Golden State v. Eastern Municipal Water Dist.

CourtCalifornia Court of Appeal
DecidedJuly 23, 2014
DocketE054618
StatusPublished

This text of Golden State v. Eastern Municipal Water Dist. (Golden State v. Eastern Municipal Water Dist.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Golden State v. Eastern Municipal Water Dist., (Cal. Ct. App. 2014).

Opinion

Filed 7/23/14 See Dissenting Opinion

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION TWO

GOLDEN STATE BORING & PIPE JACKING, INC., E054618 Plaintiff, Cross-defendant and Appellant, (Super.Ct.No. RIC502935)

v. OPINION

EASTERN MUNICIPAL WATER DISTRICT,

Defendant and Cross-complainant;

SAFECO INSURANCE COMPANY,

Defendant, Cross-defendant and Respondent.

APPEAL from the Superior Court of Riverside County. Gloria Connor Trask,

Judge. Affirmed.

Law Offices of Timothy P. Creyaufmiller and Timothy P. Creyaufmiller for

Plaintiff, Cross-defendant and Appellant.

1 Sedgwick, Jonathan J. Dunn, Andrew C. Harris, Bryan K. Lang and Hall R.

Marston for Defendant, Cross-defendant and Respondent.

No appearance for Defendant and Cross-complainant.

The Eastern Municipal Water District (EMWD) hired general contractor S.J. and

Burkhardt, Inc. (SJB) for a public works construction project in 2006. Safeco Insurance

Company (Safeco) executed performance and payment bonds for the project. Plaintiff

Golden State Boring & Pipe Jacking, Inc. (GSB) was a subcontractor for the project,

completing its work by September 2006, but it did not receive payment of $577,038.37,

owed.

In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB

sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately

seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to

interplead retained sums. Safeco made a motion for summary judgment on the cause of

action for payment under the bond on the ground that GSB’s claim was untimely. The

trial court granted the motion as to that cause of action, finding that there had been three

cessations of labor that triggered GSB’s duty to file a stop notice in order to secure

payment under Safeco’s payment bond. At a subsequent court trial on the contract

claims, GSB was awarded judgment against SJB, and Safeco was awarded judgment on

the interpleader action.

2 GSB appeals the summary judgment ruling claiming (a) the trial court erroneously

overruled its objections to evidentiary matters presented in support of Safeco’s summary

judgment, and (b) the court erred in finding the action was untimely. We affirm.

BACKGROUND

From the pleadings we discern the following facts:

EMWD hired SJB as general contractor on “Specification No. 934W, Nuevo

Road/I-215 Water Transmission Pipeline Project, Perris California” (the Project). On

April 26, 2006, SJB entered into a subcontract agreement with GSB to perform the

tunneling portion of the project. For these services, SJB originally agreed to pay GSB

$565,150. After GSB agreed to provide additional services, SJB agreed to pay an

additional $27,912.20, for a total project price of $593,062.20 On April 18, 2006,

Safeco executed a payment bond for the Project. GSB completed its portion of the work

on the Project in September 2006.

Prior to completion of the Project, there were three cessations of labor which

exceeded 30 days: the first occurred between November 11, 2006, and December 17,

2006; the second occurred between April 4, 2007 and May 20, 2007, and the third

occurred between May 20, 2007, and October 4, 2007. The overall Project was

completed in 2008. GSB alleged that it filed a stop notice with EMWD on January 2,

2008, in the amount of $577,038.37.1 On March 24, 2008, SJB informed Safeco by letter

1 The exhibits included in the record pertaining to the summary judgment motion do not include a stop notice filed by GSB. However, in the Joint Statement of Stipulated Facts and Evidence submitted after the summary judgment motion in connection with the 3 that it could not meet its obligations. Safeco sent a letter to EMWD on March 27, 2008,

regarding SJB’s default.

In July 2008, GSB filed suit against SJB for nonpayment under the contract, as

well as in common counts. The fourth cause of action included EMWD as a defendant

for Enforcement of Stop Notice, and the fifth cause of action named Safeco in a claim on

the Stop Notice Release Bond and Payment Bond. In October 2008, EMWD recorded a

Notice of Acceptance signifying completion of the Project.

On August 27, 2008, EMWD answered the complaint and filed a cross-complaint

in interpleader. EMWD tendered the amount of $86,444.59, which it had withheld from

SJB pursuant to the stop notice. EMWD was subsequently dismissed from the action.

