Robison v. Mitchel

114 P. 984, 159 Cal. 581, 1911 Cal. LEXIS 356
CourtCalifornia Supreme Court
DecidedMarch 20, 1911
DocketL.A. No. 2595.
StatusPublished
Cited by15 cases

This text of 114 P. 984 (Robison v. Mitchel) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robison v. Mitchel, 114 P. 984, 159 Cal. 581, 1911 Cal. LEXIS 356 (Cal. 1911).

Opinion

HENSHAW, J.

This action was by a materialman to foreclose his lien upon the property of defendant Fawkes for material furnished in the construction of a frame dwelling. Judgment passed for plaintiff, awarding him a lien, and from that judgment and from the order denying his motion for a new trial the defendant Fawkes appeals.

The contractors for the construction of. the building were copartners doing business under the firm name of J. Burris Mitchel & Company. Their contract with appellant was in writing and valid. It contained the usual stipulation for partial payments, and provided that if at any time during the progress of the work the contractors should refuse or neglect, without fault of the owner, to supply a sufficiency of material and workmen to complete the contract within the time limited, for the period of more than three days after having been notified by the owner in writing to furnish the same, the owner should have power to furnish and provide the material or workmen to finish the work, and the reasonable expense thereof should be deducted from the contract price. It also provided that if the owner should delay a progress payment for more than five days after the date when such payment became due, at the option of the contractor this should be held to be a prevention by the owner of performance of the contract by the contractor.

*584 It was over these provisions of the contract that difficulty arose. Work had progressed and progress payments had been made until the time came when the frame was up, and there became due under the terms of the contract a payment of eight hundred dollars. This payment the owner refused to make, upon the ground of faulty and imperfect construction. The contractors refused to proceed until payment was made. The owner thereupon gave the notice contemplated by the contract, calling upon the contractors to continue with the work, and upon the contractors’ failure and refusal so to do for a period of more than three days, the owner proceeded with the construction and completed the building. It will thus be seen that the contractors’ position was that the contract was violated by the owner in his unwarranted refusal to make a proper payment when it became due. Upon the other hand, the owner’s position was that the payment was not due because of faulty construction, and that the contractors’ refusal to proceed with the work after notice given, justified him, under the contract, in pushing the work to completion. The court found in effect that the contractors had not violated the contract, that the refusal of the owner to make the payment was unwarranted, and consequently that the contractors had been unlawfully prevented by the acts of the owner from prosecuting the contract, and the owner’s completion of the building was not, therefore, in conformity with the terms of the contract, but in violation thereof.

The owner’s notice to the contractors to proceed with the work was given upon October 15, 1906. Upon November 19, 1906, the owner filed for record his verified notice of cessation, as contemplated by the opening paragraph of section 1187 of the Code of Civil Procedure. Therein he declared that the J. Burris Mitchel Company had abandoned work, that the abandonment occurred upon the eighteenth day of October, 1906, and that since the abandonment and for more than thirty days and less than forty days the contractors had done no work upon the building and improvements under the contract, and that the owner was now proceeding to complete the building. It is a fact that the contractors ceased labor from the date mentioned and never resumed labor upon the building, but the court found that there was no cessation from labor upon the unfinished building, under the belief that *585 the owner himself undertook the completion of the building before there had been a cessation of labor thereon for the period of thirty days. The finding to this effect is attacked and will require examination. But for the present, considering the case made by the findings, it appears that the contractors ceased work under circumstances which the court finds justified their doing so, and the owner, before there had been a cessation from labor upon the unfinished contract or upon the unfinished structure for the period of thirty days, undertook the work of completion.

The lien in this case was admittedly filed within time after the actual completion of the building, but was not filed within time if the notice of cessation and abandonment filed by the owner upon November 19, 1906, set running the statutory period for the filing of the lien.

The case thus demands a consideration and an analysis of section 1187 of the Code of Civil Procedure, as amended in 1897. That section deals:

1. With the situation presented by actual completion recognized as such by the owner. In such a case the owner must within ten days after such completion file in the office of the county recorder of the county a notice setting forth the date of completion, etc. If he does not do this he is estopped in any action brought to foreclose a lien upon his property from maintaining as a defense that the lien has not been filed within the time prescribed by law. If he does do this then the original contractor has sixty days after the filing of the notice, and other lien claimants have thirty days after the filing of the notice, within which to file their claims of lien, provided, however, that if the lien sought be for labor performed in a mining claim it must be filed within thirty days after the performance of the labor without regard to the filing by the owner of any notice of completion which, because of the character of the work, is in this instance unnecessary, if not impossible. It is further provided in this connection “that in any event all claims of lien must be filed within ninety days after the completion of said building, improvement or structure, or the alteration, addition to or repair thereof.” This would seem to fix a time limit within which all liens must be filed regardless of whether the owner has filed his notice of completion or not, and it gives rise to the question *586 whether the statute which forbids the owner who has failed to file the notice of completion to make the defense that the lien has not been filed within the time provided by the chapter, means to forbid him to make that defense in every case, or only in those cases where liens have been filed within ninety days after completion. But this question it is not necessary here to resolve.

2. The section next takes up the reciprocal rights and duties of the owner and lien claimants where for any cause there has been for thirty days “a cessation from labor upon any unfinished contract, or upon any unfinished building,” etc. It is here to be noted that the continuous cessation from labor for thirty days, and this alone, is sufficient to set in motion the requirements of the statute. Nothing less than cessation from labor for thirty days will meet the statutory exaction, and nothing more than a cessation from labor for thirty days is required. When there has been such cessation it becomes the duty of the owner within ten days thereafter to file the required notice of cessation or abandonment of work under the penalty above set forth for his failure so to do,— námely, that he shall not be permitted to maintain a defense based on the ground that any lien has not been filed within the time provided.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tarlton & Sons v. Great American Ins. Co.
California Court of Appeal, 2025
Golden State v. Eastern Municipal Water Dist.
California Court of Appeal, 2014
W. F. Hayward Co. v. TransAmerica Insurance
16 Cal. App. 4th 1101 (California Court of Appeal, 1993)
Marxen v. Herron
18 P.2d 1002 (California Court of Appeal, 1933)
Boise-Payette Lumber Co. v. Longwedel
295 P. 791 (Supreme Court of Colorado, 1930)
Economy Home Builders, Inc. v. Berry
272 P. 307 (California Court of Appeal, 1928)
C. Ganahl Lumber Co. v. Thompson
270 P. 965 (California Supreme Court, 1928)
Pioneer Lumber Co. v. Binckley
2 Cal. Super. Ct. 78 (California Superior Court, 1926)
Pence v. Martin
185 P. 503 (California Court of Appeal, 1919)
Emigh-Winchell Hardware Co. v. Pylman
176 P. 722 (California Court of Appeal, 1918)
Olson-Mahoney Lumber Co. v. Dunne Investment Co.
159 P. 178 (California Court of Appeal, 1916)
National Lumber Co. v. Kennedy
154 P. 25 (California Court of Appeal, 1915)
Sunset Lumber Co. v. Bachelder
140 P. 35 (California Supreme Court, 1914)
C. Ganahl Lumber Company v. Weinsveig
117 P. 954 (California Court of Appeal, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
114 P. 984, 159 Cal. 581, 1911 Cal. LEXIS 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robison-v-mitchel-cal-1911.