B. & J. Construction Co. v. Spacious Homes, Inc.

204 Cal. App. 2d 216, 22 Cal. Rptr. 41, 1962 Cal. App. LEXIS 2235
CourtCalifornia Court of Appeal
DecidedMay 29, 1962
DocketCiv. 25622
StatusPublished
Cited by9 cases

This text of 204 Cal. App. 2d 216 (B. & J. Construction Co. v. Spacious Homes, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B. & J. Construction Co. v. Spacious Homes, Inc., 204 Cal. App. 2d 216, 22 Cal. Rptr. 41, 1962 Cal. App. LEXIS 2235 (Cal. Ct. App. 1962).

Opinion

*218 FILES, J.

This is an action to foreclose a mechanic’s lien on real property. Plaintiff is appealing from the judgment which awarded to it a partial recovery against the contractor, but extinguished the lien.

The complaint alleges that plaintiff and defendant Frank Britton entered into an oral agreement whereby plaintiff was to furnish labor and equipment to grade and fill in certain land; that plaintiff has performed, and that the reasonable value of the balance due is $10,282.11. The complaint further alleges that the property so improved is Tract 24980; that the claim of lien which plaintiff has recorded includes additional property, namely, Tract 23358, on which plaintiff claims no lien. The copy of the recorded claim of lien attached to the complaint states that plaintiff claims a lien on Tracts 23358 and 24980 for labor and equipment furnished to Frank Britton, that the total value of the labor and equipment is $31,388.36, of which $21,106.25 has been paid, leaving a balance of $10,282.11.

A joint answer was filed on behalf of all the named defendants, who will be referred to herein as Spacious Homes (a corporation), Stone Hills (a corporation), Ed Stone, Leo Stone, Stone and Stone, and Frank Britton. This answer admits that the property described in the complaint is owned by Stone Hills. The answer also contains a counterclaim for damages for clouding the title to Tract 23358. On this appeal the counterclaim may be disregarded as it was not specifically mentioned in the findings or judgment, and appellant makes no argument concerning it.

A joint pretrial statement signed by the attorneys for all parties states that plaintiff supplied some earth-moving equipment pursuant to an oral agreement between plaintiff and defendant Britton to grade and otherwise improve “the said real property in issue.” The record does not disclose any other relationship between any of the parties, except that Leo Stone testified that he is the son of Edward Stone and is “an officer in Spacious Homes and Stone Hills and the other Stone entities. ’ ’

The joint pretrial statement lists the matters at issue and contentions as follows: “1. Whether or not the equipment claimed by Plaintiff as having been supplied for the work described in the Complaint was actually so supplied. 2. On the equipment which was supplied, the contention of the Defendants are that there was excess time and excess rates charged by the Plaintiff for said equipment.”

*219 The joint pretrial statement and the resulting pretrial order were a gross violation of the rules requiring that the contentions of the parties be set forth. (California Rules of Court, rules 210, 214.) As will appear, the real contentions of the parties were much more numerous and complex than this statement discloses. The pretrial order appears to have been abandoned by common consent at the trial. A fair statement of the contentions or issues, followed by plainly worded findings of fact and conclusions of law reflecting the trial court’s resolution of those issues, would have resulted in a great saving of the time of this court in its effort to determine whether the judgment is based upon a proper application of the law to facts admitted or found to be true.

At the trial the evidence showed without material conflict the following.

Spacious Homes entered into a written contract dated April 6, 1959, with James S. Walker, whereby Walker was to furnish all labor, materials and equipment to brush, excavate, grade, water and compact (a) for the manufacture of 13 lots and a temporary water line on Tract 24980; (b) for the recompaction of two desilting basins located on Tract 23358; and (c) for smoothing of Weslin Avenue, all in accordance with certain specifications. Spacious Homes (described in the contract as owner) agreed to pay $27,200 for this work. Walker thereafter assigned his interest to defendant Britton, who accepted the agreement, and Spacious Homes consented to the assignment. Britton then orally contracted with plaintiff to do the work, charges to be made at hourly rates for each piece of manned equipment. Plaintiff began work in April and discontinued on July 3, 1959. Daily work tickets were prepared for each item of equipment, and these tickets were periodically summarized on an invoice and submitted to Leo Stone. Prom time to time Leo Stone delivered to Britton checks drawn on Stone Hills as progress payments. These payments totalled $25,361.25. Of this amount, checks totalling $21,856.25 were made payable jointly to plaintiff and Britton. Plaintiff gave defendants credit for $21,106.25.

