Kritzer v. Tracy Engineering Co.

116 P. 700, 16 Cal. App. 287, 1911 Cal. App. LEXIS 137
CourtCalifornia Court of Appeal
DecidedMay 23, 1911
DocketCiv. No. 973.
StatusPublished
Cited by17 cases

This text of 116 P. 700 (Kritzer v. Tracy Engineering Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kritzer v. Tracy Engineering Co., 116 P. 700, 16 Cal. App. 287, 1911 Cal. App. LEXIS 137 (Cal. Ct. App. 1911).

Opinion

SHAW, J.

Action to foreclose a mechanic’s lien.

Judgment went for plaintiff, from which the defendant Orange Blossom Mining and Milling Company appeals upon the judgment-roll alone. It appears from the complaint that at the times in question the Orange Blossom Mining and Milling Company owned ten contiguous mining claims consolidated and operated as one mine, known as the Orange Blossom Mine, and also owned a millsite located at Bagdad Station, nine miles distant from said mine. That defendant entered into a contract with the Tracy Engineering Company whereby the latter, for the gross sum of money therein specified, agreed to erect and construct a power plant upon said millsite, and erect and construct upon the mining *289 claim known and designated as the Orange Blossom claim a stamp-mill and install certain mining machinery, appurtenances and fixtures, together with a transmission line extending from the power plant at Bagdad Station to the power-house and improvements to be constructed upon the Orange Blossom Mining Claim, and to furnish the materials and labor necessary in the construction and completion of said work. That said Tracy Engineering Company employed plaintiff to act as foreman of the construction work so undertaken and agreed to be performed by it, under the terms of which employment plaintiff was to render services as foreman and superintendent in the construction of said work and improvements, and in consideration for such services the Tracy Engineering Company promised and agreed to pay plaintiff therefor the sum of $200 per month while so employed, together with his traveling expenses from the city of New York to Bagdad, California, and return therefrom to New York upon the completion of the plant. That plaintiff entered upon said work, and between the twenty-fourth day of March, 1908, and the twenty-fourth day of November, 1908, performed the work and labor of superintending the erection, construction and installation of said improvements so agreed to be constructed and installed by the Tracy Engineering Company, and in the capacity of such foreman and superintendent performed eight months’ labor thereon, which said work and labor actually entered into the construction of said improvements- so made upon said millsite and mining properties, and that the reasonable value of the labor and services so done and performed was the amount so agreed upon, to wit, $200 per month and his traveling expenses to and from New York City, amounting to the sum of $226.08, and making a total of $1,826.08 due to him for such work and labor so performed, upon which there was paid the sum of $201.81 and no more; that said work and improvements were fully completed and possession thereof delivered to the defendant, Orange Blossom Mining and Milling Company, on November 22, 1908; followed by sufficient allegations of the filing of a duly verified claim of lien in form and containing a statement of the matters and things required by statute.

1. Appellant assigns as error the fact that the court made no findings, and it insists that they were not waived. We *290 cannot presume that mere absence of findings constitutes error. Every intendment goes to support the judgment, and, since findings of fact may be waived (Code Civ. Proc., sec. 634), then, in the absence of some affirmative showing to the contrary, by bill of exceptions or in other appropriate manner, the presumption arises that they were waived. (Mulcahy v. Glazier, 51 Cal. 626; Campbell v. Coburn, 77 Cal. 36, [18 Pac. 860].) Appellant directs our attention to a minute entry made by the clerk, a copy of which is brought up in the transcript. This, however, is no part of the judgment-roll, for the reason that it relates, neither to an order striking out pleading, nor one made on demurrer. (Code Civ. Proc., sec. 670.) Even were it so regarded, it does not show that findings were not waived. Moreover, the judgment states that findings of fact and conclusions of law were waived by the failure of the defendant, Orange Blossom Mining and Milling Company, to appear and participate in the trial. This recital by the court must, in the absence of any showing to the contrary, be regarded as conclusive.

