ED McGILLICUDDY CONSTR. v. KNOLL RECREATION ASSN

31 Cal. App. 3d 891, 107 Cal. Rptr. 899
CourtCalifornia Court of Appeal
DecidedApril 26, 1973
Docket31088
StatusPublished

This text of 31 Cal. App. 3d 891 (ED McGILLICUDDY CONSTR. v. KNOLL RECREATION ASSN) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ED McGILLICUDDY CONSTR. v. KNOLL RECREATION ASSN, 31 Cal. App. 3d 891, 107 Cal. Rptr. 899 (Cal. Ct. App. 1973).

Opinion

31 Cal.App.3d 891 (1973)
107 Cal. Rptr. 899

E.D. McGILLICUDDY CONSTRUCTION CO., INC., Plaintiff, Cross-defendant and Appellant,
v.
KNOLL RECREATION ASSOCIATION, INC., Defendant and Appellant; CROCKER-CITIZENS NATIONAL BANK, Defendant, Cross-complainant and Appellant.

Docket No. 31088.

Court of Appeals of California, First District, Division Four.

April 26, 1973.

*894 COUNSEL

Bancroft, Avery & McAlister and Robert L. Dunn for Plaintiff, Cross-defendant and Appellant.

Burd, Hunt & Friedman, John J. Bartko, Tobin & Tobin, John L. Hosack, Landels, Ripley & Diamond and Edgar B. Washburn for Defendant, Cross-complainant and Appellant and for Defendant and Appellant.

OPINION

DEVINE, P.J.

Plaintiff, E.D. McGillicuddy Construction Co., Inc., appeals from a judgment which denies to plaintiff foreclosure of its mechanic's lien against certain units of a condominium project, and which not only denies plaintiff a personal judgment against Crocker-Citizens National Bank but awards money judgment in favor of the bank against plaintiff as a cross-defendant. The court declared that the lien was a valid one, but that it had been waived or that plaintiff is estopped from having it enforced. Defendants Crocker-Citizens National Bank (hereafter Crocker) and Knoll Recreation Association, Inc. (hereafter KRA) appeal from that portion of the judgment which declares plaintiff's lien to be valid.

Facts

On March 25, 1965, plaintiff agreed to construct a complex of 30 condominium units for D.M. Christensen Construction Co., Inc. (hereafter Christensen), owner and developer of a project called "The Knoll," in San Rafael. Plaintiff was to receive costs plus 7 percent, plus an overhead allowance of $7,500, payments on account to be made in the amount of $1,800 as each unit was sold. Six buildings or "blocks" were to be constructed, each block to be a self-sufficient integer. Units within each block had one continuous roof. A buyer would receive a fee interest in the air space and interior walls of his unit plus an individual interest in Parcel A, the "common area," which included the whole space of the project (other than individual air space and walls), part of which was a recreational area. Membership in a club, KRA, came with the purchase.

The trial court found that the project was a single work of improvement *895 and that no portion of the project could be regarded complete until all work on the project was finished.

McGillicuddy entered into performance of the work on May 5, 1965. On May 7, 1965, a deed of trust from Christensen to Crocker was recorded securing the former's obligations to the latter in the amount of $924,990. The property subject to the deed of trust was described as Lot 1, which was the residential portion of the project upon which condominium units were to be constructed. On the same date, Christensen conveyed Parcel A by grant deed to KRA.

Construction was financed by Crocker's loan to Christensen, which was funded by progress payments made upon requests by Christensen which were geared to stages of completion of individual units on a schedule determined by Crocker and Christensen. Construction continued during 1965 and 1966. Eleven units were sold during the course of construction, and McGillicuddy received $1,800 from each closing towards its fee, as provided by the construction contract.

It became apparent in 1965 that the loan funds would be inadequate to finance the project. Nevertheless, McGillicuddy completed the work on the project on February 16, 1966. Christensen filed notices of completion on all but two of the thirty units. No notice of completion was filed on the entire project. However, there is no dispute as to McGillicuddy's complete performance of the work. Claim of lien and amended claims were filed which covered the entire project. On the date of the filing of the second amended claim, May 6, 1966, there was due to McGillicuddy the amount of $126,161.63, an amount later reduced to $122,561.63.

