Heberling v. Day

209 P. 908, 59 Cal. App. 13, 1922 Cal. App. LEXIS 119
CourtCalifornia Court of Appeal
DecidedAugust 31, 1922
DocketCiv. No. 2433.
StatusPublished
Cited by9 cases

This text of 209 P. 908 (Heberling v. Day) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heberling v. Day, 209 P. 908, 59 Cal. App. 13, 1922 Cal. App. LEXIS 119 (Cal. Ct. App. 1922).

Opinion

HART, J.

The plaintiffs instituted actions in the superior court of Tulare County for the foreclosure of certain liens for materials furnished for and labor performed on the construction of a certain building in the city of Visalia, and also for recovery of judgments against the sureties upon the bond furnished by the contractor to the owner of the building for the faithful performance of the terms of the building contract to satisfy the several demands sued for. By order of the court the actions were consolidated. (Sec. 1195, Code Civ. Proc.)

On the third day of May, 1917, one D. B. Day, a building contractor, and the Visalia Elks Building Association, a corporation, entered into a written contract, by the terms of which the said contractor agreed to construct for said corporation, in the city of Visalia, and furnish therefor all necessary labor and material, a three-story building and basement, for the total sum of $53,287. Attached to the contract were the plans and specifications, and for the faithful performance of the terms of said contract, the said Day, as principal, and the defendants, Ragle, Cole, J. P. Day, and Blair, as sureties, executed and delivered to said Association a bond in the penal sum of $26,644, as follows: Ragle, in the sum of $14,000; Blair, in the sum of $15,000; Cole, in the sum of $14,000; Day, in the sum of $13,000. *16 The condition of said bond was that said Day would faithfully perform said contract in accordance with the plans and specifications annexed thereto, pay all claims of all persons performing labor upon or furnishing materials used, “and to be used in said work,” and to turn over said building to said association completed in conformity with the contract and plans and specifications, within the time limited in said contract, free and clear of all claims, demands, liens, etc. This bond, with the contract, was filed for record on the third day of May, 1917, in the office of the county recorder of Tulare County.

The complaint alleges that said building was completed and said contract between the Elks Building Association and said Day was fully performed on the twenty-first day of May, 1918, and that on the twenty-second day of May, 1918, said owner, Building Association, formally accepted said building, and caused to be prepared and to be filed in the office of the county recorder of Tulare County a notice of the completion of said building, which notice contained all the facts required to be set forth in such a notice and stated that the building had been completed on the twenty-first day of May, 1918. Then follows a statement in. detail of the materials furnished and used in said building by plaintiff, Heberling, doing business as Visalia Planing Mill, and the statement that on the twenty-seventh day of April, 1918, said Heberling, etc., filed for record in the office of the county recorder of Tulare County a elairr. of lien duly verified by his oath for the purpose of securing and perfecting a lien for the amounts due him for the materials furnished as alleged; that thereafter, and within thirty days from the date of the actual completion of said •building, and for the purpose of curing certain defects in said lien, and for the further purpose of securing and perfecting his lien for the amount due him as explained, said Heberling, etc., filed for record in the office of the county recorder of the county of Tulare, on the fourth day of June, 1918, an amended claim of lien duly verified by his oath.

The claim of the plaintiff, Clark, doing business as Visalia Plumbing and Sheet Metal Company, is next set out in the complaint with particularity, it being based upon a subcontract between said Clark, etc., and the contractor, *17 Day, for the furnishing of the necessary labor and materials, etc., for the installation of the plumbing, heating, ventilating, and vacuum cleaning system of the building and also for the sheet metal work. In this paragraph of the complaint it is alleged that the owner of the building and its representatives and lessee entered into the use and occupation of said building on or shortly after the first day of April, 1918, and further alleged that said building was completed within the meaning of section 1187 of the Code of Civil Procedure by reason of such entering into the use and occupation of said building. It is alleged that on the twenty-ninth day of April', 1918, said Clark, etc., filed in the office of the county recorder of Tulare County his claim of lien duly verified for the materials so furnished and the labor so performed. It is then alleged that within thirty days from the date of the actual completion “of said building, to wit, on the twenty-first day of May, 1918, said Clark for the purpose of curing certain defects in the lien theretofore filed, filed for record in the office of the county recorder ... an amended claim of lien duly certified, ’ ’ etc.

The claim of each of the other plaintiffs is set out in the complaint in the usual form and as to each it is alleged that a claim of lien was properly prepared and filed within due time. As to the claim of the First National Bank of Visalia it is alleged that one J. B. Murphy, having under a subcontract performed all the cement work and the lathing and plastering in said building required by the plans and specifications for the same and filed his claim of lien for the balance due for said work in the sum of $2,524.32, subsequent to the filing of said claim of lien, sold and delivered said lien and the debt to secure which it was filed to the said bank.

The prayer is for a judgment against the contractor as principal and Ragle, Cole, Blair, and John P. Day, as sureties on the faithful performance bond in favor of each of the plaintiffs in the several amounts due them and for which claims of lien were filed; that the said Building Association be required to pay into court any money due and owing from it to the said contractor, and that said amount, whatever it may be, be apportioned pro rata among the various lien claimants and plaintiffs herein, etc.

*18 The defendants demurred to each of the several counts of the complaint on general and special grounds, but the only point urged on the demurrer is that the complaint, in so ’ far as are concerned the two several counts in which the Heberling and Clark claims are set out, is faulty in that therein there are two causes of action improperly joined and not separately stated. This point will later be considered.

The demurrer to each of the counts having been overruled, the defendant, D. B. Day, answered the complaint and each of the several counts setting up the claims of the plaintiffs as lien claimants, and the sureties on the faithful performance bond likewise answered the complaint.

The answers of the Elks Building Association to the complaint and each of the several counts thereof are not in the transcript, having been inadvertently omitted therefrom. They have, however, been certified to this court on a suggestion of a diminution of the record, and it is ordered that they be made and that they now do constitute and are a part of the record on this appeal. These answers are in all particulars substantially alike, and therein it is, among other things, alleged (after averments as to the making of the contract between D. B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prehired, LLC v. Provins
E.D. California, 2023
Fontana Paving, Inc. v. Hedley Brothers, Inc.
38 Cal. App. 4th 146 (California Court of Appeal, 1995)
Gary C. Tanko Well Drilling, Inc. v. Dodds
117 Cal. App. 3d 588 (California Court of Appeal, 1981)
Talco Capital Corp. v. State Underground Parking Commn.
324 N.E.2d 762 (Ohio Court of Appeals, 1974)
Emblen v. Southern Adjustment Bureau, Inc.
403 P.2d 294 (Court of Appeals of Arizona, 1965)
Ingersoll v. Chaplin
15 P.2d 790 (California Court of Appeal, 1932)
Hammond Lumber Co. v. Richardson
270 P. 751 (California Court of Appeal, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
209 P. 908, 59 Cal. App. 13, 1922 Cal. App. LEXIS 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heberling-v-day-calctapp-1922.