2. It is next contended that plaintiff could have no right to a lien for his traveling expenses to and from New York, and that including the amount of such expenses in his. claim of lien rendered the same void. Therefore, it is contended the complaint was obnoxious to the general demurrer interposed by defendant and rendered the judgment against law. As to this point, it is sufficient to say that the demurrer was overruled by consent; hence, if the judgment was erroneous by reason of being against law, defendant, having consented thereto, cannot be heard now to complain upon such ground (Erlanger v. Southern Pac. R. R. Co., 109 Cal. 395, [42 Pac. 31]; Estate of Lorentz, 124 Cal. 495, [57 Pac. 381]). Neither does the record disclose any fact which renders the lien void. The complaint sets forth the contract made between plaintiff and the Tracy Engineering Company, from which it appears that the latter agreed to pay him for eight months’ labor and work performed the sum of $1,826.08; that the sum of $201.81, and no more, had been paid thereon, leaving a balance unpaid of $1,624.27. This sum of $1,826.08 included the sum of $226.08 paid by plaintiff for transportation to and from New York, but it was as much a part of the compensation agreed to be paid to him under the terms of the *291 contract as was the $200 per month. He claimed no lien for it as traveling expenses, but claimed a lien for the full amount on account of the labor and work performed by him pursuant to the terms of the contract, alleging said sum to be the reasonable value of the services performed, and the court so found. A different case would be presented if those who furnished the transportation were claiming, or seeking to enforce, a lien therefor.

3. Section 389, Code of Civil Procedure, provides that, “when a complete determination of the controversy cannot be had without the presence of other parties, the court must then order them to be brought in, and to that end may order amended and supplemental pleadings, or a cross-complaint to be filed, and summons thereon to be issued and served.” It is claimed that at the time of the trial defendant had been adjudicated a bankrupt. Appellant insists that before proceeding with the trial it was the duty of the court, as provided in said section 389, to make an order bringing in the trustee in bankruptcy as a party defendant. There is no pleading and nothing of record showing that defendant had been adjudicated a bankrupt, or that a trustee in bankruptcy had been appointed. .Conceding, as claimed by appellant, that such fact appears from the minute entry made by the clerk, a copy of which is printed in the transcript, nevertheless, as heretofore stated, this minute entry is no part of the judgment-roll and cannot be considered upon this appeal for any purpose. Assuming as true, however, the alleged fact that defendant had been adjudicated a bankrupt subsequent to the filing of its answer, we are unable to perceive why the presence of the trustee was necessary to a complete determination of the controversy, since the action was merely to foreclose an existing lien held by plaintiff, there being no demand for a personal judgment.

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flintkote Co. v. Lisa Construction Co.
268 Cal. App. 2d 606 (California Court of Appeal, 1968)
Lembke Construction Co. v. JD Coggins Company
382 P.2d 983 (New Mexico Supreme Court, 1963)
Vowels v. Witt
308 P.2d 415 (California Court of Appeal, 1957)
Lahn v. Structural Pest Control Board
287 P.2d 17 (California Court of Appeal, 1955)
Childers v. Childers
168 P.2d 218 (California Court of Appeal, 1946)
Heffner v. Jackson
273 P. 37 (California Court of Appeal, 1928)
Todd v. Meserve
269 P. 710 (California Court of Appeal, 1928)
People v. Myers
245 P. 1106 (California Court of Appeal, 1926)
Consolidated Lumber Co. v. Bosworth, Inc.
180 P. 60 (California Court of Appeal, 1919)
City of Oakland v. Wheeler
168 P. 23 (California Court of Appeal, 1917)
Morrison v. W. L. Green Commission Co.
1916 OK 968 (Supreme Court of Oklahoma, 1916)
Tube City Mining & Milling Co. v. Otterson
146 P. 203 (Arizona Supreme Court, 1914)
Pugh v. Moxley
128 P. 1037 (California Supreme Court, 1912)
Acme Lumber Co. v. Wessling
126 P. 167 (California Court of Appeal, 1912)
Erving v. Napa Valley Brewing Co.
122 P. 836 (California Court of Appeal, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
116 P. 700, 16 Cal. App. 287, 1911 Cal. App. LEXIS 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kritzer-v-tracy-engineering-co-calctapp-1911.