Flintkote Co. v. Lisa Construction Co.

268 Cal. App. 2d 606, 74 Cal. Rptr. 136, 1968 Cal. App. LEXIS 1351
CourtCalifornia Court of Appeal
DecidedDecember 31, 1968
DocketCiv. 32370
StatusPublished
Cited by1 cases

This text of 268 Cal. App. 2d 606 (Flintkote Co. v. Lisa Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flintkote Co. v. Lisa Construction Co., 268 Cal. App. 2d 606, 74 Cal. Rptr. 136, 1968 Cal. App. LEXIS 1351 (Cal. Ct. App. 1968).

Opinion

DUNN, J.

Defendant Lisa Construction Company is a joint venture composed of codefendants Violet Estates Incorporated and Sands Homes Incorporated. Lisa was the owner of Lots 1 through 10, inclusive, of Tract 21769 in Northridge, Los Angeles County. Lisa acted as its own general contractor in developing the property, building a residence on each of the ten lots. Most of the work was done by subcontractors. On June 7, 1963, Lisa made a written contract with The Shiffman Company whereby Shiffman agreed to install the concrete foundations for the residences at a price of $1,200 per unit. It provided for progress payment to be made by Lisa to Shiffman in usual fashion and that payment checks would be issued by Lisa payable jointly to Shiffman and its material supplier.

In 1963, Shiffman was the foundation subcontractor for a number of other projects obtaining necessary cement and reinforcing steel from plaintiff herein, The Flintkote Company doing business as “Blue Diamond Company.” Shiffman secured cement and steel for the Lisa contract from plaintiff. Plaintiff furnished the materials to Shiffman under an open book account, the cost of materials used on the job being $7,108.76. The price was computed and determined in the aggregate and as a total sum. There was no agreement between plaintiff and Shiffman as to the amount or value of materials that would be used in the construction of any specific lot or improvement. The materials were delivered to the tract in the aggregate and without reference to any lot or improvement. All of the materials were used in construction of the concrete foundations for the 10 houses.

Shiffman completed its work under the Lisa contract between September 9 and October 29, 1963. Before October 29th defendants paid Shiffman all sums due under its subcontract making its checks payable to Shiffman, alone. However, Shiffman never paid to plaintiff the amount owing for the materials mentioned.

The plaintiff had no knowledge of the agreement between Shiffman and defendants. Similarly, defendants were unaware that plaintiff furnished materials to the jobsite until receiving *608 from plaintiff the statutory preliminary notice given January 6, 1964, pursuant to Code of Civil Procedure, section 1193 (as it then read). Thereafter, and within the time provided by the Code of Civil Procedure, section 1193.1, plaintiff gave notice of its claim of lien and recorded it January 24,1964.

In its complaint filed April 16, 1964, plaintiff sought to impose and foreclose its mechanic’s lien on the 10 lots mentioned. On May 1, 1964, it recorded its “Notice of Pendency of Action to Foreclose Materialman’s Lien.” Defendants had sold five of the lots to individual purchasers who had recorded their deeds before the complaint was filed. None of these purchasers was named as a defendant in the complaint, however, and the judgment excluded the lots from the lien. The trial court found plaintiff was entitled to a lien upon the remaining five lots for the total value of the materials furnished by plaintiff for use upon the project. These five lots had been sold by the defendants, through escrows after the complaint was filed, four of them being conveyed after lis pendens recordation. As part of its judgment the court decreed that these properties could be sold by the sheriff at public auction, the proceeds to be used in satisfaction of judgment.

Defendants’ first ground of appeal is based upon Code of Civil Procedure sections 1194.1 and 1195.1. Code of Civil Procedure section 1195.1 states that if a work of improvement “. . . consists in the construction of two or more separate residential units, each such unit shall be considered a separate ‘work of improvement’ or ‘improvement.’ . . . Materials delivered to or upon any portion of said entire work of improvement or furnished to be used in said entire work of improvement and ultimately used or consumed in one of such separate residential units shall, for all the purposes of this chapter, be deemed to have been furnished to be used or consumed in the separate residential unit in which the same shall have been actually used or consumed; provided, however, that if the lien claimant is unable to segregate the amounts used on or consumed in such separate units he shall be entitled to all the benefits of Section 1194.1 of this code.”

Code of Civil Procedure section 1194.1 reads, in part: “ (a) In every case in which one claim is filed against two or more buildings ... or other improvements owned ... by the same person . . . the person filing such claim must at the same time, designate the amount due to him on each of such buildings . . .; otherwise the lien of such claim is postponed to other liens. ’ ’

*609 Appellants claim that the work of improvement consisted of constructing 10 single-family residential units on 10 separate lots, and that each unit was to be built under the same floor plan and specifications. Appellants would infer that the materials furnished by plaintiff were apportioned equally between the 10 foundations, and then rely upon the phrase in Code of Civil Procedure, section 1194.1, that: “In every ease in which one claim is filed against two or more buildings . . . , the person filing such claim must at the same time, designate the amount due to him on each of such buildings. ...” (Italics added.) Absent such designation, appellants claim the lien must fall.

To be noted in response is the further language of Code of Civil Procedure, section 1194.1, that “. . . otherwise the lien of such claim is postponed to other liens.” This is the only penalty on a claimant who fails to designate the amount due to him on each building or improvement, where such designa- • tion is possible. Secondly, there is no evidence that respondent was aware of the terms of the contract between appellants and Shiffman. It is clear from the record that construction of all 10 houses was undertaken simultaneously and was treated by Shiffman as one job or project. Shiffman kept a single set of ledger pages and made no attempt to allocate costs of materials. Respondent made deliveries to the jobsite and submitted invoices for each day’s deliveries, making no effort (and, indeed, having no basis) to designate materials for use in one particular foundation or the other. The findings of the trial court in that respect are amply supported by the evidence.

Third, appellants’ interpretation of the code section is contrary to precedent. In Kritzer v. Tracy Engineering Co. (1911) 16 Cal.App. 287 [116 P. 700], a judgment foreclosing a mechanic’s lien was sustained. The plaintiff had been employed as a foreman-superintendent on the construction of buildings on two jobs, nine miles apart, being a mine and millsite. His work was done under a single contract, and it was the defendant’s contention that Code of Civil Procedure section 1188 (now § 1194.1) required plaintiff to designate the amount due to him for his supervisorial work on each project. In disagreeing with this position, the court noted that it was impossible for him to so segregate his labors and went on to state (p. 292) : “. . . Moreover, even if this was not true, and conceding the work was done upon distinct and separate properties under separate contracts, nevertheless, since there were no other lien claimants, whose rights could be affected, it *610

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ballard v. Lawyers Title of Arizona
552 P.2d 455 (Court of Appeals of Arizona, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
268 Cal. App. 2d 606, 74 Cal. Rptr. 136, 1968 Cal. App. LEXIS 1351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flintkote-co-v-lisa-construction-co-calctapp-1968.