Shoshoni Lumber Co. v. Fidelity & Deposit Co.

24 P.2d 690, 46 Wyo. 241, 1933 Wyo. LEXIS 36
CourtWyoming Supreme Court
DecidedAugust 29, 1933
Docket1801
StatusPublished
Cited by6 cases

This text of 24 P.2d 690 (Shoshoni Lumber Co. v. Fidelity & Deposit Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shoshoni Lumber Co. v. Fidelity & Deposit Co., 24 P.2d 690, 46 Wyo. 241, 1933 Wyo. LEXIS 36 (Wyo. 1933).

Opinion

*251 Riner, Justice.

This case comes before the court upon direct appeal from a judgment of the District Court of Na-trona County in favor of Shoshoni Lumber Company, plaintiff and respondent, for convenience subsequently referred to as the “plaintiff,” and against both the Fidelity and Deposit Company of Maryland, defendant below, appellant here, and generally hereinafter mentioned as the “surety,” and James F. Turpén, defendant below, respondent here, who may appropriately be designated as the “contractor.”

The litigation was commenced by the plaintiff in Fremont County and, after the issues were framed, was removed on application of the surety to Na-trona County where the trial thereof was had and the judgment aforesaid was rendered.

On July 2, 1929, the State of Wyoming, through the State Highway Commission, entered into two contracts with the said Turpén. These instruments provided that he should “do all work and furnish all labor, materials, tools” necessary to properly complete, under the one contract, the “concrete work, iron pipe railing and painting structural steel for a 450 foot bridge over Wind River on the River-ton Shoshoni road,” and under the other, the “structural steel for a 250 foot steel truss” needed as a part of said bridge. Several days thereafter, as required by law, the contractor, with appellant surety thereon, executed two bonds to the State for its use and “also for the use and benefit of all persons who may perform any work or labor or furnish any material in the execution” of said con *252 tracts, the condition of each of said bonds being, in part, that if the said Turpén should “pay as they become due and payable, all just claims for work or labor performed and material furnished in the execution” of each contract, then the obligation should be void, otherwise it should be “in full force and effect.” The bond on the steel contract was given for the sum of $28,900, and that relating to the substructure agreement was for the sum of $35,-600. Work was begun on the bridge about the 15th of July, 1929, the steel contract being completed in April, 1930, and the substructure contract in the month of June following. It was pleaded by the plaintiff and the court found as a fact that the two contracts were “in effect, for the construction of the bridge as an integral undertaking,” as Turpén, under them, appears to have built the entire proposed structure.

The contractor failed to pay certain claims for labor and material furnished in the execution of these contracts, and the plaintiff, both on its own behalf and as assignee of sundry other unpaid claimants, brought suit against him and his surety on the bonds aforesaid, to recover the Several amounts claimed to be due. After plaintiff’s original petition, consisting of fifteen alleged causes of action, had been filed, the court, on motion of the surety, required the pleading to be recast so as to show under which of the contracts above mentioned the various items of labor and materials, for which recovery was sought in said petition were furnished. Ultimately, a second amended petition was filed by plaintiff wherein it was, at the outset, stated in substance that plaintiff could not, at that time, safely comply with the court’s order and, hence, pleaded each claim as a cause of action under each bond. A demurrer, for the most part general in *253 character, interposed by the surety to this pleading, was overruled and both defendants filed answers, in substance, general denials. Upon the trial, neither the surety nor the contractor introduced any evidence whatsoever, to sustain the issues in their behalf and the contractor, himself, was called- and testified as a witness for the plaintiff. He not only attested the correctness of plaintiff’s several claims, as labor and material duly furnished him in the execution of the contracts aforesaid, but indicated to which of these contracts the various items of said claims were properly allocated.

The judgment, of which complaint is made, found generally in favor of the plaintiff and against each of the defendants. It also specifically found and separately stated the amounts due on each claim and to which contract the several items thereof so found due were chargeable. The total amount, including interest, awarded plaintiff by the judgment was the sum of $2,'789.07.

The contractor filed no brief in this court, the attack on the judgment being maintained by the surety alone. Upon due application, permission was granted Marion A. Kline, as counsel for other parties interested in questions existing in pending litigation rather similar to some of those presented in this case, to file a brief herein as amicus curiae, to which the surety has filed its response.

It is first insisted that plaintiff’s second amended petition fails- to state a cause of action relative to any of the fifteen claims relied on therein, because it is said that, inasmuch as plaintiff has pleaded each of its claims as recoverable under each of the two bonds and, as this cannot be so in fact, no recovery at all can be had under the pleading. In substance, it is contended that each cause of action should have been pleaded so as to exactly show *254 what the proofs given upon the trial ultimately did.

But, as will be recalled from what has been stated above, plaintiff expressly declared in its pleading that it could not safely do this, and it is apparent from the evidence in the case, as well, that it did not obtain accurate information concerning the matter until long after its second amended petition was filed. The contractor at all times possessed this knowledge. He was aligned with the surety as a defendant in the case. Inasmuch as the contract of suretyship imports entire good faith and confidence between the parties' thereto relative to the whole transaction, it would seem that the surety itself could have obtained the desired information as to just what items of labor and material were used in the execution of each of the contracts, much more readily and easily than either the plaintiff or its1 assignors. Suppose, as is suggested by appellant, the plaintiff or its assignors had inquired, at the time the labor was rendered or the materials furnished, concerning the execution of which contract they were to be applied, and they had obtained, for one reason or another, inaccurate information. Appellant’s argument leads to the result that they then should lose the value of their labor and materials. We cannot think that this should be so.

The contention is not made here for the surety that the labor and materials did not enter into the execution of the contracts involved or that the amounts of the several bonds have been exceeded by the surety’s payment on account of such claims or would be exceeded if the instant judgment were allowed to stand. In view of the circumstances shown in this case relative to this phase of the matter, we fail to see how the surety has been in any *255 way prejudiced by the judgment under review. As has been mentioned, the judgment itself segregates to the several contracts the various items of labor and material of the claims adjudicated, and the surety appears, consequently, to have been afforded the information and protection it desired.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stockman Bank of Montana v. Mon-Kota, Inc.
2008 MT 74 (Montana Supreme Court, 2008)
Thompson-Green v. Estate of Drobish
2006 WY 126 (Wyoming Supreme Court, 2006)
J.W.D., Inc. v. Federal Insurance Co.
806 S.W.2d 327 (Court of Appeals of Texas, 1991)
Miller v. New Amsterdam Casualty Co.
123 S.E.2d 717 (Court of Appeals of Georgia, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
24 P.2d 690, 46 Wyo. 241, 1933 Wyo. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shoshoni-lumber-co-v-fidelity-deposit-co-wyo-1933.