W. F. Hayward Co. v. TransAmerica Insurance

16 Cal. App. 4th 1101, 20 Cal. Rptr. 2d 468, 93 Daily Journal DAR 8037, 93 Cal. Daily Op. Serv. 4787, 1993 Cal. App. LEXIS 670
CourtCalifornia Court of Appeal
DecidedJune 24, 1993
DocketB067505
StatusPublished
Cited by18 cases

This text of 16 Cal. App. 4th 1101 (W. F. Hayward Co. v. TransAmerica Insurance) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. F. Hayward Co. v. TransAmerica Insurance, 16 Cal. App. 4th 1101, 20 Cal. Rptr. 2d 468, 93 Daily Journal DAR 8037, 93 Cal. Daily Op. Serv. 4787, 1993 Cal. App. LEXIS 670 (Cal. Ct. App. 1993).

Opinion

Opinion

BOREN, P. J.

In this case, we hold that a complete work stoppage on a public work of improvement for 30 days constitutes a “cessation” of labor and a “completion” of the project. (Civ. Code, § 3086.) 1 The cessation of labor on or completion of the project commences the period during which stop notices must be filed under California’s lien laws. (§ 3184.) Here, a subcontractor’s failure to file its complaint within six months of the expiration of the period in which to file stop notices bars this suit against the surety on a contractor’s payment bond. (§ 3249.) Accordingly, we affirm the judgment.

Facts

Cates Construction, Inc. (Cates), contracted on October 25, 1988, with the County of Los Angeles (County) to construct the Lost Hills sheriffs station. Cates acted as the “original contractor” on the project within the meaning of section 3095. Appellant, W. F. Hayward Co., contracted on November 23, 1988, with Cates to provide certain labor and materials on the project. Appellant was thus a subcontractor as defined in section 3104. 2

As required by section 3247, Cates obtained a payment bond issued by respondent, Transamerica Insurance Company. 3 Construction on the project commenced but a number of delays ensued. A dispute between Cates and the County arose concerning who should bear the responsibility and expense stemming from the delays. Both Cates and its subcontractors sought additional payments from the County to defray the expenses arising out of the delays.

In a letter dated June 4, 1990, the County advised respondent that Cates had been suspended on the construction contract, effective June 5, 1990, and *1105 that the board of supervisors would adopt a formal termination of Cates’s contract on June 19, 1990. In a letter dated June 7, 1990, Cates requested that the County approve a change order in the amount of $1,227,771.79, a total which reflected the sum of the claims of Cates and its subcontractors arising out of the delays. The sum included appellant’s claim of $243,650. Cates and its subcontractors, including appellant, ceased work on the project. Cates never resumed any construction activity on the project.

On August 3, 1990, Cates and the County entered into an agreement entitled “Termination for Convenience Agreement and Mutual Release,” whereby the County relieved Cates of any further obligation or liability regarding the contract to construct the sheriffs station. By this agreement, Cates also purported to assign to the County all of its subcontracts, including the subcontract with appellant.

Appellant, in a letter to the County dated August 15, 1990, proposed that the County and appellant enter into a new contract. However, the County took the position that it had acquired a valid assignment of appellant’s contract with Cates and that appellant’s proposal was therefore unacceptable. Using the former Cates subcontractors, including appellant, the County completed the construction of the project on March 19, 1991.

On July 17, 1991, appellant filed suit against Cates, the County, and respondent, Cates’s surety. Cates was insolvent and its default was entered. This appeal concerns only the claim against respondent, seeking recovery on respondent’s payment bond.

After answering appellant’s complaint, respondent filed its motion for summary judgment, based on the ground that the lawsuit was untimely filed as to respondent and was barred by section 3249. The trial court granted respondent’s motion for summary judgment.

Discussion

On appeal from summary judgment, the reviewing court conducts a de novo examination to determine whether the moving party was entitled to summary judgment as a matter of law or whether there were any genuine issues of material fact. (Krieger v. Nick Alexander Imports, Inc. (1991) 234 Cal.App.3d 205, 212 [285 Cal.Rptr. 717].) Here, the essential facts are not in dispute; their legal significance is.

