Consolidated Lumber Co. v. Bosworth, Inc.

180 P. 60, 40 Cal. App. 80, 1919 Cal. App. LEXIS 82
CourtCalifornia Court of Appeal
DecidedFebruary 26, 1919
DocketCiv. No. 2867.
StatusPublished
Cited by6 cases

This text of 180 P. 60 (Consolidated Lumber Co. v. Bosworth, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Lumber Co. v. Bosworth, Inc., 180 P. 60, 40 Cal. App. 80, 1919 Cal. App. LEXIS 82 (Cal. Ct. App. 1919).

Opinion

*82 SLOANE, J.

This,is an appeal of the defendant Bosworth, Inc., from a judgment foreclosing upon said defendant’s real property a mechanic’s lien for materials alleged to have been furnished to and used by the contractor in the construction of buildings on said premises. Appellant asks that the judgment be reversed on the following grounds:

1. That the claim of lien was not filed in time.
2. That there is a fatal variance between the lien claim and the proof as to the terms of the contract of sale.
3. That the lumber used for forms for pouring cement for the buildings is not the basis of a valid lien.
4. That the proof fails to show that the materials furnished were expressly contracted for the buildings in question.
5. That the finding as to the date of filing claim of lien is indefinite and insufficient.
6. That the complaint alleges, and the court finds, that the buildings in question were erected by virtue of an agreement, whereas the proof shows that the buildings were erected under three separate agreements.
7. That items of charges sought to be recovered are not covered by the claim of lien.

1. We will consider the first and fifth alleged grounds of error together, as both are directed to the time of filing claim, of lien. The court finds that notice of completion of these buildings was filed “on or about” the twenty-seventh day of August, 1914, and that thereafter, and “on or about” the twenty-first day of September, 1914, the claim of lien was filed. It is alleged in the complaint, and not denied in the answer, that the claim of lien was recorded, “on”. September 21,1914. The proof showed that the notice of completion was filed “on” the twenty-seventh day of August, and the claim of lien “on” the twenty-first'day of September. It also appeared in evidence that the buildings were actually completed and accepted on the twenty-first day of August. [1]; Appellant argues that the time for filing claim of lien began to run from the date of completion, and that more than thirty days elapsed before the filing of the lien claim, if it was filed September 21st; and that, in any event, the finding is too indefinite in fixing the time “on or about” the dates mentioned. Whatever merit this contention might have if under the facts the last day for filing the claim had been on the 20th or 21st *83 of September, it is without force under the recent decisions that a lien claimant for materials furnished a contractor may make his filing within thirty days after the date of filing notice by the owner of completion of the contract. (Hughes Mfg. & L. Co. v. Hathaway, 174 Cal. 44, [161 Pac. 1159]; Pioneer Paper Co. v. Hathaway, 39 Cal. App. 405, [179 Pac. 227].) [2] In this ease the claimant had several days remaining afteF September 21st, in which he might file his claim of lien, and with this margin of time a finding that the notice of completion was filed “on or about” the 27th of August, and the notice of lien “on or about” the 21st of September, is probably sufficiently definite as a finding that the lien claim was made within a period of thirty days; particularly as there is no question under the evidence as to that fact. If we were to concede that, as to this question, appellant’s position were well taken, nevertheless, since we could not say upon this record that it was made to appear that justice had miscarried, it would be a proper case for the application of section 4% of article VI of the constitution.

2. There is more room for dispute on appellant’s second proposition. The complaint alleges, and it is set forth in the claim of lien, as follows: “That all of said materials were sold and delivered from time to time upon open account, commencing on the twenty-eighth day of April, 1914, and ending on the twenty-ninth day of July, 1914; that there was no express agreement as to the price to be paid for said materials, nor was there any time expressly agreed upon for the payment thereof; but that said materials, at the time of the sale and delivery thereof, were of the reasonable market value of fourteen hundred fifty-eight dollars ($1458), upon which said sum has been paid two hundred fifty dollars ($250), and no more.” [3] It is appellant’s contention that the proof shows a specific agreement between Dowell, the contractor, and respondent as to the price for which this lumber was sold and delivered—namely, a fixed and agreed rate per thousand feet. If the record shows, as contended, that a specific' sum of money, distinguishable from and independent of the market price, was agreed upon between the parties as the consideration of this sale, there can be no question, under the repeated rulings of the supreme court, that such fact would establish a fatal variance between the lien claim and the proof. (Reed v. Norton, 90 Cal. 590, [26 Pac. 767, 27 Pac. 426] ; Wagner v. Hansen, *84 103 Cal. 104, [37 Pac. 195] ; Wilson v. Nugent, 125 Cal. 280, [57 Pac. 1008] ; Robinett v. Brown, 167 Cal. 735, [141 Pac. 368] ; Buell & Co. v. Brown, 131 Cal. 158, [63 Pac. 167].)

In the case last cited the contract was the same as here claimed by appellant. The court there says: “The court found that the claim of lien set forth a contract to deliver the material at the reasonable market rate, but that the contract was an express one, to wit, $26.50 per thousand for lumber, and $2.50 per thousand for shingles. This was a fatal variance, and prevents a recovery by plaintiff.” The substance of the evidence given on this point in the ease at bar is as follows : “They were to furnish lumber for certain prices per thousand, and they furnished that lumber. I would say that the- price that was paid for the lumber was the market price at that time. There was an agreement to a certain amount. It was practically the market price at that time. It was a certain amount per thousand; it was not a lump sum. There was an amount fixed and agreed upon for each class of lumber per thousand feet, on the first order. We had o,ur understanding as to the price per thousand feet when we first went there. Q. And they agreed that they would furnish you certain lumber at so much a thousand feet ? A.- For that list of lumber that I submitted to them for prices. After that I simply sent in orders for additional lumber, and they furnished it. Q. And at the same prices which you had previously agreed upon? A. I couldn’t say they charged the same prices in each case. I think they did. I do not remember that they deviated from the prices they had agreed upon. My understanding at the start was that the plaintiff would sell the lumber at so much per thousand feet for certain classes of lumber ; and afterwards I sent in orders for more lumber, and it was furnished, and they charged on their bills the same prices originally agreed upon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ivy Trucking, Inc. v. Creston Brandon Corp.
100 Cal. Rptr. 2d 582 (California Court of Appeal, 2000)
Fontana Paving, Inc. v. Hedley Brothers, Inc.
38 Cal. App. 4th 146 (California Court of Appeal, 1995)
Gary C. Tanko Well Drilling, Inc. v. Dodds
117 Cal. App. 3d 588 (California Court of Appeal, 1981)
Hayward Lumber & Investment Co. v. Ross
90 P.2d 135 (California Court of Appeal, 1939)
Arata & Peters, Inc. v. Snow Mountain Water & Power Co.
267 P. 932 (California Court of Appeal, 1928)
L. W. Blinn Lumber Co. v. Pioneer Drainage District
195 P. 732 (California Court of Appeal, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
180 P. 60, 40 Cal. App. 80, 1919 Cal. App. LEXIS 82, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-lumber-co-v-bosworth-inc-calctapp-1919.