Rental Equipment, Inc. v. McDaniel Builders, Inc.

109 Cal. Rptr. 2d 922, 91 Cal. App. 4th 445, 2001 Daily Journal DAR 8495, 2001 Cal. Daily Op. Serv. 6939, 2001 Cal. App. LEXIS 626
CourtCalifornia Court of Appeal
DecidedAugust 9, 2001
DocketB139044
StatusPublished
Cited by2 cases

This text of 109 Cal. Rptr. 2d 922 (Rental Equipment, Inc. v. McDaniel Builders, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rental Equipment, Inc. v. McDaniel Builders, Inc., 109 Cal. Rptr. 2d 922, 91 Cal. App. 4th 445, 2001 Daily Journal DAR 8495, 2001 Cal. Daily Op. Serv. 6939, 2001 Cal. App. LEXIS 626 (Cal. Ct. App. 2001).

Opinion

Opinion

ARMSTRONG, J.

Rental Equipment, Inc., appeals from a judgment in favor of respondents McDaniel Builders, Inc. and Developers Insurance Company, on its action for foreclosure on a mechanic’s lien. We affirm.

Summary

A preliminary notice under Civil Code 1 section 3097 is a necessary prerequisite to enforcement of a mechanic’s lien. (§ 3097, subd (a).) Such a notice must include “A general description of the labor, service, equipment, or materials furnished, or to be furnished, and an estimate of the total price thereof.” (§ 3097, subd. (c)(1).) In this case, the preliminary notices gave estimates of $10,000, but the ensuing mechanic’s lien was in the amount of $159,898. The trial court found that the notices were fatally defective because they did not give an estimate of the total price, that is, they did not give a figure which was derived by a rational process, based upon relevant factors.

This case thus presents a question about the meaning of the word “estimate” in section 3097. We agree with the trial court that the statute requires “a derived figure, arrived at by rational analysis,” and further find substantial evidence for the trial court finding that the $10,000 estimates here were not so derived. We thus affirm the judgment.

Facts

In 1997, a group of investors, the O’Donnell Group, contracted with respondent McDaniel to demolish the buildings, foundations, walkways, and curbs on a site in Santa Fe Springs. McDaniel subcontracted with Specialty Steel. Specialty Steel’s $75,000 bid was the lowest bid by a significant amount, but McDaniel president Robert McDaniel believed it was reasonable, since Specialty Steel would be allowed to keep the salvaged materials and had already made arrangements to sell those materials. McDaniel’s subcontract with Specialty Steel was executed on September 17, 1997. Under the subcontract, Specialty Steel’s work was to take no more than six weeks, though the work was actually delayed due to rain.

*448 McDaniel erroneously believed that Specialty Steel was licensed. He based this belief on the fact that Specialty Steel’s proposal and subcontract agreement bore a license number.

Specialty Steel arranged to rent equipment from appellant and furnished appellant with a credit application. Appellant established a $10,000 line of credit for Specialty Steel. Appellant’s equipment began arriving at the project in mid-October. The first piece was an 80-foot lift. Appellant filed two.20-day notices, on November 14 and 24, 1997. Each notice gave an estimate of $10,000.

The November 14 notice identified the equipment that had been or would be furnished as “rental of construction equipment, includes: 80’ straight lift.” By that date, appellant had billed specialty Steel $8,232. A part of that, $7,800, was for the 80-foot lift. Specialty Steel had by then rented a 60-foot boom, an 80-foot boom, a backhoe, and a trak loader from appellant for the Santa Fe Springs project. The November 24 notice identified a trak loader as the equipment furnished or to be furnished. By that time, appellant had billed Specialty Steel over $23,000.

A Miss Anson of Specialty Steel prepared the preliminary notices. She did not testify at trial. For appellant, Robert Breitenstein testified as the person most knowledgeable about this lien claim, but testified that he did not know how the estimates in the preliminary notices were derived.

McDaniel testified that he examined each preliminary notice as it came in, because “that’s the only indication I have from a subtiered supplier of the amount of work and services that they are going to provide ... by looking at the 20-day notices, that tells me how much exposure there is . . . .” He also testified that if either lien had given a $100,000 estimate, he would have immediately called a meeting with appellant and Specialty Steel to advise appellant of the $75,000 contract price and avoid later problems.

By mid-January, Specialty Steel had substantially completed the project, although a few punch list items, such as removal of trash, remained. Robert McDaniel informed Specialty Steel that it would not be paid until the punch list was completed and until lien releases were obtained from appellant and another supplier. Specialty Steel did not meet those requirements and McDaniel did not make the payment.

Specialty Steel never paid any of appellant’s invoices. Appellants filed a mechanic’s lien on January 29, 1998. McDaniel’s contract with O’Donnell required that he deliver the project free of liens. Ultimately, O’Donnell *449 required McDaniel to bond around the liens. McDaniel obtained a bond from respondent Developers Insurance for that purpose.

This lawsuit followed. 2 The case went to trial on appellant’s cause of action for foreclosure of its claim for a mechanic’s lien and was tried to the court. As we have noted, the trial court ruled that the statue required “a derived figure, arrived at by rational analysis,” and that while estimate does not mean “precision or exactness,” it does mean more than “guess, conjecture, or surmise,” and that the statute is a “simple and straightforward call for an estimated total price of its labor, services and equipment.” The court further found that the amounts appellant estimated on the preliminary notices was a figure “that was not derived by any rational process, that it had no bearing whatsoever on the actual work done and to be done on the project and that it was, in truth and in fact, made out of whole cloth. The stark factual reality of this case is that [appellant’s] dollar figure of $10,000 was not even a guess, much less an estimate.”

Discussion

We begin with appellant’s discussion of the trial court’s ruling on the meaning of the word “estimate” in section 3097. The ruling is one of law, and we conduct an independent review. (People v. Duz-Mor Diagnostic Laboratory, Inc. (1998) 68 Cal.App.4th 654, 660 [80 Cal.Rptr.2d 419].)

In construing a statute, courts must afford words their ordinary commonsense meaning, given “the evident purpose for which the statute was adopted.” (In re Rojas (1979) 23 Cal.3d 152, 155 [151 Cal.Rptr. 649, 588 P.2d 789].) The dictionary definition of “estimate” is “an approximate computation of the probable cost of a piece of work made by a person undertaking to do the work.” (Webster’s New World Diet. (3d college ed. 1993) p. 465.) Thus, in ordinary use, an estimate is a figure that has been arrived at through a reasonable and logical attempt to determine the final number. That is the meaning the trial court gave the word here.

This meaning is in accord with the evident purpose of the statute. As appellant argues, the statute is “ ‘remedial legislation, to be liberally construed for the protection of laborers and materialmen.’ ” (Kim v. JF Enterprises (1996) 42 Cal.App.4th 849, 854 [50 Cal.Rptr.2d 141].) However, “ ‘ “[w]hile the essential purpose of the mechanics’ lien statutes is to protect *450

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T.O. IX, LLC v. Superior Court
165 Cal. App. 4th 140 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
109 Cal. Rptr. 2d 922, 91 Cal. App. 4th 445, 2001 Daily Journal DAR 8495, 2001 Cal. Daily Op. Serv. 6939, 2001 Cal. App. LEXIS 626, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rental-equipment-inc-v-mcdaniel-builders-inc-calctapp-2001.