The trial court granted the motion for summary judgment on the ground that appellant had not filed its complaint within the time period prescribed *1106 by the applicable statute of limitations. That statute of limitations is set forth in section 3249, which provides: “Suit against the surety or sureties on the payment bond may be brought by any claimant, or his assigns, at any time after the claimant has furnished the last of the labor or materials, or both, but must be commenced before the expiration of six months after the period in which stop notices may be filed as provided in Section 3184.”

Thus, the issue here is whether the complaint was filed within six months after the period in which appellant could file stop notices. The parties’ dispute centers on what constitutes the period for filing stop notices. 4

Section 3184, referenced in section 3249, provides that any stop notice “must be served before the expiration of: [1] (a) Thirty days after the recording of a notice of completion (sometimes referred to in public works as a notice of acceptance) or notice of cessation, if such notice is recorded, [f] (b) If no notice of completion or notice of cessation is recorded, 90 days after completion or cessation.” 5 With regard to Cates’s work on the project, the parties do not dispute that neither a notice of completion nor a notice of cessation was filed or recorded. Subdivision (b) is therefore the applicable portion of section 3184. Application of this provision presents the question: When was there a “completion or cessation”?

Because it provides a definition of “completion,” section 3086 comes into play. That section provides: “If the work of improvement is subject to acceptance by any public entity, the completion of such work of improvement shall be deemed to be the date of such acceptance; provided, however, that... a cessation of labor on any public work for a continuous period of 30 days shall be a completion thereof.”

*1107 The record in the instant case makes clear that there was a cessation of labor on the Lost Hills sheriff’s station project. However, it does not appear that appellant served any stop notice regarding this public work. (See § 3181 et seq.) Indeed, appellant’s position is that there was no cessation of labor because the subsequent performance of appellant was pursuant to the original contract between Cates and the County, which Cates and the County “modified” on August 3, 1990. However, the August 3, 1990, agreement between Cates and the County was certainly not a mere “modification” of the original contract as appellant contends.

Entitled “Termination for Convenience Agreement and Mutual Release,” the August 3, 1990, contract specified that “the Primary Contract [between the County and Cates] is hereby terminated and Cates is relieved of any further obligation or liability in connection therewith including, but not limited to, performing any more work on the Project. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tarlton & Sons v. Great American Ins. Co.
California Court of Appeal, 2025
BMO Harris Bank N.A. v. Hassanally CA1/1
California Court of Appeal, 2022
Taswell v. Regents of the Univ. of Cal.
232 Cal. Rptr. 3d 628 (California Court of Appeals, 5th District, 2018)
Taswell v. The Regents of the Univ. of Cal.
California Court of Appeal, 2018
People v. Hinojosa CA2/1
California Court of Appeal, 2015
Santiago, Rodnunsky & Jones v. Spahl CA2/2
California Court of Appeal, 2015
Golden State v. Eastern Municipal Water Dist.
California Court of Appeal, 2014
Burns v. WD-40 Co. CA4/3
California Court of Appeal, 2013
Electrical Electronic Control, Inc. v. Los Angeles Unified School District
24 Cal. Rptr. 3d 316 (California Court of Appeal, 2005)
Santa Barbara Pistachio Ranch v. Chowchilla Water District
105 Cal. Rptr. 2d 856 (California Court of Appeal, 2001)
Bowen v. Lee Process Systems Co.
536 S.E.2d 86 (Court of Appeals of South Carolina, 2000)
Wedeck v. Unocal Corp.
59 Cal. App. 4th 848 (California Court of Appeal, 1997)
Gales v. Superior Court
47 Cal. App. 4th 1596 (California Court of Appeal, 1996)
Eagle Fire Protection Corp. v. First Indemnity of America Insurance
678 A.2d 699 (Supreme Court of New Jersey, 1996)
Truck Insurance Exchange v. Amoco Corp.
35 Cal. App. 4th 814 (California Court of Appeal, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
16 Cal. App. 4th 1101, 20 Cal. Rptr. 2d 468, 93 Daily Journal DAR 8037, 93 Cal. Daily Op. Serv. 4787, 1993 Cal. App. LEXIS 670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-f-hayward-co-v-transamerica-insurance-calctapp-1993.