There is a conflict in the evidence as to the hourly rates which plaintiff agreed to charge Britton, as to what rates were reasonable, as to what extra items should be included, and as to the number of hours the various machines actually worked.

The trial judge, sitting without a jury, found that the reasonable value of the work of improvement furnished by *220 plaintiff was $29,661.85. No specific finding was made as to the amount of the contract price between plaintiff and Britton. The court found that Britton had paid to plaintiff the sum of $21,856.25, leaving a balance due from Britton to plaintiff of $7,805.60. The judgment provided that plaintiff recover this amount from Britton, and denied plaintiff any other relief.

The manner in which the trial court arrived at a figure of $29,661.85 is not disclosed. Prom the evidence the court had a vast number of possible combinations of rates and items from which to select, and we cannot say that this figure, which is almost 95 per cent of what plaintiff claimed, is not supported by evidence.

The more difficult question is whether the findings support that part of the judgment which extinguishes plaintiff’s lien and denies plaintiff any relief against the property.

The Code of Civil Procedure contains two sections bearing upon the forfeiture of a mechanic’s lien. Section 1193.1, subdivision (k), provides:

“Any person who shall willfully include in his claim of lien filed for record pursuant to this chapter work not performed upon, or materials, appliances or power not furnished for, the property described in such claim, shall thereby forfeit his lien.”

Section 1196.1 provides:

“No mistake or errors in the statement of the demand, or of the amount of credits and offsets allowed, or of the balance asserted to be due to claimant, or in the description of the property against which the claim is filed, shall invalidate the lien, unless the court finds that such mistake or error . . . was made with the intent to defraud ... [or unless innocent third parties have been misled].”

It will be noted that section 1193.1, subdivision (k), sets apart two kinds of false claims. These are claims for work not performed on the property, and claims for materials, appliances or power not furnished for the property. To willfully include work not done or materials not furnished is said to result in forfeiture as a matter of law. However, section 1193.1, subdivision (k), applies only where there is an actual intent to defraud. (Henley v. Pacific Fruit etc. Co., 19 Cal.App. 728, 734 [127 P. 800].)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carmel Development Co., Inc. v. Anderson
California Court of Appeal, 2020
ED McGILLICUDDY CONSTR. v. KNOLL RECREATION ASSN
31 Cal. App. 3d 891 (California Court of Appeal, 1973)
E. D. McGillicuddy Construction Co. v. Knoll Recreation Ass'n
31 Cal. App. 3d 891 (California Court of Appeal, 1973)
Ewing Irrigation Products v. Rohnert Park Golf Course Corp.
29 Cal. App. 3d 862 (California Court of Appeal, 1973)
A. J. Raisch Paving Co. v. Mountain View Savings & Loan Ass'n
28 Cal. App. 3d 832 (California Court of Appeal, 1972)
Thrifty Supply Co. of Seattle, Inc. v. Deverian Builders, Inc.
475 P.2d 905 (Court of Appeals of Washington, 1970)
A. A. Baxter Corp. v. Home Owners & Lenders
7 Cal. App. 3d 725 (California Court of Appeal, 1970)
Rodeffer Industries, Inc. v. Chambers Estates, Inc.
263 Cal. App. 2d 116 (California Court of Appeal, 1968)
Distefano v. Hall
218 Cal. App. 2d 657 (California Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
204 Cal. App. 2d 216, 22 Cal. Rptr. 41, 1962 Cal. App. LEXIS 2235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-j-construction-co-v-spacious-homes-inc-calctapp-1962.