Fidelity Sound Systems. Inc. v. American Bonding Co.

85 Cal. App. Supp. 3d 13, 149 Cal. Rptr. 674, 1978 Cal. App. LEXIS 1999
CourtAppellate Division of the Superior Court of California
DecidedAugust 25, 1978
DocketCiv. A. No. 14100
StatusPublished
Cited by8 cases

This text of 85 Cal. App. Supp. 3d 13 (Fidelity Sound Systems. Inc. v. American Bonding Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Superior Court of California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity Sound Systems. Inc. v. American Bonding Co., 85 Cal. App. Supp. 3d 13, 149 Cal. Rptr. 674, 1978 Cal. App. LEXIS 1999 (Cal. Ct. App. 1978).

Opinion

Opinion

COLE, P. J.

Sevkija Vrgora was the general contractor on a job for the Los Angeles City Unified School District. American Bonding Company issued his labor and material bond. They are the appellants here. “220 Electric,” not a party to this appeal, was an electrical subcontractor for Vrgora. It purchased some materials from Fidelity Sound Systems, Inc. (Fidelity), the respondent. Vrgora paid 220 Electric for the materials but the latter did not pay Fidelity. On May 7, 1975, Fidelity filed a stop notice with the school district and on May 14, 1975, the contract section of the district forwarded to the claims paying section a memorandum regarding the stop notice. Appellants, among others, received copies of this memorandum, which went by ordinary and not by certified or registered mail. A notice of completion was recorded September 3, 1975. It states “Physical Completion of work 1-23-75.” It also states, although the parties fail to mention this fact, that “the contract has been completed and was accepted by the Board of Education on the 28th day of August, 1975.” On March 2, 1976, the school district’s contract section sent a memorandum to the claims paying section releasing the notice to withhold which had been based on Fidelity’s stop notice. Copies of the memorandum went to appellants. The reason stated for the release was [Supp. 17]*Supp. 17“Failure of Claimant to commence court proceedings to enforce the claim and to give the District timely notice thereof. (CC3210 and 3211.)” The instant action was commenced on February 3, 1976.

Fidelity sued appellants for the money owing to it and received judgment. Appellants urge reversal on two separate grounds: (1) The action was barred by the statute of limitation set forth in Civil Code section 3249.1 (2) Fidelity failed to comply with the preliminary bond notice requirements of section 3091, and thus is disenabled from maintaining the action. Neither contention is well founded. We affirm.

Statute of Limitation Issue

Resolution of the statute of limitation question requires a circuitous trip through the laws relating to claims by materialmen on public works, interspersed in the mechanics’ liens statutes. (§§ 3082 through 3267.) Our trip begins with the statute of limitation here applicable, section 3249:

“Suit against the surety or sureties on the payment bond may be brought by any claimant, or his assigns, at any time after the claimant has furnished the last of the labor or materials, or both, but must be commenced before the expiration of six months after the period in which stop notices may be filed as provided in Section 3184.”

The next stop is section 3184:

“To be effective, any stop notice pursuant to this chapter must be served before the expiration of: (a) Thirty days after the recording of a notice of completion (sometimes referred to in public works as a notice of acceptance) or notice of cessation, if such notice is recorded, (b) If no notice of completion or notice of cessation is recorded, 90 days after completion or cessation.”

The parties argue whether the notice of completion was properly recorded. Appellants point out that section 3093 provides for such recordation within 10 days after actual completion of a work. Thus, they argue, citing Doherty v. Carruthers (1959) 171 Cal.App.2d 214 [340 P.2d 58], the notice of completion recorded here is invalid on its face. The next [Supp. 18]*Supp. 18step in the reasoning is that the 90-day provision of section 3184, subdivision (b), applies, so that the action had to be filed within 90 days of January 23, 1975, the date of physical completion. Respondent meets this argument head on. It argues that if the notice of completion is valid, the instant action clearly was filed in time: i.e., under section 3184 a stop notice might be filed within 30 days of September 3, 1975, when the notice of completion was recorded, and the action did not have to be brought until six months after the 30-day period, or in other words, in April 1976. Since the action was filed on February 3, 1976, it would be timely.

