Tarlton & Sons v. Great American Ins. Co.

CourtCalifornia Court of Appeal
DecidedMay 21, 2025
DocketB336550
StatusPublished

This text of Tarlton & Sons v. Great American Ins. Co. (Tarlton & Sons v. Great American Ins. Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tarlton & Sons v. Great American Ins. Co., (Cal. Ct. App. 2025).

Opinion

Filed 5/21/25

CERTIFIED FOR PARTIAL PUBLICATION*

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION SIX

TARLTON & SONS, INC., 2d Civ. No. B336550 (Super. Ct. No. Plaintiff and Appellant, 2023CUBC007933) (Ventura County) v.

GREAT AMERICAN INSURANCE COMPANY,

Defendant and Respondent.

Appellant Tarlton & Sons, Inc. (Tarlton) appeals a judgment of dismissal after the trial court sustained a demurrer to its third amended complaint without leave to amend. Tarlton contends its claim on a public works payment bond (Civ. Code,1 § 9550 et seq.) is not barred by the statute of limitations. It also contends the third amended complaint alleges facts sufficient to

* Pursuant to California Rules of Court, rules 8.1100 and

8.1110, this opinion is certified for partial publication. The portions of this opinion to be deleted from publication are identified as those portions between double brackets, e.g., [[/]].

1 Unspecified statutory references are to the Civil Code. state causes of action for false promise, promissory estoppel, fraud, and negligent misrepresentation. We agree the trial court should have overruled the demurrer as to the payment bond cause of action. We will reverse judgment as to that claim but otherwise affirm. FACTUAL AND PROCEDURAL BACKGROUND2 Oxnard Union High School District (District) awarded Fast Track Construction Corporation (Fast Track) a prime contract to perform heating and air conditioning work at two high schools. Fast Track obtained the required public works payment bond from respondent Great American Insurance Company (GAIC). Fast Track entered into a subcontract with appellant Tarlton to perform framing and drywall work in connection with the project. Tarlton began working on the project in April 2021. A dispute arose between Fast Track and the District in August of 2021. Tarlton continued working on the subcontract until November 12, 2021.3 Around this time, the District hired Viola Inc. to “perform general contractor duties.” Tarlton entered into a separate subcontract with Viola on November 29, 2021 that modified the scope of its work at the high schools. Tarlton was not “provided formal notice of Fast-Track’s termination by the

2 We source all facts from the third amended complaint.

3 The third amended complaint deleted the allegation that

Tarlton stopped work under its Fast Track contract on November 12, 2021 and instead alleged Tarlton continued to perform work “on the Project at the direction of the general contractor” (except a stoppage between August 31, 2021 and September 22, 2021) “through the date of filing of this amended complaint.” Tarlton maintains the date after which it could file an action on the bond under section 9558, i.e. when it “ceased providing work under [the] Fast Track” contract, was November 12, 2021.

2 District, if it was terminated, or shown any agreement related to either the termination of Fast-Track or the District’s contract with Viola.” Work on the project then continued. For unknown reasons, the District continued to issue change orders to Fast Track “through and including, at a minimum, January 31, 2022.” Tarlton submitted a payment bond claim to GAIC in April of 2022 for work performed under the Fast Track subcontract. It initially sought $596,677.46 but later increased the amount to $688,353.66. GAIC notified Tarlton that it was only partially accepting the claim. GAIC requested Tarlton sign a waiver and release with respect to the amount of the accepted part of the claim. GAIC acknowledged Tarlton’s right “to pursue the balance of the amount of its claim.” Tarlton sued GAIC, the District, Fast Track, and others in April of 2023 when negotiations over Tarlton’s payments failed. The trial court sustained a demurrer to Tarlton’s second amended complaint with leave to amend in November of 2023. Tarlton filed a third amended complaint alleging the following causes of action against GAIC: amounts owed on payment bond (third cause of action); false promise (fifth cause of action); promissory estoppel (sixth cause of action); fraud (seventh cause of action); and negligent misrepresentation (eighth cause of action). The trial court sustained GAIC’s demurrer to the third amended complaint—this time without leave to amend. It relied in part on the prior demurrer ruling. It entered judgment on April 4, 2024 and dismissed all claims against GAIC. DISCUSSION Standard of Review “In reviewing an order sustaining a demurrer, we examine the operative complaint de novo to determine whether it alleges facts sufficient to state a cause of action under any legal theory.”

