Blair Excavators, Inc. v. Paschen Contractors, Inc.

9 Cal. App. 4th 1815, 12 Cal. Rptr. 2d 420, 92 Cal. Daily Op. Serv. 8387, 92 Daily Journal DAR 13817, 1992 Cal. App. LEXIS 1201
CourtCalifornia Court of Appeal
DecidedOctober 6, 1992
DocketA052744
StatusPublished
Cited by3 cases

This text of 9 Cal. App. 4th 1815 (Blair Excavators, Inc. v. Paschen Contractors, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blair Excavators, Inc. v. Paschen Contractors, Inc., 9 Cal. App. 4th 1815, 12 Cal. Rptr. 2d 420, 92 Cal. Daily Op. Serv. 8387, 92 Daily Journal DAR 13817, 1992 Cal. App. LEXIS 1201 (Cal. Ct. App. 1992).

Opinion

Opinion

PETERSON, J. *

This appeal follows a trial to the court on public project bond claims concerning unpaid construction bills, after a subcontractor’s 90-day preliminary bond notice and a 20-day preliminary stop notice under Civil Code 1 sections 3091 and 3098. In the published portion of this opinion, we will hold, in affirming the judgment, that the statutory requirement of “substantial accuracy” in the statement of the amount claimed in a bond notice under section 3091 was designed to avoid prejudice to the party claimed against and that, in the absence of any such prejudice, a plaintiff may recover an amount greater than that stated in the initial section 3091 notice.

I. Facts and Procedural History

For present purposes, the facts may be briefly summarized. Blair Excavators, Inc. (Blair), respondent herein, performed certain excavating work on a public wastewater treatment project in Marin County; in connection with the project, appellant general contractor executed a bond in the amount of more than $43 million. Blair performed its work as a subcontractor to Ferrante Construction Company, which in turn was a subcontractor to and in privity of contract with appellant general contractor. Ferrante and Blair had a falling *1818 out after Blair had performed substantial work; Blair contended it was not paid for all of the work it did. Ferrante subsequently declared bankruptcy and is not a party to this litigation.

Blair gave statutory notices of its claim to appellant general contractor, seeking payment of the amounts which Ferrante did not pay. Blair sent a 90-day preliminary bond notice under the terms of section 3091, and a 20-day preliminary stop notice under section 3098. Both notices specified the amount due pursuant to Blair’s subcontract with Ferrante, slightly more than $200,000. Blair subsequently brought suit pursuant to its bond notices.

At trial, the court allowed Blair to prove damages in excess of the $200,000 which was owing by Ferrante—in accord with California precedents holding that it is the reasonable value of the services provided, not the price specified in a contract with a party which is not before the court, which is the proper measure of damages in an action such as this one where the general contractor defendant is not contractually in privity with the plaintiff subcontractor of an intermediate subcontractor. The trial court also ruled that appellant general contractor here would suffer no prejudice from facing a claim in excess of the approximately $200,000 specified in the 90-day notice.

The trial court ruled that Blair should collect $335,000 as the reasonable value of the unpaid work. The trial court also awarded prejudgment interest on this sum from the date of suit. Appellant general contractor and its sureties (hereafter appellants) brought a timely appeal.

II. Discussion

A. Respondent May Recover an Amount Greater Than That Stated in a Preliminary Bond Notice Since Appellants Were Not Thereby Prejudiced

We affirm. The trial court properly awarded damages and interest in the particular circumstances of this case; appellants’ contentions to the contrary are without merit.

Appellants primarily claim that Blair’s recovery should have been limited to the amount of its contract price with Ferrante, slightly more than $200,000, which was also the amount stated in the bond notices. However, the trial court properly concluded that the correct measure of damages here was the reasonable value of the services rendered, not the contract price, since appellant general contractor was not in privity with Blair, the subcontractor of a subcontractor. (See, e.g., Lewis & Queen v. S. Edmondson & Sons (1952) 113 Cal.App.2d 705, 707 [248 P.2d 973]; accord, Powers Regulator Co. v. Seaboard Surety Co. (1962) 204 Cal.App.2d 338, 345 [22 Cal.Rptr. 373].)

*1819 Further, the trial court found that Ferrante had required Blair to do much work on the project which was not within the scope and terms of the original project, causing the value of Blair’s work to exceed the contract price.

The primary legal issue raised on this appeal, however, arises from the fact Blair’s bond notice claimed only about $200,000, although at trial it sought to prove the reasonable value of its services greatly exceeded that figure. The trial court found that, although the value proved at trial for Blair’s services exceeded the roughly $200,000 it had claimed previously in the 90-day bond notice, Blair’s recovery should not be limited to the amount stated in the bond notice since Blair had complied with the demand of section 3091, requiring the amount claimed to be stated with “substantial accuracy”; and that appellant general contractor and its sureties had not been at all prejudiced by the difference in the amounts stated. There is no authority directly on point as to whether the amount stated with “substantial accuracy” in the bond notice provides an absolute upper limit on a plaintiff’s claim at trial. We agree with the trial court’s ruling that, in the absence of a showing of prejudice, the amount of the section 3091 notice does not limit the amount of recovery. Further, the trial court properly found no prejudice here.

Appellants even now point to no solid, actual prejudice suffered as a result of the difference in the amounts (the general contractor did not claim it would have paid the claim if it had been for more than $200,000), but simply conjecture there might have been some prejudice. We will not overturn the trial court’s ruling based upon mere speculation. Appellants cite no cases, nor have we found any, which would limit the amount of the reasonable value of services to be awarded on a section 3091 claim to the amount stated in the plaintiff’s preliminary bond notice. To the contrary, the courts have liberally construed these statutory remedies enacting mechanic’s liens, in order to provide adequate compensation for those providing materials or services to public works projects. (Connolly Development; Inc. v. Superior Court (1976) 17 Cal.3d 803, 826-827 [132 Cal.Rptr. 477, 553 P.2d 637]; Hutnick v. United States Fidelity & Guaranty Co. (1988) 47 Cal.3d 456, 462 [253 Cal.Rptr. 236, 763 P.2d 1326].)

For instance, in California Elec. Supply Co. v. United Pac. Life Ins. Co. (1964) 227 Cal.App.2d 138, 147 [38 Cal.Rptr. 479], Division One of this district interpreted the “substantial accuracy” provision, as then stated in Government Code section 4209, as requiring only that “the nature and state of plaintiff’s claim [be] brought home to [the] prime contractor” by a schedule of work completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rental Equipment, Inc. v. McDaniel Builders, Inc.
109 Cal. Rptr. 2d 922 (California Court of Appeal, 2001)
MCM Constr., Inc. v. City & County of San Francisco
78 Cal. Rptr. 2d 44 (California Court of Appeal, 1998)
Granite Constr. Co. v. Am. Motorists Ins. Co.
29 Cal. App. 4th 658 (California Court of Appeal, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
9 Cal. App. 4th 1815, 12 Cal. Rptr. 2d 420, 92 Cal. Daily Op. Serv. 8387, 92 Daily Journal DAR 13817, 1992 Cal. App. LEXIS 1201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blair-excavators-inc-v-paschen-contractors-inc-calctapp-1992.