Precision Framing Systems Inc. v. Luzuriaga

CourtCalifornia Court of Appeal
DecidedAugust 29, 2019
DocketE069158
StatusPublished

This text of Precision Framing Systems Inc. v. Luzuriaga (Precision Framing Systems Inc. v. Luzuriaga) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Precision Framing Systems Inc. v. Luzuriaga, (Cal. Ct. App. 2019).

Opinion

Filed 8/29/19

CERTIFIED FOR PARTIAL PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION TWO

PRECISION FRAMING SYSTEMS INC., E069158 Plaintiff and Appellant, (Super.Ct.No. MCC1400466) v. OPINION HENRY LUZURIAGA et al.,

Defendants and Appellants.

APPEAL from the Superior Court of Riverside County. Gloria Trask and Angel

M. Bermudez, Judges.⸸ Affirmed.

Tyler & Bursch, Jennifer L. Bursch, James A. Long, and Nada N. Higuera for

Plaintiff and Appellant.

 Pursuant to California Rules of court, rules 8.1105(b) and 8.1110, this opinion is certified for publication with the exception of parts III, V, VI, and VII.

⸸ Judge Trask denied the motion to compel production of documents and summarily adjudicated one of the affirmative defenses. Judge Bermudez granted the motion for summary judgment, entered judgment, and awarded costs. Law Offices of Jonathan C. Stevens and Jonathan C. Stevens for Defendants and

Appellants.

Henry and Deborah Luzuriaga contracted with a general contractor for the

construction of a commercial building. The general contractor, in turn, contracted with

Precision Framing Systems, Inc. (Precision) for the framing, including the necessary

trusses. And Precision contracted with Inland Empire Truss, Inc. (Inland) for the

fabrication of the trusses. Precision never received full payment. Accordingly, it

recorded a mechanic’s lien claim.

Meanwhile, there was a problem with some of the trusses. There was much

finger-pointing as to who was to blame. After Precision had already recorded its

mechanic’s lien claim, Precision and/or Inland came back to the site and repaired the

trusses.

Precision filed this action to foreclose its mechanic’s lien. Ms. Luzuriaga filed a

cross-complaint. The trial court granted summary judgment against Precision on its

complaint. It ruled that the mechanic’s lien claim was filed prematurely — i.e., before

Precision had “cease[d] to provide work.” (Civ. Code, § 8414, subd. (a).)

Precision appeals. Its primary contention is that there was a triable issue of fact as

to whether it had ceased to provide work, because (1) “ceas[ing],” within the meaning of

the statute, can be a gradual process, (2) the repair of the trusses was not part of

Precision’s “work,” (3) there was evidence that Precision completed all of its work before

2 it recorded its mechanic’s lien claim, and (4) there was evidence that the repairs were

done by Inland. Henry Luzuriaga and the Luzuriagas’ bonding company cross-appeal.1

We will affirm. We agree with the trial court: The evidence showed, beyond a

triable issue of fact, that Precision had not yet “cease[d] . . . work” when it recorded its

mechanic’s lien claim. This moots the cross-appeal.

I

FACTUAL BACKGROUND

The following facts are taken from the evidence introduced in connection with the

motion for summary judgment.

The Luzuriagas undertook the construction of a veterinary hospital on a piece of

property that they owned in Wildomar. They hired an architect and a general contractor.

The general contractor, in turn, hired Precision as the framing subcontractor. Precision’s

contract stated that that the contact price was “for labor, lumber, trusses, and hardware

necessary to complete the . . . project.” (Capitalization altered.)

George Mears is the president of Precision. He testified that Precision was

supposed to “supply and install[]” the trusses. In its interrogatory responses, Precision

stated that its scope of work consisted of framing, including “procurement of materials

(lumber[,] hardware and trusses).”

1 Ms. Luzuriaga also cross-appealed, but we dismissed her because her cross- complaint is still being litigated.

3 Precision selected Inland to design and manufacture the trusses. As Mears put it,

“Precision used Inland” for the trusses. Inland contracted solely with Precision and

invoiced Precision, although Inland was paid directly by the construction lender.

Inland designed the trusses, based on the plans and specifications, and built them.

However, the architect had to approve the truss design, incorporate it into his plans, and

make sure they matched (redesigning his own plans if necessary). Thus, as the general

contractor testified, the “truss details” were “ultimately[] the architect’s responsibility.”2

On July 24, 2013, Precision started work on the framing. On July 29, 2013, Inland

delivered the trusses to the site. On August 2, 2013, Precision began installing the

On August 7, 2013, the city issued a correction notice relating to the trusses. It

stated: “Truss bearing points are not as per plan . . . .” In the architect’s opinion, this

was because the trusses were not fabricated in accordance with the plan. On August 14,

2013, Precision notified Inland that the trusses were defective. Later in August 2013,

Inland carried out some repairs to the trusses.

