A. L. Young MacHinery Co. v. Cupps

2 P.2d 321, 213 Cal. 210, 1931 Cal. LEXIS 512
CourtCalifornia Supreme Court
DecidedJuly 28, 1931
DocketDocket No. Sac. 4097.
StatusPublished
Cited by15 cases

This text of 2 P.2d 321 (A. L. Young MacHinery Co. v. Cupps) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. L. Young MacHinery Co. v. Cupps, 2 P.2d 321, 213 Cal. 210, 1931 Cal. LEXIS 512 (Cal. 1931).

Opinion

CURTIS, J.

In this action we granted a rehearing for the reason that we failed in the opinion heretofore rendered by us to pass upon the special demurrer interposed to the second amended complaint in this action by the defendant surety company. We are in entire accord with the conclusions reached by us regarding the merits of the general demurrer as set forth in our former opinion, and we express our approval of this opinion by adopting it in its entirety.

It reads as follows:

*212 “Plaintiff appeals from a judgment of dismissal in favor of defendant insurance company entered after the trial court had sustained a demurrer to plaintiff’s second amended complaint without leave to amend. The facts as set forth in plaintiff’s complaint, so far as necessary to be considered on this appeal, are as follows:
“ On November 26, 1924, defendant Cupps entered into a contract with the county of San Joaquin for the construction of a designated public highway in the county for the total sum of $10,459.50. On December 4,1924, Cupps filed with the board of supervisors of the county of San Joaquin a bond in the sum of one-half the contract price, naming the defendant insurance company as surety. The bond specifically recited that it was given and executed pursuant to the Public Works Act of 1919 (Stats. 1919, p. 487). It is then alleged that during the performance of the work under this contract, and between January 13 and February 16, 1926, the plaintiff sold, delivered and furnished to the contractor certain materials, supplies, implements and machinery, consisting of one 30-foot steel frame bucket elevator complete; one 36 by 12' inch screen; a one-yard drag scraper; and certain pulleys, belts, lanterns, hose and extension for the elevator; that there still remains due and unpaid on the above articles the sum of $1,405.75. It is then specifically alleged that the above equipment was ‘furnished for use under the contract above mentioned and were used in, upon, for and about the work contracted to be executed and performed under said contract, and were totally used up, consumed, destroyed and worn out in, upon, for and about the performance of said work under said contract, and at the completion of said work had no further use or value for the purpose for which they were constructed, and were without salvage value’. The date of completion of the work and the filing of the verified claim and withhold notice required by the statute are then alleged, it appearing from such allegations that these steps were all taken within the time and in the manner provided by law. Plaintiff asks judgment against the surety on its bond for the amount of the unpaid balance on the purchase price of the above equipment.
“The trial court, holding the view that the purchase price of such equipment was not covered by the bond, sustained a demurrer without leave to amend. Respondent surety com *213 pany contended on the demurrer, and contends now that it is not liable on the bond for the purchase price of such equipment, on the theory that the bond required by the public works statute allows recovery only for the reasonable rental value of such equipment, when such equipment is in fact rented, and allowed no recovery for the purchase price thereof.
“As stated above, the bond in question was a statutory bond given and executed under the 1919 act, as it then read. The act provides that on public work the contractor must ' give a bond for at least one-half of the contract price of the work, which bond must guarantee that if the contractor ‘fails to pay for any materials, provisions, provender or other supplies, or teams, used in, upon, for or about the performance of the work contracted to be done or for any work or labor done thereon of any kind, that the surety or sureties will pay the same . . .’ The bond issued by respondent is broader in many respects than the bond required by the statute. Both appellant and respondent devote the major portion of their briefs to the question as to whether those provisions in the bond more onerous than those required by the statute can be enforced against the surety. It is not necessary to determine that point on this appeal. It is our opinion that the expressions ‘materials’ and ‘supplies’ found in the statute are sufficiently broad to include equipment of the nature involved herein, .when such equipment is purchased for the particular job, and is entirely consumed thereon, except for normal salvage value. It is true, of course, that the purchase price of equipment capable of being used on more than one job and which becomes part of the contractor’s general equipment, is not covered by the statute, but when the equipment is of such a nature that in the usual course of events it will be entirely used and consumed on the particular job for which it was purchased, it is our opinion that such equipment is included within the meaning of ‘materials’ and ‘supplies’, as used by the statute. Respondent cites several mechanics’ lien cases which indicate that in those cases the lien extends only to those articles which physically go into the structure against which the lien is sought to be exerted. Those cases are not in point. It has repeatedly been held in reference to the 1919 act, and its predecessors, that such acts are to be *214 more liberally construed than the mechanic’s lien statutes, and that the reasons for giving a limited construction to the latter are not applicable. to the former. (Pacific Wood & Coal Co. v. Oswald, 179 Cal. 712 [178 Pac. 854]; Sherman v. American Surety Co., 178 Cal. 286 [173 Pac. 161]; French v. Powell, 135 Cal. 636 [68 Pac. 92]; Associated Oil Co. v. Commary-Peterson Co., 32 Cal. App. 582 [163 Pac. 702].) It has been held under the 1919 act and similar public work statutes that rental of machinery, money expended on the hiring of mule teams, money spent for provisions, harness and other equipment, including scrapers, freight on mules and equipment, etc., are all recoverable against the surety. (Williamson v. Egan, 209 Cal. 343 [287 Pac. 503]; Pacific Wood & Coal Co. v. Oswald, supra; Bricker v. Rollins & Jarecki, 178 Cal. 347 [173 Pac. 592, 594]; Sherman v. American Surety Co., supra; Peoples Nat. Bank v. Southern Surety Co., 105 Cal. App. 731 [288 Pac. 827].) The theory of these cases is that the statute was intended to cover all those things which have contributed to the improvement,' whether directly by physically going into the construction, or indirectly, by being entirely consumed or used in the construction. In discussing the word ‘supplies’, as used in a previous statute, the court in Bricker v. Rollins, supra, stated: ‘The ordinary meaning of this term in its general and accepted use is such as to include goods, wares, and merchandise of almost every kind and nature, whether used in the household or on the farm, or in any sort of productive or constructive work requiring the labor or service of men or animals or machinery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George F. Kennedy, Inc. v. Miles & Sons Construction Division
5 Cal. App. 3d 516 (California Court of Appeal, 1970)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
International Harvester Co. v. L. G. DeFelice & Son, Inc.
197 A.2d 638 (Supreme Court of Connecticut, 1964)
Bernard v. Indemnity Insurance
329 P.2d 57 (California Court of Appeal, 1958)
Thayer v. Board of Osteopathic Examiners
320 P.2d 28 (California Court of Appeal, 1958)
Baker v. Littman
292 P.2d 595 (California Court of Appeal, 1956)
American Surety Co. v. Sampsell
148 F.2d 986 (Ninth Circuit, 1945)
Gurley Lord Tire Co. v. Newgard
50 P.2d 1043 (California Court of Appeal, 1935)
Christie v. Commercial Casualty Insurance Co.
45 P.2d 263 (California Court of Appeal, 1935)
Shoshoni Lumber Co. v. Fidelity & Deposit Co.
24 P.2d 690 (Wyoming Supreme Court, 1933)
Rhodes v. Riley
169 S.E. 525 (West Virginia Supreme Court, 1933)
Garbutt v. Chappe
21 P.2d 594 (California Court of Appeal, 1933)
H. G. Fenton Material Co. v. Noble
15 P.2d 884 (California Court of Appeal, 1932)
McCormick Saeltzer Co. v. Haidlen
6 P.2d 255 (California Court of Appeal, 1931)
Fitzpatrick v. Haskell
4 P.2d 580 (California Court of Appeal, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
2 P.2d 321, 213 Cal. 210, 1931 Cal. LEXIS 512, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-l-young-machinery-co-v-cupps-cal-1931.