French v. Powell

68 P. 92, 135 Cal. 636, 1902 Cal. LEXIS 860
CourtCalifornia Supreme Court
DecidedFebruary 28, 1902
DocketL.A. No. 1014.
StatusPublished
Cited by46 cases

This text of 68 P. 92 (French v. Powell) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
French v. Powell, 68 P. 92, 135 Cal. 636, 1902 Cal. LEXIS 860 (Cal. 1902).

Opinion

*637 CHIPMAN, C.

Plaintiff’s complaint sets forth three causes of action upon a bond executed by defendant Powell, as principal, and defendant company, as surety, under the provisions of the act of March 27, 1897, (Stats. 1897, p. 201). It is alleged that Powell entered into an agreement with the city of Los Angeles on February 8, 1899, to construct a tunnel in Third Street, from Hill to Flower Street, and to furnish at his own cost all the labor and material necessary therefor, and that said work was never completed; that defendants entered into a written undertaking as provided for in the above act. For a first cause of action it is alleged that plaintiff furnished the said Powell the work of certain teams during the months of July, August, and September, 1899, at an agreed price per day for each team and man, amounting in value, in all, to $514.75, and that said work of said teams was completed on the ninth day of September, 1899; that all said work was “furnished for and actually used in the construction of said tunnel under said contract,” and that on March 19, 1900, plaintiff filed with said council a verified statement of his said claim, with a statement that the same had not been paid.

A second cause of action sets forth that one Clapham performed labor for said Powell as a blacksmith during the same months as above named, at the agreed price of three dollars per day, amounting in all to $154; that his said work was completed September 6, 1899, and that said labor was performed in the construction of said tunnel under said contract; that said Clapham filed a verified statement of his said claim with said council on March 19, 1900, and on the same day assigned to plaintiff his claim as aforesaid and all his rights against the defendant- company.

For a third cause of action, and by similar allegations, plaintiff sets forth the claim of one French for one day’s labor, in the month of July, 1899, as superintendent of the work on said tunnel, at the agreed price of $2.50; alleges the filing of the claim and its assignment the same as in the case of said Clapham. Appended to the complaint are copies of the itemized claims filed with the council.' Defendants answered, controverting the allegations of the complaint, and, as a separate defense, pleaded the act in bar, alleging that notice of the several claims was not filed within the time re *638 quired by the act. The contract between Powell and the city was executed February 8, 1899, and is fully set forth in the findings; the court found that Powell assigned all his interest in this contract on May 10, 1899, to the firm of Swenson & Hill; that since said date Swenson & Hill have been engaged in carrying out said contract, “and with the knowledge and approval of said municipal corporation; and all payments of money by said contract provided to be made to said Powell have been made direct to Swenson & Hill by said corporation, as said payments have come due under the contract,” and since said assignment to Swenson & Hill said Powell has done no work and “has never performed any part of said contract.” On May 17, 1899, Swenson & Hill let a contract, which is fully set forth, to one Chaffey to do the excavating, grading, and filling required by the contract, and Chaffey immediately entered upon the work; plaintiff furnished said Chaffey the teams mentioned in the first cause of action, at Chaffey’s request, at the price of $514.75, and the same were used in and about the work of excavating said tunnel. Clapham, mentioned in the second cause of 'action, was employed by Chaffey, and performed blacksmith-work near said tunnel, sharpening tools and implements, to be used, and which were used, in said tunnel, and also he did work on a boring-machine used therein, and his work was of the value of $154. Said French, mentioned in the third cause of action, was employed at the request of Chaffey to oversee the laborers engaged in the work of excavating said tunnel, at the agreed price of $2.50. The claims of Clapham and French were properly assigned to plaintiff. The work contracted to be performed by Powell has never been completed, and the work is still in progress, and the work let to Chaffey by Swenson & Hill has never been completed, and is still in progress. The assignment of the contract by Powell to Swenson & Hill was with the consent and approval of the defendant company, and it agreed to stand as surety for Swenson & Hill in place of Powell, and ever since then Swenson & Hill have paid all premiums on said bond set forth in the complaint, and said company has accepted the same from them. All claims were filed and verified as alleged in the complaint, and, as filed, were made out against Powell, and not against Swenson & Hill or Chaffey. As conclusion of law, the court found that plain *639 tiff was entitled to recover judgment against both defendants for the several amounts claimed, and judgment was entered accordingly. Defendants appeal from the judgment on the judgment-roll.