SJB’s default was entered June 8, 2009.2

On December 22, 2010, Safeco filed a motion for summary judgment as to the

fifth cause of action relating to the payment bond. In support of its motion, Safeco

submitted a declaration of one of its counsel, Brian Lang, as well as a declaration

regarding the summary of voluminous documents received during discovery from

pending court trial, the parties stipulated that “[o]n or about January 2, 2008, GSB filed a stop notice with EMWD in the amount of $577,038.37 in connection with the Project.” 2 The record contains EMWD’s request to enter SJB’s default as to the cross- complaint, however the Register of Actions reflects that GSB requested entry of SJB’s default on the original complaint on that date. On August 10, 2011, following a prove-up hearing on SJB’s default, judgment was entered in GSB’s favor in the amount of $1,467,734.48. Since SJB never made a general appearance in the action, and no one disputed that a default was entered as to SJB by plaintiff during the default prove up, we assume that SJB’s default on GSB’s original complaint was duly entered. (Evid. Code, § 664.) 4 EMWD. Those documents related to the daily performance and non-performance of

work on the Project, including certified payroll reports, inspector’s reports, EMWD

safety inspection reports, and statement of non-performance. The motion was also based

on GSB’s responses to interrogatories propounded by Safeco, and EMWD’s response to

Safeco’s Request for Production of Documents.

In response to the motion, GSB generally objected to both declarations, citing

hearsay, lack of personal knowledge, opinion, speculation, and that the declarant was not

an expert. However, GSB did not dispute that there were cessations of labor, arguing

instead that the issue of cessation of labor is not relevant unless there has been no notice

of completion. Nor did GSB object to EMWD’s responses to the Request for Production

of Documents, by which Safeco obtained the documents summarized by Lang.

The trial court overruled GSB’s objections and granted Safeco’s motion for

summary judgment. Notice of Entry of the Order and Judgment on the Fifth Cause of

Action was filed on August 2, 2011. GSB filed notice of appeal from that order on

September 19, 2011.

The matter proceeded to court trial on the remaining causes of action based on

various stipulated facts and evidence. On the first three causes of action against SJB, the

court awarded GSB $577,038.37 under the contract, plus penalties pursuant to Business

and Professions Code section 7108.5 in the amount of $590,016.60, plus interest on

progress payments in the amount of $242, 981.62, plus penalties pursuant to Business and

Professions Code section 7107 in the amount of $50,863.50, plus interest on that sum in

5 the amount of $6,834.39, for a grand total of $1,467,734.38. On the fourth cause of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hayman v. Block
176 Cal. App. 3d 629 (California Court of Appeal, 1986)
Krueger Bros. Builders, Inc. v. San Francisco Housing Authority
198 Cal. App. 3d 1 (California Court of Appeal, 1988)
Vanguard Recording Society, Inc. v. Fantasy Records, Inc.
24 Cal. App. 3d 410 (California Court of Appeal, 1972)
Central Industrial Engineering Co. v. Strauss Construction Co.
98 Cal. App. 3d 460 (California Court of Appeal, 1979)
Kirby v. Alcoholic Beverage Control Appeals Board
8 Cal. App. 3d 1009 (California Court of Appeal, 1970)
Twaite v. Allstate Insurance
216 Cal. App. 3d 239 (California Court of Appeal, 1989)
DiCola v. White Brothers Performance Products, Inc.
69 Cal. Rptr. 3d 888 (California Court of Appeal, 2008)
Johnson v. United Cerebral Palsy/Spastic Children's Foundation
173 Cal. App. 4th 740 (California Court of Appeal, 2009)
Wall Street Network, Ltd. v. New York Times Co.
164 Cal. App. 4th 1171 (California Court of Appeal, 2008)
W. F. Hayward Co. v. TransAmerica Insurance
16 Cal. App. 4th 1101 (California Court of Appeal, 1993)
Prato-Morrison v. Doe
126 Cal. Rptr. 2d 509 (California Court of Appeal, 2002)
Western Mutual Ins. Co. v. Yamamoto
29 Cal. App. 4th 1474 (California Court of Appeal, 1994)
Truong v. Glasser
181 Cal. App. 4th 102 (California Court of Appeal, 2009)
Carnes v. Superior Court
23 Cal. Rptr. 3d 915 (California Court of Appeal, 2005)
Lopez v. University Partners
54 Cal. App. 4th 1117 (California Court of Appeal, 1997)
Tibor v. Superior Court
52 Cal. App. 4th 1359 (California Court of Appeal, 1997)
Heaps v. Heaps
21 Cal. Rptr. 3d 239 (California Court of Appeal, 2004)
DEPARTMENT OF INDUS. REL. v. Fidelity Roof Co.
60 Cal. App. 4th 411 (California Court of Appeal, 1997)
Pajaro Valley Water Management Agency v. McGrath
27 Cal. Rptr. 3d 741 (California Court of Appeal, 2005)
Bozzi v. NORDSTROM, INC.
186 Cal. App. 4th 755 (California Court of Appeal, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Golden State v. Eastern Municipal Water Dist., Counsel Stack Legal Research, https://law.counselstack.com/opinion/golden-state-v-eastern-municipal-water-dist-calctapp-2014.