First Nat'l Bank of Bridgeport v. Perris Irrigation Dist.

40 P. 45, 107 Cal. 55, 1895 Cal. LEXIS 711
CourtCalifornia Supreme Court
DecidedApril 5, 1895
DocketNo. 19501
StatusPublished
Cited by24 cases

This text of 40 P. 45 (First Nat'l Bank of Bridgeport v. Perris Irrigation Dist.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Nat'l Bank of Bridgeport v. Perris Irrigation Dist., 40 P. 45, 107 Cal. 55, 1895 Cal. LEXIS 711 (Cal. 1895).

Opinion

The COURT.

Plaintiff a corporation, commenced this action July 22, 1893, to recover of defendant a sum of money alleged to be due the plaintiff under an assignment of a claim therefor to it made by the Ætna Iron and Steel Company, also a corporation, on May 16, 1893. The defendant is an irrigation district formed under the statute providing for the organization and government of such districts, approved March 7, 1887. One W. L. Ewing filed a complaint in intervention, but the findings and judgment were against him, and he has not appealed. The case comes here on the judgment-roll alone.

From the record it appears that on March 26, 1891, defendant made a contract with the Silver Gate Manufacturing Company, a corporation, whereby such company agreed to construct for defendant a line of wood pipe 6.5 miles in length, and to keep the same in repair, free from leakage, for the period of one year after the completion thereof; the price to be paid by defendant for such work was by the contract made payable thirty-five days after the completion of the pipe line. The construction of such pipe was completed by the Silver Gate "Manufacturing Company, or by said .¿Etna Iron and Steel Company, acting for and in the stead of said manufacturing company, on the ninth day of January, 1893. Previously, on September 14, 1892, said manufacturing company, the original contractor, assigned its claims due, or to become due, on account of the contract to the said .¿Etna Iron and Steel Company.

On May 2, 1893, the defendant by its board of directors allowed and approved the account of the .¿Etna Iron [58]*58and Steel Company, as assignee of the original contractor, for the balance due under the said contract, amounting to the sum of $11,692.05; of which amount $7,500 was paid, and the sum of $4,192.05 remains unpaid, and is the subject of this action; the demand of said .Etna Iron and Steel Company for such balance was assigned to plaintiff May 16, 1893, as stated above.

The interest of the intervenor, Coronado Foundry and Machine Company, arose in this wise: Subsequently to March 26, 1891, the date of the contract, said intervenor entered into an oral agreement with the contractor, the Silver Gate Manufacturing Company, whereby said intervenor promised to furnish to the contractor all the iron couplings to be used in the construction of said pipe line, the quantity of such material so to be furnished being not otherwise specified, at the price of 4£ cents per pound, which price the contractor agreed to pay. The court found that such agreement “ also included the making by said intervenor of all patterns for said couplings and the furnishing of boxes in which to ship said couplings, said Silver Gate Manufacturing Company agreeing to pay the reasonable value of said patterns and boxes to said intervenor.” No time of payment was specified in said agreement.

The intervenor made such patterns to the value of $111 05, and boxes to the value of $99.05.. Patterns, boxes, and couplings were made and supplied by the intervenor to the contractor in divers quantities and at divers times, from April 13, 1891, to November 9°, 1891 (except a single item of patterns, amounting to $7.65, found to have been furnished February 19, 1891); the last item of couplings, $10.60 in amount, being supplied November 9, 1891. The couplings were actually used in the construction of the pipe line, but no patterns or boxes were so used; it seems that the patterns were used by the intervenor in moulding the couplings at its own works, and were necessary for that purpose; they were [59]*59charged to the contractor, though it never had actual possession of them; the boxes were necessarily employed in the shipment of the couplings from the place of manufacture to the place of use.

Payments were made to the intervenor on account in the month of July, 1891, amounting to $300; and on October 26, 1893, after this action had been begun, said intervenor served written notice on the defendant that it, the intervenor, “ furnished materials to the Silver Gate Manufacturing Company, to be used, and which actually were used in the construction of the pipe line for the Perris Irrigation District, under the contract between the said Perris Irrigation District and the said Silver Gate Manufacturing Company; that said material was cast couplings to be used in the construction of said pipe line, and that the value of the materials so furnished was $2,439.58”; also that only $300 had been paid on account thereof, and that a balance of $2,139.58 remained due and unpaid; and required defendant to retain in its possession sufficient funds due under its contract with the Silver Gate Manufacturing Company to pay such balance. A few days later, November 4, 1893, said intervenor filed its complaint in intervention herein.