On December 9, 2013, the city issued a second correction notice relating to the

2 Precision claims there was evidence that the architect designed the trusses. The cited portions of the record do not support this. The architect himself testified that he designed the floor plan, which specified the bearing points for the trusses — i.e., the points at which the rest of the building was supposed to support them — but he did not design the trusses themselves. We have found no other evidence contradicting this. The designs themselves are in the record and have Inland’s logo on them.

4 On December 23, 2013, the general contractor and Precision’s superintendent

“walked the [p]roject” together. The general contractor found that Precision’s work was

complete and fully in compliance with the plans and specifications. At that point,

according to both Mears and the general contractor, Precision had completed its scope of

work. The city approved Precision’s framing work.

Precision, however, never received full payment. Ms. Luzuriaga told Mears “she

was not interested in paying Precision and told [him] to sue her.” Accordingly, on

January 2, 2014, Precision recorded its mechanic’s lien claim for $53,268.16.

Sometime between January 2 and 29, 2014, the Luzuriagas changed the locks of

the building, locking out all contractors.

Sometime between January 20 and 29, 2014, Mears met with the architect and the

building inspector. At this meeting, he later testified, he first became aware of the

correction notices.3

On January 29, 2014, Ms. Luzuriaga took the position that Precision’s mechanic’s

lien claim was “premature” because it had not yet completed its scope of work, and in

particular because the correction notices were still outstanding. She asked, “Does

Precision . . . intend to return to the job and correct the issues that are pending?” Mears

3 By August 14, 2013, Precision knew there was a problem with the bearing points of some of the trusses. Moreover, by December 31, 2013, it knew the building inspector had raised “a question” about the trusses. On January 9, 2014, it received Inland’s engineering drawing of the proposed repair. On January 11, 2014, it asked Inland when it was going to do this repair. However, there is no evidence that it was aware specifically of the outstanding correction notices before the January meeting.

5 responded, “We intend on completing any work pursuant to our contract . . . [W]e are

willing to meet and discuss any remaining scope . . . .”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise v. DLA Piper CA4/1
220 Cal. App. 4th 1180 (California Court of Appeal, 2013)
Justus v. Atchison
565 P.2d 122 (California Supreme Court, 1977)
Hutnick v. United States Fidelity & Guaranty Co.
763 P.2d 1326 (California Supreme Court, 1988)
Hundley v. Marinkovich
127 P.2d 600 (California Court of Appeal, 1942)
Ochoa v. Superior Court
703 P.2d 1 (California Supreme Court, 1985)
Nevada County Lumber Co. v. Janiss
78 P.2d 200 (California Court of Appeal, 1938)
Decoto School District v. M. & S. Tile Co.
225 Cal. App. 2d 310 (California Court of Appeal, 1964)
North Bay Construction Inc. v. City of Petaluma
49 Cal. Rptr. 3d 455 (California Court of Appeal, 2006)
Sosinsky v. Grant
6 Cal. App. 4th 1548 (California Court of Appeal, 1992)
Aguilar v. Atlantic Richfield Co.
24 P.3d 493 (California Supreme Court, 2001)
Schachter v. Citigroup, Inc.
218 P.3d 262 (California Supreme Court, 2009)
Elsner v. Uveges
102 P.3d 915 (California Supreme Court, 2004)
Boeken v. PHILIP MORRIS USA, INC.
230 P.3d 342 (California Supreme Court, 2010)
Lockheed Martin Corp. v. Superior Court
63 P.3d 913 (California Supreme Court, 2003)
Cheal v. El Camino Hospital
223 Cal. App. 4th 736 (California Court of Appeal, 2014)
Brewer Corp. v. Point Center Financial, Inc.
223 Cal. App. 4th 831 (California Court of Appeal, 2014)
Moorefield Construction, Inc. v. Intervest-Mortgage Investment Co.
230 Cal. App. 4th 146 (California Court of Appeal, 2014)
Picerne Construction Corp. v. Castellino Villas
244 Cal. App. 4th 1201 (California Court of Appeal, 2016)
Grettenberg v. Collman
5 P.2d 944 (California Court of Appeal, 1931)
Ferger v. Gearhart
186 P. 376 (California Court of Appeal, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
Precision Framing Systems Inc. v. Luzuriaga, Counsel Stack Legal Research, https://law.counselstack.com/opinion/precision-framing-systems-inc-v-luzuriaga-calctapp-2019.