Kaiser Cement Corporation, a Delaware Corporation v. Fischbach and Moore, Inc., the Howard P. Foley Co., a District of Columbia Corporation

793 F.2d 1100, 1986 U.S. App. LEXIS 26791, 55 U.S.L.W. 2107
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 8, 1986
Docket85-1846
StatusPublished
Cited by464 cases

This text of 793 F.2d 1100 (Kaiser Cement Corporation, a Delaware Corporation v. Fischbach and Moore, Inc., the Howard P. Foley Co., a District of Columbia Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaiser Cement Corporation, a Delaware Corporation v. Fischbach and Moore, Inc., the Howard P. Foley Co., a District of Columbia Corporation, 793 F.2d 1100, 1986 U.S. App. LEXIS 26791, 55 U.S.L.W. 2107 (9th Cir. 1986).

Opinion

BEEZER, Circuit Judge:

Kaiser appeals a grant of summary judgment for defendants. 1 Kaiser claims that defendants conspired to fix prices in the electrical construction industry in violation of the Sherman Act, 15 U.S.C. § 1, 2 Califor *1102 nia’s Cartwright Act, Cal.Bus. & Prof.Code 1116720 et seq., and the Racketeer Influenced Corrupt Organizations Act, 18 U.S.C. § 1961 et seq. Kaiser also claims that defendants committed fraud. 3 The district court held that Kaiser could not establish any damage and granted summary judgment. We AFFIRM.

FACTS

In 1979, Kaiser invited bids from several electrical construction companies for work at its Permanente, California cement plant. Three companies submitted bids, Fischbach & Moore, Inc. (Fischbach), the Howard P. Foley Company (Foley), and Roy M. Butcher Electric (Butcher). Kaiser alleges that Foley, Fischbach, and others conspired to fix bid prices.

Kaiser awarded the contract to Foley. Under the contract, Kaiser assumed the responsibility of coordinating the work. Foley’s work was to be completed within ten and a half months but actually took 24 months. Foley anticipated expending 67,-000 manhours but actually used 216,000. Foley claimed that Kaiser had breached the contract and that Foley’s extra costs resulted from that breach. 4

Foley filed a state court action to compel arbitration as required by the contract. Upon removal, the district court ordered serial arbitration between Kaiser and Foley and also between Kaiser and other contractors involved in the Permanente Project. The Kaiser-Foley arbitration panel received extensive oral and documentary evidence. The arbitrators awarded Foley $330,998 for change orders and $3,455,206 for delay and disruption. 5 The arbitration panel did not explain the basis upon which it calculated the award amounts. 6 The panel considered evidence of Foley’s actual *1103 costs, 7 an audit requested by the arbitrators, exhibits 2 and 7, which may have been fabricated, and Frank Lench’s testimony which was claimed to be false. 8 Kaiser argues that the arbitrators based the award on the fraudulent evidence. On August 5, 1983, the district court observed that “[I]t is not self-evident how the arbitrators determined the amount of the award.” Kaiser reasons, however, that the award incorporates the fixed price and therefore constitutes injury.

Three days before confirmation of the award, Kaiser filed this antitrust action. The district court granted Foley’s motion for summary judgment on March 4, 1985, stating that “[t]he arbitrators having determined the actual cost of Foley’s work and the fair compensation to which Foley is entitled for that work, there remains no genuine issue of material fact because there can be no damage to Kaiser.” The RICO, Cartwright Act, and fraud claims were also dismissed because Kaiser failed to establish injury. 9 On appeal the parties raise questions of the preclusive effect of an arbitration award in subsequent antitrust litigation and the applicability of judicial estoppel to Kaiser’s argument in the arbitration litigation. We affirm the district court on other grounds and do not consider these issues. 10