On July 8, 1966, plaintiff commenced a foreclosure action. On December 8, 1966, McGillicuddy, Christensen, KRA, Crocker and certain title insurance companies made an agreement, for the purpose of having an orderly sale of the remaining units, that plaintiff's action would be held in abeyance; but they agreed that the stay might be terminated at will. Crocker commenced foreclosure of its deed of trust on August 21, 1967. This constituted termination of the stay, according to its provisions, so plaintiff called for a pleading to its complaint. The bank answered, alleging that plaintiff had been fully paid, and further asserting the superiority of its lien over any lien which plaintiff might have.

Timeliness of Filing of Claim of Lien

(1) It is convenient to discuss first the simpler of the two appeals, that *896 of defendants as cross-appellants. This appeal is from that portion of the judgment which declares that plaintiff's mechanic's lien is valid and prior to the interests of defendants in Lot 1 and Parcel A. Although the court made further conclusions against plaintiff in respect of waiver and estoppel, as described under the next heading, conclusions which defendants as respondents essay to sustain, defendants at this point assert that the purported lien is of no validity because notice was not timely filed.

The court found 1) that plaintiff fully performed the obligations of the construction contract and completed construction of the project on March 14, 1966, the last work on the buildings themselves being done on February 16, 1966; 2) that plaintiff recorded its claim of lien on April 11, 1966, an amended claim on April 12, 1966, and a second amended claim on May 6, 1966; 3) that the parties consistently treated the construction project as a single development; that it would have been impossible to apportion particular costs to particular units; and that there is no specific amount due plaintiff under the construction contract for the construction of any one unit.

If the finding be sustained that the work was completed on March 14, 1966 (it being conceded that no notice of completion of the entire project was filed), the recording, even of the second amended claim, was within 90 days and was timely. (Civ. Code, § 3115, former Code Civ. Proc., § 1193.1, subd. (a).) But defendants contend that the work was completed earlier. The problem must be considered somewhat separately as to the individual residential units and to the common use development.

a) The residential units. A notice of completion was filed by Christensen upon the finishing of construction of each of the thirty units, except two (the reason for the omission in the two cases was unknown). The determination of the date of completion of a work of improvement is a question of fact. (Scott, Blake & Wynne v. Summit Ridge Estates, Inc., 251 Cal. App.2d 347, 357 [59 Cal. Rptr. 587].) Defendants make no serious assault on the finding, but merely say that "there were separate individual residential units." Without a specific showing of how the evidence fails to support a finding, this is not an assignment of error. (6 Witkin, Cal. Procedure (2d ed. 1971) Appeal, § 425, pp. 4391-4392.)

The filing of the notices of completion of individual units, in a case where the contract was for an integrated complex and the entire work was far from completion, is premature and of no effect. (Scott, Blake & Wynne v. Summit Ridge Estates, supra, at p. 357.)

*897 b) The common area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hendrickson v. Bertelson
35 P.2d 318 (California Supreme Court, 1934)
Church v. Public Utilities Commission
333 P.2d 321 (California Supreme Court, 1958)
Jaekle v. Halton
78 P.2d 441 (California Court of Appeal, 1938)
Schrader Iron Works, Inc. v. Lee
26 Cal. App. 3d 621 (California Court of Appeal, 1972)
A. A. Baxter Corp. v. Home Owners & Lenders
7 Cal. App. 3d 725 (California Court of Appeal, 1970)
B. & J. Construction Co. v. Spacious Homes, Inc.
204 Cal. App. 2d 216 (California Court of Appeal, 1962)
Ware Supply Co. v. Sacramento Savings & Loan Ass'n
246 Cal. App. 2d 398 (California Court of Appeal, 1966)
Transport Clearings-Bay Area v. Simmonds
226 Cal. App. 2d 405 (California Court of Appeal, 1964)
Scott, Blake & Wynne v. Summit Ridge Estates, Inc.
251 Cal. App. 2d 347 (California Court of Appeal, 1967)
Xum Speegle, Inc. v. Fields
216 Cal. App. 2d 546 (California Court of Appeal, 1963)
J. W.C. Shull v. Doerr
294 P. 464 (California Court of Appeal, 1930)
Schulte v. Buben
8 P.2d 843 (California Supreme Court, 1932)
Newhall v. Hatch
66 P. 266 (California Supreme Court, 1901)
R. D. Reeder Lathing Co. v. Allen
425 P.2d 785 (California Supreme Court, 1967)
E. D. McGillicuddy Construction Co. v. Knoll Recreation Ass'n
31 Cal. App. 3d 891 (California Court of Appeal, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cal. App. 3d 891, 107 Cal. Rptr. 899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ed-mcgillicuddy-constr-v-knoll-recreation-assn-calctapp-1973.