Fontana Paving, Inc. v. Hedley Brothers, Inc.

38 Cal. App. 4th 146, 45 Cal. Rptr. 2d 295, 95 Daily Journal DAR 12265, 95 Cal. Daily Op. Serv. 7207, 1995 Cal. App. LEXIS 882
CourtCalifornia Court of Appeal
DecidedSeptember 11, 1995
DocketF022447
StatusPublished
Cited by5 cases

This text of 38 Cal. App. 4th 146 (Fontana Paving, Inc. v. Hedley Brothers, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fontana Paving, Inc. v. Hedley Brothers, Inc., 38 Cal. App. 4th 146, 45 Cal. Rptr. 2d 295, 95 Daily Journal DAR 12265, 95 Cal. Daily Op. Serv. 7207, 1995 Cal. App. LEXIS 882 (Cal. Ct. App. 1995).

Opinion

Opinion

THAXTER, J.

We hold here that a mechanic’s lien claim recorded more than 90 days after completion of the work of improvement is ineffective notwithstanding a later filed notice of completion which erroneously recites a completion date postdating the claim of lien. As we read the applicable statutes, 1 a valid notice of completion serves to shorten the lien-claim filing period. An invalid notice of completion has no legal effect, although it may furnish a factual basis for estopping a statute of limitations defense. Because there was no evidence supporting estoppel here, we will reverse the trial court’s judgment in favor of the lien claimant.

Factual and Procedural Background

Appellant Hedley Brothers, Inc. (Hedley) was the general contractor engaged to construct a Wal-Mart Store in Ridgecrest, Kern County, on property owned by Wal-Mart Stores, Inc. The written construction contract was dated May 17, 1990, and provided for substantial completion of the work no later than December 18, 1990. Hedley, in turn, entered into a subcontract with L M Contracting, Inc. (L M) for the asphalt paving work associated with the project. Respondent Fontana Paving, Inc. (Fontana) furnished asphaltic concrete materials to the subcontractor at the jobsite.

*150 L M completed its paving work before December 31, 1990, and Hedley paid it $295,000, leaving an unpaid retention of only $1,350. L M did not pay Fontana for all materials supplied, leaving an unpaid balance of $72,709.33.

The entire work of improvement was completed no later than January 23, 1991. The City of Ridgecrest issued a certificate of occupancy and the Wal-Mart Store opened for business in January. No notice of completion was recorded at that time.

On March 1, 1991, Fontana recorded a mechanic’s lien claim for the $72,709.33 balance due it. Unfortunately, the claim was filed in San Bernardino County rather than Kern County, in which the property was located. 2

On March 25, 1991, Fontana executed an “Unconditional Waiver and Release Upon Progress Payment” pursuant to section 3262, subdivision (d)(2). The release form acknowledged that Fontana had been paid and received a progress payment of $1,350 3 for material furnished to the project, and it released “pro tanto any mechanic’s lien” which Fontana had on the job for materials furnished to Hedley and L M “through Dec. 31, 1991 [szc]” except for “any retention or items furnished after that date.” Before signing the waiver and release form, Fontana’s credit manager altered it by adding a typewritten notation: “This [$1,350 payment] is only a partial payment of monies owed thru 12-31-90. There is still a balance of $71,359.33.”

On June 4, 1991, Fontana, having discovered that its original lien claim was filed in the wrong county, recorded a new claim of lien in Kern County.

On June 25,1991, Hedley recorded in Kern County a notice of completion for the project. The notice was dated June 18, 1991, and recited that the work of improvement was completed on that date. The notice was signed by Thomas D. Eads, Hedley’s vice-president. Immediately under the signature *151 line on the printed form appeared the words: “Signature of owner or corporate officer of owner named in paragraph 2 or his agent.” 4

Fontana filed this action on July 19, 1991, against L M, Hedley, Wal-Mart Stores, Inc., and other defendants, seeking various forms of relief, including foreclosure of its mechanic’s lien recorded on June 4. On April 13, 1993, Hedley recorded a release of lien bond pursuant to section 3143, and Wal-Mart Stores, Inc. was thereafter dismissed from the action with prejudice. Fontana then filed a supplemental complaint adding a cause of action on the release bond against Hedley, as principal, and appellant Federal Insurance Company, as surety. Hedley and Federal Insurance Company filed a general denial and asserted various affirmative defenses. One affirmative defense alleged that the action was barred because Fontana’s claim of lien was not timely filed in accordance with section 3116. Another asserted that the notice of completion was invalid pursuant to section 3093.

The case was tried without a jury. After submission the court issued a written ruling ordering judgment for Fontana against L M for $71,359.33 plus interest, costs, and attorney fees, and directing that the proceeds of the mechanic’s lien release bond issued by Federal Insurance Company on behalf of Hedley be released to Fontana in the amount of $71,359.33 plus interest and costs. 5

In its written ruling the court made certain findings, including:

“2. For purposes of section 3116, the work of improvement was completed no later than January 23, 1991. . . .
“3. [Fontana] properly filed its Mechanic’s Lien in Kern County on June 4, 1991 . . . which was more than 90 days after the work of improvement was completed. Accordingly, Fontana may not rely upon section 3116(a) to enforce the Lien.
*152 “4. [Hedley] filed a Notice of Completion on June 25, 1991 . . . which was signed by Thomas D. Eads, employed by Hedley. For purposes of signing the Notice, Hedley/Eads was the agent of Wal-Mart Stores, Inc., the owner. Hedley prepared/generated the Notice on its own.
“5. The Notice, even though it contains an erroneous date of completion, i.e., June 18, 1991, is valid. Hedley is estopped from arguing that the Notice, which it [Hedley] prepared for its own purposes, is invalid as violative of Civil Code section 3093.
“6. If Hedley had not filed the Notice, Fontana would be ‘out of luck’ in foreclosing the Lien. Since the Notice is valid, Fontana would have been entitled to rely upon it in filing the Lien 30 days after its recordation. In reality, the Lien was filed 30 days before the Notice. Accordingly, the Lien is premature.
“7. In enforcement of any lien, a claimant may opt to wait to file its lien until 30 days after recordation of a notice of completion, (section 3116 (b)) The key policy behind section 3116 (b) is that the claimant, such as Fontana, is entitled to rely upon the notice of completion to protect and enforce its rights. In this case, Fontana relied upon the fact that a notice of completion had not been filed in making its decision to file the Lien.
“8. In Century Superior Gunite, Inc. v. Rodriguez (1981) 118 Cal App 3d Supp. 12 [173 Cal.Rptr. 661], the Appellate Department, Superior Court, Los Angeles, dealt with the issue of prematurity as it relates to section 3116 and the filing of a lien prior to completion of the work of improvement. In discussing this issue, the court said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chase Manhattan Mortgage Corp. v. Caraway
2003 NMCA 020 (New Mexico Court of Appeals, 2002)
DEPARTMENT OF INDUS. REL. v. Fidelity Roof Co.
60 Cal. App. 4th 411 (California Court of Appeal, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cal. App. 4th 146, 45 Cal. Rptr. 2d 295, 95 Daily Journal DAR 12265, 95 Cal. Daily Op. Serv. 7207, 1995 Cal. App. LEXIS 882, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fontana-paving-inc-v-hedley-brothers-inc-calctapp-1995.