ANALYSIS

Summary judgment is appropriate in antitrust actions when there is no “significant probative evidence tending to support the complaint.” Robert’s Waikiki U-Drive, Inc. v. Budget Rent-A-Car Systems, Inc., 732 F.2d 1403, 1406 (9th Cir.1984) (quoting First National Bank of Arizona v. Cities Service Co., 391 U.S. 253, 290, 88 S.Ct. 1575, 1593, 20 L.Ed.2d 569 (1968)). See Mutual Fund Investors, Inc. v. Putnam Management Co., 553 F.2d 620, 624 (9th Cir. 1977). Summary judgment is proper when the moving party establishes that he is entitled to judgment as a matter of law and that no genuine issue of material fact exists. 11 Jewel Cos., Inc. v. Pay Less Drug Stores Northwest, Inc., 741 F.2d 1555,1559 (9th Cir.1984). The granting of a summary judgment is reviewed de novo. Lew v. Kona Hospital, 754 F.2d 1420, 1423 (9th Cir.1985). On review, we must view the evidence and inferences therefrom in the light most favorable to the party opposing summary judgment. Diaz v. American Telephone & Telegraph, 752 F.2d 1356, 1362 (9th Cir.1985); Jewel Cos., 741 F.2d at 1559.

“The initial burden of showing the absence of material factual issues rests on the proponent of a summary judgment motion. Once that burden is met, however, the opponent must counter with specific factual allegations revealing a genuine dispute of fact in order to preclude summary judgment.” International Union of Bricklayers & Allied Craftsman Local Union No. 20 AFL-CIO v. Martin Jaska, Inc., 752 F.2d 1401, 1405 (9th Cir.1985). A party opposing summary judgment does *1104 not have to file any countervailing materials when the movant’s papers are insufficient on their face to demonstrate the lack of any material issue of fact. Lew, 754 F.2d at 1423; Sheet Metal Workers' International Association Local No. 355 v. NLRB, 716 F.2d 1249, 1254 (9th Cir.1983); Zoslaw v. MCA Distributing Corp., 693 F.2d 870, 883 (9th Cir.1982), cert. denied, 460 U.S. 1085, 103 S.Ct. 1777, 76 L.Ed.2d 349 (1983). Once the moving party establishes that he would be entitled to a directed verdict at trial unless contradicted, the burden shifts to the opposing party to show that a contradiction is possible. ALW, Inc. v. United Air Lines, Inc., 510 F.2d 52, 55 (9th Cir.1975); Stansifer v. Chrysler Motors Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott v. Green
D. Nevada, 2025
Scott v. Henley
D. Nevada, 2025
Samuels v. We've Only Just Begun Wedding Chapel, Inc.
154 F. Supp. 3d 1087 (D. Nevada, 2015)
Estrella v. FREEDOM FINANCIAL NETWORK, LLC
778 F. Supp. 2d 1041 (N.D. California, 2011)
Newmont USA Ltd v. American Home Assurance Co.
676 F. Supp. 2d 1146 (E.D. Washington, 2009)
Crum v. Tomlinson (In Re Hettick)
413 B.R. 733 (D. Montana, 2009)
Notmeyer v. Stryker Corp.
502 F. Supp. 2d 1051 (N.D. California, 2007)
In Re Feature Realty Litigation
634 F. Supp. 2d 1163 (E.D. Washington, 2007)
Abbey v. Retz (In Re Retz)
364 B.R. 742 (D. Montana, 2007)
Bowoto v. Chevron Corp.
481 F. Supp. 2d 1010 (N.D. California, 2007)
Boland v. Crum (In Re Brown)
363 B.R. 591 (D. Montana, 2007)
Decker v. Washington Mutual Bank
357 B.R. 825 (D. Montana, 2007)
Morris Ex Rel. Morris v. Tanner
288 F. Supp. 2d 1133 (D. Montana, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
793 F.2d 1100, 1986 U.S. App. LEXIS 26791, 55 U.S.L.W. 2107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaiser-cement-corporation-a-delaware-corporation-v-fischbach-and-moore-ca9-1986.