Jaekle v. Halton

78 P.2d 441, 25 Cal. App. 2d 706, 1938 Cal. App. LEXIS 887
CourtCalifornia Court of Appeal
DecidedApril 14, 1938
DocketCiv. 5676
StatusPublished
Cited by8 cases

This text of 78 P.2d 441 (Jaekle v. Halton) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jaekle v. Halton, 78 P.2d 441, 25 Cal. App. 2d 706, 1938 Cal. App. LEXIS 887 (Cal. Ct. App. 1938).

Opinion

THOMPSON, J.

In a suit to foreclose a mechanic’s lien for materials supplied for two separate buildings on the same property, it was held the lien was waived by conduct which created an equitable estoppel. The claim of lien is for mill-work used in constructing two separate buildings simultaneously on the same property under different contracts. A receipted bill for $525 for materials used in the bungalow constructed under the first contract was presented by the contractor to the owners of the property. Relying on that receipt the owners paid the contractor in full. The contractor appropriated the money and drew his personal check in favor of the plaintiffs in payment of the bill. His check was dishonored. The plaintiffs have not been paid. Without notice or knowledge of the dishonoring of the contractor’s fictitious check, the owners subsequently paid all claims to which the contractor was entitled. The lien for that amount was disallowed on the ground of equitable estoppel.

Regarding a claim of lien to secure payment of another bill for millwork used in constructing the separate guest house under a subsequent oral agreement, the «owners paid the contractor the further sum of $249.50 without a receipted bill from plaintiffs. That money was also appropriated by the contractor, who drew his personal check in favor of the *708 plaintiffs in payment thereof, which check was likewise dishonored. But the owners had notice on the same day of the dishonoring of this second check. The owners did not make subsequent payments to the contractor, relying upon a receipted bill for this amount. The court, however, found that this claim was also barred by conduct amounting to an equitable estoppel.

The defendants, Edward H. Halton and wife, own an acre of land at Coombsville in Napa County. May 14, 1931, they contracted in writing with the defendant Warren E. Younger to build a bungalow on that land for the agreed price of $3,750. The contract provides that payments for materials should be made to the contractor only upon receipted bills therefor. A few days later an oral agreement was made with the same contractor to construct an additional guest house on the same property under similar terms and conditions. Both buildings were built at the same time. The plaintiff furnished all the millwork for both structures. The millwork for the bungalow amounted to $525. The mill-work for the guest house came to $249.50 additional. June 24th the contractor, Younger, presented to the owners of the land the bill for millwork on the bungalow for $525, endorsed by the plaintiffs as paid in full. The following day Edward H. Halton gave Younger his check covering that bill, which was cashed by Younger that same day. June 30th Younger presented to the owners of the buildings the plaintiffs’ bill for millwork on the guest house for the additional sum of $249.50. This bill was not then receipted, but it was nevertheless paid to the contractor by the owners. This money was also appropriated by the contractor, who drew his personal check for that amount in favor of the plaintiffs on July 22d. This check was also dishonored on the following day. At the time Younger drew his second fictitious check in favor of the plaintiffs they endorsed that bill as paid in full. That receipted bill was presented to the owners on the last-mentioned date. But on that day the owners were notified of the refusal to pay Younger’s last check. With respect to the claim of lien for the 'millwork on the guest house for the sum of $249.50, the owners did not make subsequent payments, relying on that receipted bill. At the time of receiving notice of the dishonoring of the last Younger check on July 22d, the owners had paid all bills accruing under *709 the contracts for both houses, except the sum of $400 due to other materialmen for obligations already incurred. The last-mentioned bills were afterward paid.

Mr. Halton testified positively that he supposed both bills for millwork had been paid by Younger to the plaintiffs, and that he had no knowledge to the contrary until he was notified of the dishonoring of the Younger checks on July 22d; that he paid Younger the first check for millwork in the sum of $525, relying on the bill receipted by plaintiffs, including that amount, which was then delivered to the owners and retained by them; that believing plaintiffs were fully paid for that work, the owners thereafter, and prior to July 22d, paid to Younger and other claimants all sums of money to which they were entitled under the contract, except as hereinbefore stated; that on June 24th, when the first claim for millwork was paid to Younger, he was then entitled to approximately $800, which was paid to him before the owners had notice of the dishonoring of his checks.

July 24, 1931, notices of the completion of the buildings were recorded by the owners in the office of the county recorder of Napa County, as provided by law. August 19, 1931, within the thirty days’ limitation prescribed by section 1187 of the Code of Civil Procedure, plaintiffs filed their notice of claim of lien in due form. This suit was then commenced. The owners of the buildings pleaded, and the court found, that plaintiffs by their conduct waived their right to liens for materials furnished, and that they were estopped from asserting liens by prematurely receipting the bills as fully paid, and by failure to notify the owners regarding the fictitious checks until all of the money due pursuant to the contract had been fully paid or the bills therefor incurred. From the judgment which was rendered accordingly the plaintiffs have appealed.

The only questions presented on appeal are whether a materialman may waive his claim of lien by conduct amounting to an estoppel in pais, and whether the facts of this case support the findings that they did so forfeit their right to a lien.

Plaintiffs' bill for millwork furnished on the first contract for the bungalow was presented to Mr. Halton by Younger, the contractor, June 25, 1931. Edward H. Halton drew his check on that date in favor of Younger for the full *710 amount of that bill. That check was immediately cashed by Younger. On June 29th, Younger drew his personal check in favor of plaintiffs for $525, the full amount of that bill. The plaintiffs presented that check to the bank for payment the following day. Payment of Younger’s check was refused for the reason that he had no funds on deposit in the bank. When Younger gave plaintiffs his check for $525 in payment of their bill for millwork on the bungalow they receipted their bill as paid in full-on that date, June 29th. That receipted bill was immediately delivered to Mr. Halton, who assumed it was in satisfaction of that entire transaction. There appears to be some conflict of evidence regarding notice to the owners of the building of the dishonoring of Younger’s check. The court, however, found that the owners had no knowledge of that fact until July 22d, prior to which time they had paid the contractor all the money he was entitled to receive under the contract. During that interval, without knowledge of the dishonoring of the Younger check, the owners paid to him the further sum of about $800. After acquiring that knowledge the owners did pay some $400 to other subcontractors for bills previously incurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bentz Plumbing & Heating v. Favaloro
128 Cal. App. 3d 145 (California Court of Appeal, 1982)
ED McGILLICUDDY CONSTR. v. KNOLL RECREATION ASSN
31 Cal. App. 3d 891 (California Court of Appeal, 1973)
E. D. McGillicuddy Construction Co. v. Knoll Recreation Ass'n
31 Cal. App. 3d 891 (California Court of Appeal, 1973)
Flintkote Co. v. Lisa Construction Co.
268 Cal. App. 2d 606 (California Court of Appeal, 1968)
R. D. Reeder Lathing Co. v. Allen
425 P.2d 785 (California Supreme Court, 1967)
Ware Supply Co. v. Sacramento Savings & Loan Ass'n
246 Cal. App. 2d 398 (California Court of Appeal, 1966)
Western Specialty Co. v. Clairemont Construction Co.
204 Cal. App. 2d 532 (California Court of Appeal, 1962)
Balestreiri v. Arques
122 P.2d 277 (California Court of Appeal, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
78 P.2d 441, 25 Cal. App. 2d 706, 1938 Cal. App. LEXIS 887, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jaekle-v-halton-calctapp-1938.