Showplace Square Loft Co. v. Primecore Mortgage Trust, Inc. (In Re Showplace Square Loft Co.)

289 B.R. 403, 2003 Bankr. LEXIS 295, 2003 WL 292059
CourtUnited States Bankruptcy Court, N.D. California
DecidedFebruary 6, 2003
Docket19-40238
StatusPublished
Cited by3 cases

This text of 289 B.R. 403 (Showplace Square Loft Co. v. Primecore Mortgage Trust, Inc. (In Re Showplace Square Loft Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Showplace Square Loft Co. v. Primecore Mortgage Trust, Inc. (In Re Showplace Square Loft Co.), 289 B.R. 403, 2003 Bankr. LEXIS 295, 2003 WL 292059 (Cal. 2003).

Opinion

MEMORANDUM DECISION ON MECHANIC’S LIEN CLAIMANT’S MOTION FOR SUMMARY JUDGMENT

DENNIS MONTALI, Bankruptcy Judge.

On January 24, 2003, this court held a hearing on the motion for summary judgment (“MSJ”) filed by Defendant Killarney Construction Company, Inc. (“Killarney”). Defendant Primecore Mortgage Trust, Inc. (“Primecore”) filed an opposition to the MSJ. For the reasons stated below, the court will grant summary judgment in part and deny summary judgment in part. 1

I. Relevant Undisputed Facts

Killarney was the general contractor for the construction of live-work lofts for Showplace Square Loft Company, LLC (“Debtor”). Primecore was the initial lender for the project and recorded its deed of trust on March 16, 2000.

As of February 29, 2000, trenches had been dug at the construction site and stakes indicated the outline of the building to be constructed there. 2 In addition, on *405 February 29, 2000, the site superintendent (Garrett O’Donoghue) was present when Construction Testing Services performed field inspections, tested the soil, bore holes and took soil samples. Between March 9 and March 14, 2000, the site superintendent oversaw soil compaction work at the construction site.

Even though Killarney issued a stop work notice to all subcontractors and suppliers on May 4, 2001, work was performed between May 4, 2001, and July 5, 2001 (when Killarney was paid in full for its work through that date). In particular, one of Killarney’s subcontractors — Anvil Iron Works (“Anvil”) — installed ground floor exterior guard rails and interior handrails between May 9, 2001, and May 18, 2001.

Debtor recorded a Notice of Completion on December 20, 2001; the Notice indicated that work was completed on November 8, 2001. On February 26, 2002, Killarney recorded its mechanic’s lien in the amount of $488,347.60 plus interest. Killarney filed an amended mechanic’s lien on February 27, 2002, to correct the zip code of Debtor.

The City and County of San Francisco issued a Certificate of Final Completion and Occupancy for the project on November 8, 2001. The certificate stated: “To the best of our knowledge, the construction described above has been completed and, effective as of the date the building permit application was filed, conforms both to the Ordinance of the City and County of San Francisco and to the Laws of the State of California.” In addition, Killarney sent memoranda dated November 13 and November 14 to certain subcontractors noting that it “will be off’ the site or job on November 16, 2001.

On December 18, 2001, Killarney faxed to its primary subcontractors a punch list of items which needed to be completed. While many of these tasks were de mini-mus (i.e., clean kitchen counter, clean lower bath mirror and glass shelves, etc.), the punch list also directed subcontractors to, *406 inter alia, paint doors, caulk glass into place, finish window frames, adjust drains, and paint other specific spots. Killarney, however, has not introduced evidence that these tasks were actually completed, and has not established the dates such tasks were done and the time required to complete such tasks.

II. Procedural History

On November 1, 2002, this court held a status conference in the above-captioned adversary proceeding. At that time, counsel for Killarney announced that she would shortly be filing the MSJ. The court and the parties discussed possible hearing dates and the need to take discovery prior to the hearing. The court tentatively scheduled the hearing for December 27, 2002, and counsel for Primecore indicated that he would file a Rule 56(f) declaration if the hearing were held so quickly. Counsel for Primecore requested that the hearing be held on January 17, 2002.

The parties agreed to work out an arrangement for rescheduling the hearing and for conducting discovery. On December 27, 2002, Killarney filed its MSJ and set it for hearing on January 24, 2002. 3

III. Discussion

A. Standard for Summary Judgment

Federal Rule of Civil Procedure 56(c) (“Rule 56”) (incorporated by Federal Rule of Bankruptcy Procedure 7056 (“Bankruptcy Rule 7056”)), provides that summary judgment “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.”

“The proponent of a summary judgment motion bears a heavy burden to show that there are no disputed facts warranting disposition of the case on the law without trial.” Younie v. Gonya (In re Younie), 211 B.R. 367, 373 (9th Cir. BAP 1997), aff'd, 163 F.3d 609 (9th Cir.1998), (quoting Grzybowski v. Aquaslide ‘N’ Dive Corp (In re Aquaslide ‘N’ Dive Corp.), 85 B.R. 545, 547 (9th Cir. BAP 1987)). If the moving party adequately carries its burden, the party opposing summary judgment must then “set forth specific facts showing that there is a genuine issue for trial.” Kaiser Cement Corp. v. Fischbach & Moore, Inc., 793 F.2d 1100, 1103-04 (9th Cir.1986), cert. denied, 479 U.S. 949, 107 S.Ct. 435, 93 L.Ed.2d 384 (1986). Significantly, the “burden carried by a summary judgment movant to show lack of factual dispute should not include demonstrably irrelevant or inapposite factual issues.” California First Bank v. Griffin (In re Orosco), 93 B.R. 203, 208 (9th Cir. BAP 1988).

All reasonable doubt as to the existence of genuine issues of material fact must be resolved against the moving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). *407 Nonetheless, “[d]isputes over irrelevant or unnecessary facts will not preclude a grant of summary judgment.” T.W. Electrical Service, Inc. v. Pacific Electrical Contractors Assn., 809 F.2d 626, 630 (citing Liberty Lobby, 477 U.S. at 248, 106 S.Ct. 2505). “The nonmoving party must do more than show there is some metaphysical doubt as to a material fact.” Kowalski-Schmidt v. Forsch (In re Giordano), 212 B.R. 617, 621 (9th Cir. BAP 1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Picerne Construction Corp. v. Castellino Villas
244 Cal. App. 4th 1201 (California Court of Appeal, 2016)
Magnum Builders v. Preferred Bank CA2/7
California Court of Appeal, 2014
Leimbach v. Lane (In Re Lane)
302 B.R. 75 (D. Idaho, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
289 B.R. 403, 2003 Bankr. LEXIS 295, 2003 WL 292059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/showplace-square-loft-co-v-primecore-mortgage-trust-inc-in-re-canb-2003.