Emigh-Winchell Hardware Co. v. Pylman

176 P. 722, 38 Cal. App. 508, 1918 Cal. App. LEXIS 173
California Court of Appeal·Decided October 26, 1918·No. Civ. No. 1582.·Published·Cited by 1 cases

Opinion

BURNETT, J.

makes the mistake of assuming that this is a case for the application of the section of the code relating to the condition wherein there has been not an actual completion of the building, but a mere cessation from labor. If that were true, the building would not be deemed completed until thirty days after such cessation.

But, as pointed out in our former opinion, the evidence and the finding were to the effect that the building was actually completed on May 2, 1914. If respondent, Pylman, had relied upon the circumstance of the cessation of labor, regardless of actual completion, as the starting point for the statutory period within which a claim for lien must be filed, then there might be some merit in appellant’s contention that its lien was filed in time. We have, however, no such case, and there is no occasion to invoke such provision of the code. The language of the statute seems entirely too plain to permit of serious disagreement. Unless we are to disregard its unequivocal mandate, that the lien must be filed in any event within ninety days of the completion of the building, we must hold that appellant was too late. To the authorities cited in our former opinion we may add these two late decisions by our supreme court, in which the ninety day period of limitation is emphasized: Bird v. American Surety Co., 175 Cal. 625, 631, [166 Pac. 1009] , Hogan Lumber Co. v. Boyle (Nichols), 177 Cal. 477, [170 Pac. 1106]. As to the latter decision it may be said that Sunset Lumber Co. v. Batchelder, 167 Cal. 572, [Ann. Cas. 1916B, 664, 140 Pac. 35], cited therein, involved work done under the old statute when both occupancy and cessation from labor were required to constitute constructive completion in the sense of the statute.

We adhere to the views expressed in our former opinion as follows:

“The action was against the owner and the contractor of a building for materials furnished for the use of said building, and for foreclosure of a mechanic’s lien. Plaintiff recovered judgment against the contractor for the amount of the claim, but judgment for costs was entered in favor of defendant Pylman, from which the appeal has been taken. *510 The court found that the work on the building was begun in the month of October, 1913, ‘and was completed on May 2, 1914 .... and was then and there occupied by said owner as completed, and at the same time the said defendant Pylman and his family moved into and occupied said building and began then and there openly and publicly to use and occupy the same as their place of residence, and they ever since have continued to so use and occupy said premises and to reside thereon. ’
“It was also found that the owner had fully paid the contractor, and that the material was furnished by plaintiff at the instance and request of said contractor, but ‘that no materials furnished by the plaintiff were used in said building after the second day of May, 1914, ’ although on the tenth of July following, plaintiff sent to said building four special hinges of small value which had been previously ordered by the contractor, and they were afterward paid for by the owner. It was also found that plaintiff filed its claim of lien for record on August 8, 1914. Indeed, it was so alleged in the complaint and not denied. The court concluded ‘that the time to file liens for labor or materials furnished in the construction of said building began to run on the second day of May, 1914, and the time to file liens thereon expired on the thirty-first day of July, 1914, and prior to the filing of plaintiff’s alleged lien. ’
“As to the finding in reference to the completion of the building, there can be no possible doubt of the sufficiency of the evidence in its support. It was stipulated at the trial that the Pylmans were living in the house on April 28, 1914, and from that time continuously. Nellie Pylman testified that on the twenty-eighth day of April the contractor had everything done with the exception of putting on a few hooks on the screen doors and a very few little necessary things, and that this was attended to within a few days and that the building was. then accepted by them. It appears, also, that on April 13th, the owner and contractor had a settlement and at that time agreed to eliminate certain work from the contract, and deductions were made for the things omitted. This was in accordance with the provisions of the contract between the parties, and the evidence shows that the contract, as thus modified was completely executed. *511 “We have, therefore, not only constructive but actual completion of the building not later than May 2, 1914. As to the circumstances of occupation and acceptance of the building, section 1187 of the Code of Civil Procedure provides that: In all cases any of the following shall be deemed equivalent to a completion for all purposes of this chapter.’ 1. ‘The occupation or use of a building, improvement or structure by the owner, ’ or 2. ‘ The acceptance by said owner of said building, improvement or structure. ’ Hence, it is entirely clear that we cannot question the finding of the court that said building for all the purposes of filing a mechanic’s lien was completed on May 2, 1914.
“In reference to certain facts which the law declares to be sufficient to support the conclusion that the building for the purpose of a lien has been completed, it may be stated that the statute has undergone certain changes, which are pointed out in various decisions of the courts. Prom 1887 to 1897 said section of the statute limited the operation of the occupation or use and acceptance to those cases wherein there was a duly recorded contract, the legislature having provided ‘and in case of contracts, the occupation,’ etc. In the latter year the section was amended so as to make occupation and acceptance apply to all cases, but a further amendment was added to the effect that either must be coupled with cessation from labor for thirty days in order to constitute constructive completion. These changes are fully discussed in Robison v. Mitchel, 159 Cal. 586, [114 Pac. 984], and we need not dwell upon them further. Then comes the amendment of 1911, which applies to cases wherein the contract has not as well as those wherein it has been recorded; and as clear as language can make it, the section now provides that any of the three circumstances shall constitute constructive completion, namely: 1. Occupation of the building; 2. Acceptance of the building by the owner; and 3. Cessation from labor for thirty days.
“By a sort of metaphysical refinement, appellant seeks to make it appear that cessation from labor for the period of thirty days must still be added to the other circumstances above mentioned to constitute completion, but the section is too plain to admit of discussion. Indeed, it is pointed out in Hughes Mfg. etc. Co. v. Hathaway, 174 Cal. 48, [161 Pac. 1159], that the phrase ‘ completion of the building, ’ as used *512

Free access — add to your briefcase to read the full text and ask questions with AI

Emigh-Winchell Hardware Co. v. Pylman, 176 P. 722, 38 Cal. App. 508, 1918 Cal. App. LEXIS 173 (Cal. Ct. App. 1918).

176 P. 722 (Emigh-Winchell Hardware Co. v. Pylman) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

C. Ganahl Lumber Co. v. Thompson
270 P. 965 (California Supreme Court, 1928)