Coombs v. Green Mill, Inc.

290 P. 620, 107 Cal. App. 204, 1930 Cal. App. LEXIS 405
California Court of Appeal·Decided July 11, 1930·No. Docket Nos. 4119, 4160.·Published·Cited by 3 cases

Opinion

THOMPSON, (R. L.), J.

Separate appeals were taken from judgments foreclosing mechanics’ liens in these actions, which were consolidated for trial.

The appellant is the owner of eight lots in Los Angeles County which are described in the complaint. November 30, 1922, he executed a ten-year lease of the property to Green Mill Catering Company, a corporation. The lease recited that it was the intention of the lessee to promptly erect a building thereon to he used for restaurant and entertainment purposes. Before this structure was commenced and on December 11, 1922, the appellant posted and recorded notices under the provisions of section 1192 of the Code of Civil Procedure for the purpose of exempting the real property from liability for a failure to pay for this structure. A few days later the lessee constructed a concrete foundation for the proposed building. No further work was ever performed on this building. The Catering Company became financially embarrassed. The construction *206 of the building was abandoned. The lease was transferred to another corporation called the Green Mill, Inc. The appellant resided on the premises and knew of the abandonment of the structure on the part of the Catering Company. About five months later the Green Mill, Inc., contracted with the plaintiff Coombs to construct a restaurant on the same premises at a cost of $75,000. Work upon this new building was immediately commenced. The foundation which had been previously constructed by the original lessee was demolished. The new structure was completed in due time. The original lessee had nothing to do with its construction or the contract therefor. The building was entirely distinct from the one which was planned by the Catering Company. The appellant had full knowledge of the progress and completion of this restaurant. No notices of nonliability for the cost of this structure were ever posted or recorded. No such notices were ever given except the ones heretofore referred to which were posted by the owner of the land on December 11, 1922. Neither the contractor nor the materialmen were entirely paid for their contribution to this building. Liens were accordingly filed to secure the unpaid portion thereof. Payment was refused and these actions were instituted. The indebtedness was conceded. The appellant contends that the posting and recording of his original notices of nonliability relieve him from responsibility for this indebtedness. The evidence which was adduced in both cases is exactly alike with the exception of the amount and character of the indebtedness.

The court found that the Green Mill Catering Company and the Green Mill, Inc., company are separate and distinct corporations, having no privity of interest in the property involved; that the last-mentioned corporation constructed the building and that the Catering Company had no part or interest in the same; that in the process of constructing said building, which was commenced May 15, 1923, the plaintiffs performed labor and furnished materials as alleged in the complaints, specifying the proportion thereof which remained unpaid; that liens therefor were duly filed; that the appellant is the owner of said property; that no notices of nonresponsibility therefor were posted or recorded pursuant to section 1192 of the Code of Civil Procedure and that the appellant is liable for said sums and *207 plaintiffs are entitled to a decree of foreclosure of said liens to satisfy the judgments. Judgments and decrees of foreclosure were accordingly entered, from which these appeals were perfected.

The respondents contend that the notices of nonliability which were posted and recorded by the appellant on December 11, 1922, had no application to the structure subsequently erected which is involved in these actions and therefore do not serve to relieve him from said obligations and liens; that the notices which were formerly posted were fatally defective in that the recorded copy thereof was not verified as required by law, and that the building was constructed under the direct agency of the appellant pursuant to a provision of his lease, to the effect that the building which was to be constructed by the lessee “shall at the end of said term, or the sooner termination of this lease, become the property of said parties of the first part [appellant and wife, and] constitutes a part of the consideration for the granting of this lease.”

In view of our construction of section 1192 of the Code of Civil Procedure requiring the affirming of the judgments, it becomes unnecessary to pass upon the last two contentions of the respondents.

The notices of exemption from liability which were posted and recorded by the appellant pursuant to section 1192 of the Code of Civil Procedure had no application to the particular building for the cost of construction of which the liens were filed, and they were, therefore, ineffectual to relieve him from the statutory burden of the liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Coombs v. Green Mill, Inc., 290 P. 620, 107 Cal. App. 204, 1930 Cal. App. LEXIS 405 (Cal. Ct. App. 1930).

290 P. 620 (Coombs v. Green Mill, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Jay Bailey Construction Co. v. Beery Hotel Corp.
221 Cal. App. 2d 135 (California Court of Appeal, 1963)
Hayward Lumber & Investment Co. v. Ross
90 P.2d 135 (California Court of Appeal, 1939)
Dixon v. Fredericks
19 P.2d 272 (California Court of Appeal, 1933)