Hayward Lumber & Investment Co. v. Ross

90 P.2d 135, 32 Cal. App. 2d 455, 1939 Cal. App. LEXIS 377
CourtCalifornia Court of Appeal
DecidedApril 27, 1939
DocketCiv. 2268
StatusPublished
Cited by6 cases

This text of 90 P.2d 135 (Hayward Lumber & Investment Co. v. Ross) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hayward Lumber & Investment Co. v. Ross, 90 P.2d 135, 32 Cal. App. 2d 455, 1939 Cal. App. LEXIS 377 (Cal. Ct. App. 1939).

Opinion

GRIFFIN, J.

This is an action to foreclose a lien for materials used in alteration work on a building in Bakersfield, *456 Kern County, California. At the trial it was conceded by all parties that materials of the approximate value alleged in the complaint were furnished by the plaintiff and were actually used in the work of construction, with the exception of $26.60, representing the charges for cartage of approximately $900 worth of materials. It was further conceded at the trial and the court found that the plaintiff was entitled to a lien against the right, title and interest of the defendant and respondent Bank of America National Trust & Savings Association, except in so far as that right might be affected by the posting of notice of nonresponsibility by the bank on March 18, 1936, and its recordation on March 20, 1936.

The actual work of construction was commenced on August 26, 1936, and actually completed about November 1, 1936. Appellant filed its claim of lien in due and legal time, filed its suit of foreclosure within the time allowed by law, and in all other respects complied with all requirements of the law concerning such liens.

The respondent Bank of America National Trust & Savings Association knew on February 3, 1936, by the terms of its lease of the property in question, that the alteration and construction work was intended by its lessee. This lease by its terms became effective May 15, 1936. Respondent bank knew, through its officers, of the progress of the work as it was being done, but did not cause to be posted nor recorded any notice of nonresponsibility after the commencement of the actual work of improvement, and posted and filed no notice of nonresponsibility except the one of March 18, 1936, herein referred to.

The defendant W. P. Ross, having defaulted, the court found that appellant was entitled to judgment against him as prayed for. The court further found that appellant was entitled to a lien against the leasehold interest of respondent Food City Market Corporation to the extent of $429.44.

The court found that the improvements in question were made by respondent Food City Market Corporation and defendant W. P. Ross with the knowledge of all defendants having any proprietary interest in the premises. The court also found that the respondent bank had knowledge of the work of improvement at the time the work was being done, viz., between August 15, 1936, and November 1, 1936. The *457 court also found that on March 18, 1936, the respondent bank caused a notice of nonresponsibility to be posted on the real property (therein described) and thereafter on March 20, 1936, caused said notice of nonresponsibility, together with affidavit of posting, to be recorded in the office of the county recorder of Kern County.

As conclusions of law the court found that the judgment should be a lien to the extent of $429.44, plus costs against the respondent Food City Market Corporation, and that appellant is not entitled to a lien against the right, title and interest of respondent Bank of America National Trust & Savings Association in and to the property described in the complaint.

One of the questions presented is this: Where an owner has knowledge of intended improvements by a tenant on his property and he posts and records a notice of non-responsibility for such intended improvements, and approximately 5 months thereafter work of improvement is actually commenced and the owner had knowledge of the actual improvements at the time they were commenced and files no other notice of nonresponsibility, does the notice of non-responsibility posted and recorded approximately 5 months before actual commencement of the work of improvement .relieve him of liability for a materialman’s lien under section 1192 of the Code of Civil Procedure in effect in 1936 Í

The courts have adopted the general rule of strict construction of any act or provision by which the owner of property upon which improvements are made may relieve himself from or escape liability therefor. (Hammond Lumber Co. v. Goldberg, 125 Cal. App. 120 [13 Pac. (2d) 814].) The amendment of section 1192 of the Code of Civil Procedure in 1873 (Stats. 1873-1874, chap. CCCCX, [Volume of Amendments to Codes, pp. 108, 109]) provided for the posting and recording of notice of nonresponsibility “within three days after he (the owner) shall have obtained knowledge of the construction, alteration, or repair, or the intended construction, alteration or repair. ...” In 1907 (Stats. 1907, p. 577) this section was amended, providing that the owner should file notice of nonresponsibility within ten days “after he shall obtain knowledge of the construction, alteration, repair, or work or *458 labor, ...” The phrase “or the intended construction, alteration or repair” was eliminated.

In John R. Gentle & Co. v. Britton, 158 Cal. 328, 332 [111 Pac. 9], (1910) our Supreme Court stated:

“The statute as originally enacted did not contain the clause 1 intended construction, ’ and the time for posting the notice was fixed at three days after knowledge of the construction, alteration or repair. This must then be construed to mean of the progress of the work, which could not have been earlier than the commencement of the work, and it has been held that where an owner had knowledge of the ‘intended construction’ and did not give the notice within three days thereafter, but gave such notice within three days after the commencement of the work, he was entitled to the protection of the statute. . . .
‘ ‘ The law does not say that upon the posting of the notice the owner will not be liable for any labor performed or material furnished thereafter,'but that if he fails to post such notice within the statutory time after knowledge that the improvement was being made, it shall be held to have been constructed at his instance. There is no limitation in respect to the stage of the work at the time at which the notice must be posted. The statutory provision would be complied with by a posting on the same day the improvement was begun, if this were within three days after knowledge was obtained, either of the construction or intended construction. And, if done within three days after knowledge received, we see no reason why it would not be timely upon any day when the work on the improvement was in progress. ...”

In Whiting-Mead Com. Co. v. Brown, 44 Cal. App. 371, 374 [186 Pac. 386, 388], (1919) it was related:

“This leaves for our consideration the question of the personal responsibility of the defendant. The only point made by the appellant in its attack upon this portion of the judgment is that because the defendant had notice at the time of the contract with Alex Brown for the sale of the premises that the said Alex Brown intended to make certain improvements to the premises, the defendant was charged with notice of the making of said improvements, irrespective of whether he had actual knowledge or not, at the time he entered into said agreement with said Alex Brown. As pointed out by the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ivy Trucking, Inc. v. Creston Brandon Corp.
100 Cal. Rptr. 2d 582 (California Court of Appeal, 2000)
Los Banos Gravel Co. v. Freeman
58 Cal. App. 3d 785 (California Court of Appeal, 1976)
Arthur B. Siri, Inc. v. Bridges
189 Cal. App. 2d 599 (California Court of Appeal, 1961)
Bond Electric Co. v. Mill City Plastics, Inc.
102 N.W.2d 281 (Supreme Court of Minnesota, 1960)
Hayward Lumber & Investment Co. v. Ford
148 P.2d 689 (California Court of Appeal, 1944)
Hayward Lumber & Investment Co. v. Orondo Mines
94 P.2d 380 (California Court of Appeal, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
90 P.2d 135, 32 Cal. App. 2d 455, 1939 Cal. App. LEXIS 377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hayward-lumber-investment-co-v-ross-calctapp-1939.