We note in passing that the purpose of notices of completion is to protect the owner by shortening the time period in which stop notices or mechanics’ lien claims may be filed. Therefore, when an owner delays in such filing he only injures himself, by rendering the recorded notice ineffective. It does not necessarily follow, then, that the fact that a stop notice is ineffective under section 3093 controls the statute of limitation problem which we are discussing. But, with the parties, we will assume that it does. On this basis, respondent urges, quite correctly, that a new port of call, section 3086, must be visited. We do not accept the detail of respondent’s reasoning, which is based on the false premise that the notice of completion was invalid. In our view section 3086 shows that it is valid, as follows: Under section 3093 a notice of completion must be recorded within 10 days after the completion of the work. But “completion” is itself defined by section 3086. And in the case of a public work of improvement, such as is here involved, the definition of “completion” is that it is “the date of acceptance.” We have already noted that the notice of completion sets forth that date as August 28, 1975. It follows that the notice of completion need not have been filed for 10 days thereafter. It was filed within that period.

To avoid this conclusion appellant urges that completion is not the date of acceptance because of the last clause of section 3086. We quote here the applicable last paragraph of the section: “If the work of improvement is subject to acceptance by any public entity, the completion of such work of improvement shall be deemed to be the date of such acceptance; provided, however, that, except as to contracts awarded under the State Contract Act, [citation omitted] a cessation of labor on any public work for a continuous period of 30 days shall be a completion thereof.”

[Supp. 19]*Supp. 19The only dates which might relate to any cessation of labor which appear in the record are the enigmatic reference “Physical Completion of work 1-23-75” on the notice of completion, and the reference in the agreed statement to testimony of respondent’s president that respondent’s work dockets show the last day of work “actually performed” by respondent-to be March 28, 1975.

Neither of these dates establish a “cessation of labor” such as to require an earlier filing of the notice of completion. These dates apparently refer to actual completion of contracts for the work. As used in section 3086, actual completion of a contract is not the cessation of labor referred to in the statute. (Southwest Paving Co. v. Stone Hills (1962) 206 Cal.App.2d 548, 554 [24 Cal.Rptr. 48] (referring to predecessor § 1193.1 of the Code Civ. Proc.); Mott v. Wright (1919) 43 Cal.App. 21, 27 [184 P. 517](referring to predecessor § 1187 of the Code Civ. Proc.).)

Accordingly, the notice of completion was properly filed and the action was timely brought.

Preliminary Bond Notice Issue

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fontana Paving, Inc. v. Hedley Brothers, Inc.
38 Cal. App. 4th 146 (California Court of Appeal, 1995)
Granite Constr. Co. v. Am. Motorists Ins. Co.
29 Cal. App. 4th 658 (California Court of Appeal, 1994)
Blair Excavators, Inc. v. Paschen Contractors, Inc.
9 Cal. App. 4th 1815 (California Court of Appeal, 1992)
Krueger Bros. Builders, Inc. v. San Francisco Housing Authority
198 Cal. App. 3d 1 (California Court of Appeal, 1988)
San Joaquin Blocklite, Inc. v. Willden
184 Cal. App. 3d 361 (California Court of Appeal, 1986)
IGA Aluminum Products, Inc. v. Manufacturers Bank
130 Cal. App. 3d 699 (California Court of Appeal, 1982)
Gary C. Tanko Well Drilling, Inc. v. Dodds
117 Cal. App. 3d 588 (California Court of Appeal, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
85 Cal. App. Supp. 3d 13, 149 Cal. Rptr. 674, 1978 Cal. App. LEXIS 1999, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-sound-systems-inc-v-american-bonding-co-calappdeptsuper-1978.