The plaintiff pleaded, among other defenses to interven or’s action, that the same is barred: 1. By the provisions of subdivision 1 of section 339 of the Code of Civil Procedure; 2. By the provisions of section 1190 of the same code.

Regarding the controversy between plaintiff and defendant the court found that default was made in performance of that term of the contract between defendant and the Silver Gate Manufacturing Company, by which the latter agreed to keep the pipe in repair for one year after the completion thereof, and that defendant necessarily expended for that purpose during such period, from January 9, 1893, to January 9, 1894, the sum of $1,223.15. The only averment in the pleadings setting up a counterclaim for this sum is contained in the de[60]*60fendant’s answer filed January 13, 1894, and its most material language is that defendant “ will be required to expend more than the sum of $4,192.05 withheld by defendant herein to keep said pipe line in repair for one year from its completion.”

The court gave judgment in favor of the intervenor, Coronado Foundry and Machine Company, for the amount of its demand—$2,139.58 — and in favor of plaintiff for $829.32, besides interest from February 13, 1893; the remainder of the fund in the hands of defendant, $1,223.15, being allowed to it in virtue of the counterclaim referred to. Plaintiff appeals.

1. Was the notice served on defendant by the intervenor, October 26, 1893, in sufficient time to fix the right of the intervenor in the fund yet remaining in the hands of defendant? Such notice was given more than eight months after the completion of the contract for the construction of the pipe, more than seven months after the balance due undei said contract became payable according to its terms, more than one year after the original contractor had assigned its rights to such balance, and more than three months after plaintiff, as a subsequent assignee thereof, had commenced this action to recover the same. Appellant maintains that, these circumstances considered, the notice was too late. The decision of this question turns upon the proper construction of the statute (Code Civ. Proc., sec. 1184) as amended in 1887; what that construction should be is not discussed in the briefs filed on behalf of either the intervenor or the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stiller v. Rogers
69 Cal. App. Supp. 2d 805 (California Court of Appeal, 1945)
Stiller v. Rogers
69 Cal. App. 2d 805 (Appellate Division of the Superior Court of California, 1945)
Hayward Lumber & Investment Co. v. Ross
90 P.2d 135 (California Court of Appeal, 1939)
Bank of America National Trust & Savings Ass'n v. Casady
59 P.2d 444 (California Court of Appeal, 1936)
Mortgage Guarantee Co. v. Hammond Lumber Co.
57 P.2d 164 (California Court of Appeal, 1936)
Madson v. Ballou
260 N.W. 831 (South Dakota Supreme Court, 1935)
Fairbanks v. Crump Irrigation & Supply Co.
291 P. 629 (California Court of Appeal, 1930)
Mott v. Wright
184 P. 517 (California Court of Appeal, 1919)
General Electric Co. v. American Bonding Co. of Baltimore
182 P. 444 (California Supreme Court, 1919)
Southern California E. Co. v. McDonald
173 P. 760 (California Supreme Court, 1918)
Sweeney v. Board of Trustees of Auburn School District
165 P.2d 42 (California Court of Appeal, 1917)
Pacific Portland Cement Co. v. Hopkins
162 P. 1016 (California Supreme Court, 1917)
Miles v. Ryan
157 P. 5 (California Supreme Court, 1916)
Lynip v. Alturas School District
141 P. 835 (California Court of Appeal, 1914)
Farmer's Irrigation Co. v. Kamm
55 Colo. 440 (Supreme Court of Colorado, 1913)
Reardan v. Cockrell
103 P. 457 (Washington Supreme Court, 1909)
American Bridge Co. v. City of Boston
88 N.E. 1089 (Massachusetts Supreme Judicial Court, 1909)
Weldon v. Superior Court
71 P. 502 (California Supreme Court, 1903)
French v. Powell
68 P. 92 (California Supreme Court, 1902)
Perry v. Parrott
67 P. 144 (California Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
40 P. 45, 107 Cal. 55, 1895 Cal. LEXIS 711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-natl-bank-of-bridgeport-v-perris-irrigation-dist-cal-1895.