Emigh-Winchell Hardware Co. v. Pylman

37 Cal. App. 533, 1918 Cal. App. LEXIS 612
CourtCalifornia Court of Appeal
DecidedJune 15, 1918
DocketCiv. No. 1582.
StatusPublished

This text of 37 Cal. App. 533 (Emigh-Winchell Hardware Co. v. Pylman) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emigh-Winchell Hardware Co. v. Pylman, 37 Cal. App. 533, 1918 Cal. App. LEXIS 612 (Cal. Ct. App. 1918).

Opinion

BURNETT, J.

The action was against the owner and the contractor of a building for materials furnished for the use of said building, and for the foreclosure of a mechanic’s lien. Plaintiff recovered judgment against the contractor for the amount of the claim, but judgment for costs was entered in favor of defendant Pylman, from, which the appeal has been taken. The court found that the work on the building was begun in the month of October, 1913, “and was completed on May 2, 1914 . . . and was then and there occupied by said owner as completed, and at the same time the said defendant Pylman and his family moved into and occupied said building and began then and there openly and publicly to use and occupy the same as their place of residence, and they ever since have continued to so use and occupy said premises and to reside thereon.”

It was also found that the owner had fully paid the contractor, and that the material was furnished by plaintiff at the instance and request of said 'contractor, but “that no materials furnished by the plaintiff were used, in said building-after the second day of May, 1914,” although on the 10th of *535 July following plaintiff sent to said building four special hinges of small value, which had been previously ordered by the contractor, and they were afterward paid for by the owner. It was also found that plaintiff filed its claim of lien for record on August 8, 1914. Indeed, it was so alleged in the complaint and not denied. The court concluded “that the time to file liens for labor or materials furnished in the construction of said building began to run on the second day of May, 1914, and the time to file liens thereon expired on the thirty-first day of July, 1914, and prior to the filing of plaintiff’s alleged lien.”

As to the finding in reference to the completion of the building, there can be no possible doubt of the sufficiency of the evidence in its support. It was stipulated at the trial that the Pylmans were living in the house on April 28, 1914, and . from that time continuously. Nellie Pylman testified that on the twenty-eighth day of April the contractor had everything done with the exception of putting on a few hooks on the screen doors and a very few little necessary things, and that this was attended to within a few days and that the building was then accepted by them. It appears, also, that on April 13th the owner and contractor had a settlement and at that time agreed to eliminate certain work from the contract, and deductions were made for the things omitted. This was in accordance with the provisions of the contract between the parties, and the evidence shows that the contract, as thus modified, was completely executed.

We have, therefore, not only constructive, but actual, completion of the building, not later than May 2, 1914. As to the circumstances of occupation and acceptance of the building, section 1187 of the Code of Civil Procedure provides that: “In all cases, any of the following shall be deemed equivalent to a completion for all the purposes of this chapter”: 1. “ The occupation or use of a building, improvement, or structure, by the owner,” or 2. “The acceptance by said owner or said agent, of said building, improvement, or structure.” Hence, it is entirely clear that we cannot question the finding of the court that said building for all the purposes of filing a mechanic’s lien was completed on May 2, 1914.

In reference to certain facts which the law declares to be sufficient to support the conclusion that the building for the purpose of a lien has been completed, it may be stated that the *536 statute has undergone certain changes, which are pointed out in various decisions of the courts. From 1887 to 1897 said section of the statute limited the operation of the occupation or use and acceptance to those cases wherein there was a duly recorded contract, the legislature having provided “and in case of contracts, the occupation,” etc. In the latter year the section was amended so as to make occupation and acceptance apply to all cases, hut a further amendment was added to the effect that either must be coupled with cessation from labor for thirty days in order to constitute constructive completion. These changes are fully discussed in Robison v. Mitchel, 159 Cal. 586, [114 Pac. 984], and we need not dwell upon them further. Then comes the amendment of 1911, which applies to cases wherein the contract has not as well as those wherein it has been recorded; and as clear as language can make it, the section now provides that any of the three circumstances shall constitute constructive completion, namely: 1. Occupation of the building; 2. Acceptance of the building by the owner; and 3. Cessation from labor for thirty days.

By a sort of metaphysical refinement, appellant seeks to make it appear that cessation from labor for the period of thirty days must still be added to the other circumstances above mentioned to constitute completion, but the section is too plain to admit of discussion. Indeed, it is pointed out in Hughes Mfg. & Lumber Co. v. Hathaway, 174 Cal. 48, [161 Pac. 1159], that the phrase “completion of the building,” as used in the last clause of said section, “must be understood to mean either the actual completion or the completion by cessation of labor for thirty days upon the building, etc., or completion by occupation or acceptance, as the case may be.”

The ease is virtually as strong upon the theory of actual completion, since it was competent for the parties to provide for changes in the plans, and to so alter the contract, and thus to have a completely executed agreement. (White v. Soto, 82 Cal. 654, [23 Pac. 210]; Gilliam v. Brown, 116 Cal. 454, [48 Pac. 486]; Anderson v. Johnston, 120 Cal. 657, [53 Pac. 264].)

Nor is there any doubt as to the conclusion that plaintiff’s claim of lien was filed too late.

It is to be observed that the materialman 'has thirty days after he ceases to furnish materials within which to file said claim, and upon the pretense of having furnished said hinges *537 on July 10th, plaintiff claims to have brought itself within this provision. But the concluding portion of said section requires “that all claims of lien must be filed within ninety days after the completion of any building, improvement, or structure,” etc.

Appellant contends that this time limit was waived, for the reason that no notice of completion was filed by the owner. As to this appellant is in error.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Lumber Co. v. Kennedy
154 P. 25 (California Court of Appeal, 1915)
Boscus v. Waldmann
160 P. 180 (California Court of Appeal, 1916)
Yost v. Roux
149 P. 781 (California Court of Appeal, 1915)
Hughes Manufacturing & Lumber Co. v. Hathaway
161 P. 1159 (California Supreme Court, 1916)
Stimson Mill Co. v. Los Angles Traction Co.
74 P. 357 (California Supreme Court, 1903)
Robison v. Mitchel
114 P. 984 (California Supreme Court, 1911)
Brunt v. Farinholt-Meredith Co.
88 A. 42 (Court of Appeals of Maryland, 1913)
P. T. Walton Lumber Co. v. Cox
1911 OK 279 (Supreme Court of Oklahoma, 1911)
Barrows v. Knight
55 Cal. 155 (California Supreme Court, 1880)
Schwartz v. Knight
16 P. 235 (California Supreme Court, 1887)
White v. Soto
23 P. 210 (California Supreme Court, 1890)
Gilliam v. Brown
48 P. 486 (California Supreme Court, 1897)
Anderson v. Johnston
53 P. 264 (California Supreme Court, 1898)
Lane & Bodley Co. v. Jones
79 Ala. 156 (Supreme Court of Alabama, 1885)
Cross v. Eyerley
125 N.W. 1085 (Nebraska Supreme Court, 1910)
Maryland Brick Co. v. Dunkerly
36 A. 761 (Court of Appeals of Maryland, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cal. App. 533, 1918 Cal. App. LEXIS 612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emigh-winchell-hardware-co-v-pylman-calctapp-1918.