without notice to plaintiff prior to payment for any of such billings.

On November 6, 1957, plaintiff filed a materialman's lien claim against lots 116 through 120 in the amount of $164 each, and against lots 121 through 127 in the amount of $328 each—a total of $3,116. Rollingwood recorded a bond pursuant to section 1193.2 of the Code of Civil Procedure, guaranteeing payment of any sum which plaintiff might recover on its lien claim. On January 24, 1958, plaintiff commenced this action to foreclose the lien. Rollingwood answered and cross-complained, alleging in the answer that plaintiff had been fully paid for all materials furnished by it for use on the property, and seeking by the cross-complaint to recover damages allegedly resulting from the filing of the lien.

The trial court found that plaintiff had been fully paid, by means of the cheeks payable to plaintiff and Horpel jointly, for all materials furnished by plaintiff for use on the property. That finding was a product of the court’s conclusion that plaintiff was “required by law to apply the funds derived from said joint checks in payment of all materials furnished by plaintiff . . . before using the funds for any other purpose. ’ ’

With respect to the cross-complaint, the court found that Rollingwood was damaged in the amounts it was required or had agreed to pay; i.e., the bond premium, filing fee, and $1,400 as attorney’s fee. This appeal by plaintiff followed.

In support of the judgment the owner, Rollingwood, relies upon Edwards v. Curry (1957) 152 Cal.App.2d 726 [313 P.2d 613], and Westwood Bldg. Materials Co. v. Valdez (1958) 158 Cal.App.2d 107 [322 P.2d 79]. In both of those cases, as here, joint checks were issued to the subcontractor and the materialman. In neither case, however, does it appear to have been shown that the proceeds of the cheeks were intended by the parties to be applied in any specific manner or in pay *793 ment for labor and materials furnished to only expressly designated lots or jobs. Thus, in the Edwards ease the court comments (p. 730 [la] of 152 Cal.App.2d), “From the findings and judgment roll it would be reasonable for Curry [general contractor] and the court to believe that the material-man [who requested joint checks] was interested in seeking security for the payment of its claim and if any balance remained it would remit it to the subcontractor; that when the subcontractor endorsed the checks and they were turned over to the materialman, and he placed the funds in the material-man’s general account, so far as the general contractor was concerned, and in the absence of a showing of any other agree ment, it was to that extent, a payment of and should be applied to the account of materials furnished. ...” (Italics added.) And in Westwood the court points out (p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown Wholesale Electric Co. v. Beztak of Scottsdale, Inc.
788 P.2d 73 (Arizona Supreme Court, 1990)
Medford School Dist. v. PETERSON & JONES
708 P.2d 623 (Court of Appeals of Oregon, 1985)
Post Bros. Construction Co. v. Yoder
569 P.2d 133 (California Supreme Court, 1977)
Ewing Irrigation Products v. Rohnert Park Golf Course Corp.
29 Cal. App. 3d 862 (California Court of Appeal, 1973)
Bohannan Bros. v. Lo Jean Development Co.
3 Cal. App. 3d 200 (California Court of Appeal, 1969)
Rodeffer Industries, Inc. v. Chambers Estates, Inc.
263 Cal. App. 2d 116 (California Court of Appeal, 1968)
Rural Plumbing & Heating, Inc. v. Hope Dale Realty, Inc.
140 S.E.2d 330 (Supreme Court of North Carolina, 1965)
Northern Virginia Savings & Loan Ass'n v. J. B. Kendall Co.
135 S.E.2d 178 (Supreme Court of Virginia, 1964)
B. & J. Construction Co. v. Spacious Homes, Inc.
204 Cal. App. 2d 216 (California Court of Appeal, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
366 P.2d 444, 56 Cal. 2d 789, 17 Cal. Rptr. 1, 1961 Cal. LEXIS 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-s-schirm-co-v-rollingwood-homes-co-cal-1961.