3 (T.H. v. Novartis Pharmaceuticals Corp. (2017) 4 Cal.5th 145, 162.) “‘We treat the demurrer as admitting all material facts properly pleaded, but not contentions, deductions or conclusions of fact or law. [Citation.] We also consider matters which may be judicially noticed.’ [Citation.] Further, we give the complaint a reasonable interpretation, reading it as a whole and its parts in their context.” (Blank v. Kirwan (1985) 39 Cal.3d 311, 318.) Applicable Law The rights of a public works project contractor “with respect to any fund for payment of construction costs” are governed exclusively by the Civil Code. (§ 9350.) A direct contractor (also called the general or prime contractor) on public works project “involving an expenditure in excess of . . . $25,000” must give a payment bond to the public entity before starting work. (§ 9550, subd. (a).) The bond assures that funds will be available to pay subcontractors working on the project if the subcontractor is not paid under its contract. (§ 9554, subd. (b).) A subcontractor can file an action on the bond if not paid for work performed on the project. (§ 9100, subd. (a)(1).) Before doing so, it may notify the direct contractor of the unpaid amounts by serving a stop payment notice on the direct contractor. (§ 9564, subd. (a); see National Technical Systems v. Commercial Contractors, Inc. (2001) 89 Cal.App.4th 1000, 1006 [stop payment notice “is a remedy to reach unexpended construction funds in the hands of the owner or lender . . . and may be served by a claimant other than an original contractor”].) “A claimant may commence an action to enforce the liability on the bond at any time after the claimant ceases to provide work, but not later than six months after the period in which a stop payment notice may be given under Section 9356.” (§ 9558.) A stop payment notice is not effective unless, as

4 relevant here, given “90 days after cessation or completion.” (§ 9356, subd. (b).)4 “[C]ompletion of a work of improvement” occurs at the earlier of acceptance of the work by the public entity or “[c]essation of labor on the work of improvement for a continuous period of 60 days.” (§ 9200, subd. (b).) Payment Bond Cause of Action The trial court sustained GAIC’s demurrer when it found “completion” occurred 60 days after Tarlton stopped work for Fast Track, i.e., on November 12, 2021. Tarlton contends work continued on the District’s project despite any formal termination of the Fast Track contract. This meant no “cessation of labor” occurred that would have triggered Tarlton’s period to file a stop notice on that date. Alternatively, it contends GAIC’s misleading conduct either estops the surety from relying on the statute or tolls the limitations period. We agree no cessation of labor occurred and reverse the order sustaining the demurrer on Tarlton’s payment bond claim. We need not reach the alternative contention. The trial court cited W. F. Hayward Co. v. Transamerica Ins. Co. (1993) 16 Cal.App.4th 1101 (Hayward) in support of its ruling. In Hayward, Cates Construction, Inc. contracted with the County of Los Angeles to construct a sheriff’s station. Hayward was a subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blank v. Kirwan
703 P.2d 58 (California Supreme Court, 1985)
W. F. Hayward Co. v. TransAmerica Insurance
16 Cal. App. 4th 1101 (California Court of Appeal, 1993)
Small v. Fritz Companies, Inc.
65 P.3d 1255 (California Supreme Court, 2003)
Jones v. Wachovia Bank
230 Cal. App. 4th 935 (California Court of Appeal, 2014)
Robison v. Mitchel
114 P. 984 (California Supreme Court, 1911)
T.H. v. Novartis Pharmaceuticals Corporation
407 P.3d 18 (California Supreme Court, 2017)
National Technical System v. Commercial Contractors, Inc.
89 Cal. App. 4th 1000 (California Court of Appeal, 2001)
Behnke v. State Farm General Insurance
196 Cal. App. 4th 1443 (California Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Tarlton & Sons v. Great American Ins. Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/tarlton-sons-v-great-american-ins-co-calctapp-2025.