1. Apellants contend that the suit is prematurely brought, for the reason, as appellants construe the terms of the act, that the claims must be filed within thirty days after the completion of the whole work. In other words, that the expression, “shall within thirty days from the time such work is completed,” etc., fixes the beginning and the ending of the time within which the claim must be filed.

On the other hand, respondent contends “that this language was meant simply to set a limit of time after which such claims could not be filed, and not to forbid the filing of a claim before the completion of the whole work, provided the claimant’s demand is past due.” Section 1 requires that— “Every contractor ... to whom is awarded a contract for the . . . performance of any building, excavating, or other mechanical work for this state, or by any . . . city . . . therein, shall, before entering upon the performance of such work, file with the . . . common council . . . a . . . bond ... in a sum not less than one-half of the total amouiit payable by the terms of the contract; such bond shall be executed [prescribes by whom], and must provide that if the contractor . . . fails to pay for any materials or supplies furnished- for the performance of the work contracted to be done, or for any work or labor done thereon of any kind, that the sureties will pay the same, . . . provided, that such claims shall be filed as hereafter required. ’ ’ Section 2 provides that “Any material-man, . . . furnishing materials, . . . used in the performance of the work, ... or any person who performed work or labor upon the same, . . . whose claim has not been paid, . . . shall, within thirty days from the time such work is completed, file with the . . . common council ... a verified statement that the same has not been paid. At any time within ninety days after the filing of such claim, the person . . . filing the same may commence an action against the sureties on the bond, specified and required by section 1 hereof.”

Appellants’ argument is that the act must receive the same construction as was given section 1187 of the Code of Civil *640 Procedure, where the language is, “within thirty days after the completion of any building . . . file for record,” etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Primo Team, Inc. v. Blake Construction Co.
3 Cal. App. 4th 801 (California Court of Appeal, 1992)
Lange v. Fisher
146 Cal. App. 3d 113 (California Court of Appeal, 1983)
Glass v. Benkert
18 Cal. App. 3d 322 (California Court of Appeal, 1971)
Reifke v. State
31 A.D.2d 67 (Appellate Division of the Supreme Court of New York, 1968)
Contractors Dump Truck Service, Inc. v. Gregg Construction Co.
237 Cal. App. 2d 1 (California Court of Appeal, 1965)
Hodges v. SOUTH GEORGIA NATURAL GAS COMPANY
141 S.E.2d 182 (Court of Appeals of Georgia, 1965)
Powers Regulator Co. v. Seaboard Surety Co. of New York
204 Cal. App. 2d 338 (California Court of Appeal, 1962)
Wixted v. Fletcher
192 Cal. App. 2d 706 (California Court of Appeal, 1961)
Bernard v. Indemnity Insurance
329 P.2d 57 (California Court of Appeal, 1958)
Jensen v. Nelson
19 N.W.2d 596 (Supreme Court of Iowa, 1945)
Young v. Waldrop
109 P.2d 59 (Montana Supreme Court, 1941)
McKesson-Fuller-Morrisson Co. v. Chapell Ice Cream Co.
2 N.E.2d 561 (Appellate Court of Illinois, 1936)
Gurley Lord Tire Co. v. Newgard
50 P.2d 1043 (California Court of Appeal, 1935)
Christie v. Commercial Casualty Insurance Co.
45 P.2d 263 (California Court of Appeal, 1935)
American Surety Co. of New York v. Superior Court
23 P.2d 508 (California Supreme Court, 1933)
McCormick Saeltzer Co. v. Haidlen
6 P.2d 255 (California Court of Appeal, 1931)
A. L. Young MacHinery Co. v. Cupps
2 P.2d 321 (California Supreme Court, 1931)
National Surety Co. v. W. H. Holliday Co.
295 P. 913 (Wyoming Supreme Court, 1931)
Williamson v. Egan
287 P. 503 (California Supreme Court, 1930)
Ryan v. Shannahan
285 P. 1045 (California Supreme Court, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
68 P. 92, 135 Cal. 636, 1902 Cal. LEXIS 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/french-v-powell-cal-1902.