Nevada County Lumber Co. v. Janiss

78 P.2d 200, 25 Cal. App. 2d 579, 1938 Cal. App. LEXIS 863
CourtCalifornia Court of Appeal
DecidedApril 1, 1938
DocketCiv. 5902
StatusPublished
Cited by9 cases

This text of 78 P.2d 200 (Nevada County Lumber Co. v. Janiss) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nevada County Lumber Co. v. Janiss, 78 P.2d 200, 25 Cal. App. 2d 579, 1938 Cal. App. LEXIS 863 (Cal. Ct. App. 1938).

Opinion

THOMPSON, J.

In a suit to foreclose a mechanic’s lien, judgment was rendered against George M. Bobst, the contractor for $799.07, the unpaid balance due plaintiff for materials furnished and used to construct two duplex cabins for Lorraine Janiss upon adjacent parcels of land in Nevada County. The two similar duplex cabins were constructed at the same time by the same contractor under separate agreements. The orders for materials for the two buildings were not segregated. The materials were hauled to the premises and divided equally between the two structures as the work progressed. , The plaintiff kept but one account against the contractor for materials sold for both buildings. Payments were credited to that account without regard to the separate buildings which were being constructed. After the work was completed a balance of $799.07 for materials purchased remained unpaid. A notice of claim of lien was filed by the plaintiff as provided by section 1187 of the Code of Civil Procedure, March 16, 1936. The adjoining tracts upon which the two duplex cabins were built are designated as parcels “A” and “B”. The court rendered a decree vesting a mechanic’s lien for the full amount of the unpaid balance against parcel “B” belonging to the defendant, Lorraine Janiss, and directed the sale of that property to satisfy the judgment. Prom that judgment the defendant Janiss, only, has appealed.

The appellant contends that two findings which were adopted by the court are not supported by the evidence. The challenged findings are to the effect that the notice of claim of lien "was filed December 20, 1935, within the ninety days’ limitation prescribed by section 1187 of the Code of Civil Procedure and that all materials represented by the unpaid *582 balance of $799.07, were used in the building constructed on parcel “B” of the land involved in this suit.

It is conceded the two buildings were exactly alike in plans, specifications and costs thereof. The contract for the one to be built on parcel “A” was executed September 23, 1935. The one to be constructed on parcel “B” was made October 8, 1935. The defendant, Janiss, owns both pieces of property. Both buildings were, however, constructed by the same contractor at the same time. The contracts were not recorded, nor was the notice of completion of the buildings filed by the owner in the office of the county recorder.

We are of the opinion the court’s findings that the building on parcel “B” was not completed until December 20, 1935, and that the notice of claim of lien which was filed March 16, 1936, was therefore within the authorized statutory time, are supported by the evidence. It is true that one part of the duplex cabin on parcel “B” was occupied by a tenant of the defendant, Janiss, on December 2, 1935, but substantial work necessary to the completion of the contract was performed as late as December 20, 1935. The appellant contends that the occupancy of the premises by a tenant on December 2nd constituted acceptance of the premises and acknowledgment of completion of the job, and that the services which were later performed were unsubstantial and did not extend the time when the job is deemed to have been completed.

Section 1187 of the Code of Civil Procedure specifies certain circumstances which “shall be deemed equivalent to a completion” of a contract for the purposes of that chapter of the code. The provision relied on by the appellant declares that 11 the occupation or use of a building ... by the owner, or his representative, accompanied by cessation from labor thereon” will be deemed to constitute a completion of the job, for the purpose of determining the limitation of time within which a notice of claim of lien may be filed. It will be observed the statute does not declare that mere occupation of the building is sufficient to set the statute of limitations running. That occupation must be accompanied by cessation from labor thereon. The question of the completion of a building is one of fact, with the determination of which we may not *583 interfere where there is substantial evidence to support the finding in that regard.

The fulfillment of the contract in question required the construction of a suitable sewer system to connect the building with a septic tank. The sections of this sewer pipeline had been so joined that the cement which was used for that purpose filled the pipes and obstructed the drainage. The system failed to operate. Within the time allowed for filing the notice of claim of lien, the attention of the contractor was called to that defect, and on the 16th, 17th, and 20th of December, he, in company with other workmen, procured the necessary materials and removed the drainpipes, replacing them with other sections to complete his contract. Eleven hours of work and three men were employed in completing the job. Mr. D. T. Smith, the plumber who, in company with the contractor, worked on the project, testified in that regard:

“I cleared a sewer line, so the water would travel from the house to the septic tank instead of backing up in the line and flooding the floors in the house. ... I put on sewer cocks or water faucets on the side of the house. . . . Instead of putting it together in the way it should have been done they had forced all the cement in the joint and the water wouldn’t go through. . . . Q. Were there fourteen pieces of four inch, two foot, vitrified sewer pipe [used on that job] ? . . . A. Yes, but to pick up both houses. (The Court) Did they each have a separate tank? A. No. ... It had to be fixed before it would operate. . . . Q. How much time did you put in in putting those on or installing those items ? A. Eleven or twelve hours. . . . The date on the first tag 8892 [when the work was performed] is December 16th, the date on the next tag is December 17th, the 9902 tag. The last tag number 9039, • was December 20th [when the work was completed]. . . . This work consisted of repairing a line to the septic tank? A. No, I put in a whole new line. . . . The line never functioned because the water would never go through it. . . . Q. You removed the pipe line that was put in originally and put in a new one? A. Yes sir.”

This furnishes evidence that the building with its necessary sewer system was not completed until December 20, 1935. The notice of claim of lien was filed March 16, 1936, which *584 was within the ninety-day period of time allowed by the statute.

The appellant contends that since a mechanic’s lien may be established for the value of materials, only, which have actually been used in the construction of the particular building sought to be charged, the lien in this case should have been limited to one-half of the amount of the unpaid balance, for the reason that all materials were equally divided between the two structures. The rule is well established that a mechanic’s lien will vest only to secure payment for materials which are actually used in a particular building. It is said in Stimson Mill Co. v. Los Angeles Traction Co., 141 Cal. 30 [74 Pac. 357] :

“It is settled by many decisions in this state that to entitle a materialman to a lien under section 1183 of the Code of Civil Procedure the materials must be furnished to be used,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Framing Systems Inc. v. Luzuriaga
California Court of Appeal, 2019
Precision Framing Sys. Inc. v. Luzuriaga
251 Cal. Rptr. 3d 858 (California Court of Appeals, 5th District, 2019)
North American Capacity Insurance v. Claremont Liability Insurance
177 Cal. App. 4th 272 (California Court of Appeal, 2009)
Flintkote Co. v. Lisa Construction Co.
268 Cal. App. 2d 606 (California Court of Appeal, 1968)
Munger & Munger v. McBratney
280 P.2d 232 (California Court of Appeal, 1955)
Newt Olson Lumber Co. v. Cue
232 P.2d 64 (California Court of Appeal, 1951)
Baird v. Havas
164 P.2d 952 (California Court of Appeal, 1946)
Hundley v. Marinkovich
127 P.2d 600 (California Court of Appeal, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
78 P.2d 200, 25 Cal. App. 2d 579, 1938 Cal. App. LEXIS 863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nevada-county-lumber-co-v-janiss-calctapp-1938.