A. J. Raisch Paving Co. v. Mountain View Savings & Loan Ass'n

28 Cal. App. 3d 832, 105 Cal. Rptr. 96, 1972 Cal. App. LEXIS 800
CourtCalifornia Court of Appeal
DecidedNovember 21, 1972
DocketCiv. 29755
StatusPublished
Cited by5 cases

This text of 28 Cal. App. 3d 832 (A. J. Raisch Paving Co. v. Mountain View Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. J. Raisch Paving Co. v. Mountain View Savings & Loan Ass'n, 28 Cal. App. 3d 832, 105 Cal. Rptr. 96, 1972 Cal. App. LEXIS 800 (Cal. Ct. App. 1972).

Opinion

Opinion

TAYLOR, P. J.

Defendant, Mountain View Savings and Loan Association (Savings and Loan), appeals a judgment after a court trial foreclosing a mechanic’s lien of plaintiff, A. J. Raisch Paving Company (Raisch) on tentative subdivision Tract 2634 owned by Savings and Loan in the City of Newark (City), in the amount of $16,068.15, with interest at 7 percent, together with costs of suit. Savings, and Loan contends that the claim of lien was not timely filed and even if so, the costs of the sewer on Robertson Avenue, that also benefited completed subdivision Tract 2633, must be apportioned. For the reasons set forth below, we have concluded that the lien was timely filed but the cost of the Robertson Avenue sewer must be apportioned between Tract 2634 and Tract 2633.

The undisputed material facts are as follows: On May 12, 1964, the original owner, Donald L. Stone Homes, Inc. (Stone), had filed with the City a tentative subdivision map for Tract 2634, which had been approved by the City planning commission pursuant to City Ordinance No. 62. 1 The one-year period for filing a final subdivision map, which commenced May 12, 1964, was subsequently extended by the planning commission for one year commencing May 12, 1965.

Stone, on November 25, 1964, contracted with Raisch to install certain “street paving, curbs, gutters, sidewalks, drive approaches, sanitary and storm sewers, water lines, street trees, monuments, barricades, street signs and lot grading” in Tract 2634. The contract provided that “All work is to be done in accordance with the plans and specifications and to the satisfac *835 tion and acceptance of the Superintendent of Streets and/or the City Engineer for the City of Newark."

Subsequent to the date of its contract with Stone, Raisch entered into a subcontract with W. H. Ebert Corporation-Spartan Construction Corporation (Ebert) on February 25, 1965, pursuant to which Ebert agreed to install sanitary sewers for the tract. Raisch commenced work on the tract pursuant to its contract subsequent to November 25, 1964. The last work performed by Raisch was on September 13, 1965, at which time, Raisch had completed a $10,000 portion of the lot and site grading. As of September 13, 1965, Ebert had already completed its sewer installations and had billed Raisch accordingly. Ebert included in his bill to Raisch the sewer line installed on Robertson Avenue, a public street, pursuant to Newark City final and recorded map for the adjacent Tract 2633 that Stone then also owned. The sewer lines installed in Robertson Avenue were also intended for the purpose of servicing tentative Tract 2634 at such time as it was, in fact, subdivided and developed. This Robertson Avenue sewer line was accepted by the Union Sanitary District and Tract 2633 was accepted and approved by the City of Newark. No lien was filed against Tract 2633 within the time prescribed by former Code of Civil Procedure sections 1193.1, subdivision (d), and 1193.1, subdivision (e). 2

No permits for work to be performed in Tract 2634 were obtained nor was the tentative map approved by the planning commission ever submitted to the City council for final approval nor were the requirements prior to recordation of a final map, as called for in the Subdivision Map Act and the ordinances of the City of Newark, ever carried out by either Stone or Raisch.

Raisch billed Stone for the work completed, in the amount of $16,068.15, comprised of $10,000 for the work performed by Raisch, and of $6,068.15 for the sewer work performed by Ebert. This bill was never paid. Following the last work performed by Raisch under its contract with Stone, Savings and Loan recorded on January 12, 1966, a grant deed purporting to give it title to Tract 2634. In fact, the testimony shows that the grant deed to Savings and Loan merely created a security interest subject to vesting of both legal and equitable title if Stone failed to meet his financial commitments on or before June 30, 1966.

*836 On December 29, 1966, Raisch served upon Savings and Loan a written notice in accordance with section 1193 of the Code of Civil Procedure. Notice of claim of lien was filed on February 8, 1967, and suit was filed upon the claim of lien on May 2, 1967. At the trial, the court found for Raisch and against Savings and Loan.

Savings and Loan first contends that Raisch’s claim of lien was not timely filed under the requirements of former section 1193.1, subdivision (d), of the Code of Civil Procedure which provided that in case of cessation of labor for a continuous period of 60 days, the claim of lien must be recorded within 90 days from the expiration of such 60-day period. Raisch argues that its claim of lien comes within the exception to 1193.1, subdivision (d), set forth in subdivision (e), as follows: “If the work of the improvement is subject to acceptance by any public or governmental authority, the completion of such work of improvement shall be deemed to be the date of such acceptance” (italics added). The crucial question is whether or not the work of improvement performed by Raisch was “subject to acceptance by any public or governmental authority.” If so, the claim of lien was timely filed as the improvement was never, in fact, accepted by the City and thus never completed.

Raisch properly relies on the case of Howard A. Deason & Co. v. Costa Tierra Ltd., 2 Cal.App.3d 742 [83 Cal.Rptr. 105], that authoritatively defines “subject to acceptance” in section 1193.1, subdivision (e). In Deason, as in this case, the primary issue was whether the evidence sustained the finding that the project was subject to acceptance by public or governmental authority. The court stated at page 751: “We hold that the phrase ‘subject to acceptance’ as set forth in section 1193.1, subdivision (e) is not to be equated with inspection and approval or the issuance of certificates of occupancy under building regulations, but must find its base in some legislative enactment by the public authority” (italics added). The court then proceeded to find that since the contract for the installation of streets, curbs and gutters was by city ordinance made subject to acceptance through the issuance of a certificate-by the city engineer and there was no evidence that the city had actually ever accepted the work of improvment, it had never been completed as provided in section 1193.1, subdivision (e), and plaintiff’s claim of lien thereon was timely filed. Southwest Paving Co. v. Stone Hills, 206 Cal.App.2d 548 [24 Cal.Rptr. 48], holds to the same effect in relation to a subcontractor’s hen. 3

*837 Savings and Loan argues that the subdivision work was not “subject to acceptance” because the tentative subdivision map had not been submitted to the City council for final approval nor had the permits been obtained nor the requirements prior to recordation of final map, as called for by the Subdivision Map Act and City Ordinance 62, been performed. We see no merit in this contention. As noted in Deason,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palomar Grading v. Wells Fargo
California Court of Appeal, 2014
R&R Pipeline, Inc. v. Bond Safeguard Insurance
223 Cal. App. 4th 438 (California Court of Appeal, 2014)
Rental Equipment, Inc. v. McDaniel Builders, Inc.
109 Cal. Rptr. 2d 922 (California Court of Appeal, 2001)
Burton v. Sosinsky
203 Cal. App. 3d 562 (California Court of Appeal, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
28 Cal. App. 3d 832, 105 Cal. Rptr. 96, 1972 Cal. App. LEXIS 800, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-j-raisch-paving-co-v-mountain-view-savings-loan-assn-calctapp-1972.