Newport Wharf & Lumber Co. v. Drew

58 P. 187, 125 Cal. 585, 1899 Cal. LEXIS 907
CourtCalifornia Supreme Court
DecidedAugust 16, 1899
DocketL. A. No. 554
StatusPublished
Cited by18 cases

This text of 58 P. 187 (Newport Wharf & Lumber Co. v. Drew) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newport Wharf & Lumber Co. v. Drew, 58 P. 187, 125 Cal. 585, 1899 Cal. LEXIS 907 (Cal. 1899).

Opinion

HARRISON, J.

Dewar & Chisholm, as contractors, entered into a contract with the board of trustees of the Southern California State Asylum for the insane and inebriates, January 5, 1894, by which they agreed to perform the labor and furnish the material required for the carpenters’ and plasterers’ work of a ward building for the asylum, at an agreed price to be paid as follows, viz., ninety per cent of the value of the materials used [587]*587and labor performed “as the work progresses,” and payment in full “upon the acceptance of said work by the board of trustees.” For the purpose of determining the amount of the several payments, the contract provided that the superintendent of construction should for each payment make a certificate “showing a full and accurate estimate of the labor performed and materials furnished under the contract, with the amount due thereon,” which estimate should, in all cases, give the amount of the preceding estimates, if any, and the amount of labor performed and materials furnished since the last estimate; and it was further provided that these estimates should not be required oftener than once a month, and that the trustees of the asylum should retain from each and all payments a sum amounting to ten per cent of the amount thereof, “until the completion and acceptance of said work” by them. Under these provisions ten estimates, or certificates, were made by the superintendent of construction, of which the first seven were paid to the contractors. The controversy herein relates only to the last three estimates and the ten per cent of the contract price retained by the trustees.

The customary mode of making these estimates was as follows: A certificate showing the labor performed and materials furnished by the contractors subsequent to the preceding one, together with their value, was prepared in the form of a bill of account in behalf of the contractors, with the approval of the superintendent of construction indorsed thereon, and was presented to the board of trustees for its allowance and order for payment. Upon the allowance and order for payment of this bill a warrant was drawn by the state controller in favor of the trustees for the payment of ninety per cent of its amount and delivered to them. In this manner the eighth estimate, amounting to $2,814.75, was presented to the board of trustees, and by that body allowed and ordered paid January 14, 1895, and a warrant for ninety per cent thereof, viz., $2,533.28, was drawn by the controller in favor of the trustees March 2d, and thereafter paid to the trustees. The ninth estimate, for $649.75, was presented and allowed February 11th, and a warrant for ninety per cent thereof, viz., $584.78 was drawn March 29th and paid to the trustees. March 18th the tenth and final estimate, for [588]*588$725.90, was presented and allowed, and the work of the contract having at that time been completed, a warrant for $2,579.33, the amount of this estimate, together with the amount of the previous deductions of ten per cent, was drawn in favor of the trustees and paid May 17th.

The plaintiff herein furnished materials to Dewar & Chisholm at various times prior to February 7, 1895, which were used in the performance of their contract, and on March 1, 1895, gave to the board of trustees a notice in writing of that fact, and that there was remaining unpaid thereof the sum of $6,654.10, and demanded payment to it of the balance then remaining unpaid to Dewar & Chisholm. Dewar & Chisholm borrowed money at different times during the performance of their contract from the Farmers’ Exchange Bank, one of the defendants herein, and in some instances executed their promissory notes therefor, and.assigned to the bank the estimates of the superintendent of construction as security for their payment. The superintendent of construction was accustomed to give to them informal certificates, or estimates, before presenting them to the board of trustees for allowance, and upon their receipt Dewar & Chisholm assigned them to the bank, as such security, with directions that the amount of the estimate be paid to the bank. Such informal certificate for the eighth estimate was made December 28, 1894, and was assigned to the bank on the next day as security for a note of two thousand dollars, with an order for its pajnnent to the bank. The ninth estimate is dated February 11, 1895, and was in like manner indorsed over to the bank February 13th. After the approval of these estimates by the board of trustees and an order for their payment, the cashier gave notice to the trustees that they had been assigned to the bank, and requested that the amount thereof should be paid to it. The tenth informal certificate is' dated February 15th, and states that it will be presented to the trustees for their approval March 11th. It was indorsed over to the bank on the day of its date, and on the same day the cashier gave notice thereof to the trustees, stating therein that the estimate would be presented to the board at its next meeting.

At the meeting of the trustees March 18th, at which the tenth estimate was approved, the above notice given by the [589]*589plaintiff to the trustees was considered by them, and they determined that inasmuch as the above three estimates had been assigned for value to the bank, prior to the receipt of the notice, the amount thereof should be paid to the bank and not to the plaintiff. Thereupon the plaintiff brought the present action for the purpose of determining the respective rights of it and the bank to the same. The superior court held that the bank was entitled to the unpaid amount of its advances upon the estimates to Dewar & Chisholm, and that the plaintiff was entitled to the surplus thereof, and rendered judgment accordingly. From this judgment and the order denying a new trial the plaintiff has appealed.

1. The effect of the notice of March 1st, given by the plaintiff to the trustees, was to intercept in their hands any money which Dewar & Chisholm were then entitled to receive, or which afterward might be payable to them in accordance with the terms of their contract. The notice was equivalent to a garnishment of the moneys then payable to them, and also operated as a notice to the trustees of the plaintiff’s claim against Dewar & Chisholm, and that the payment to the latter of any moneys that might thereafter become payable to them under the terms of the contract would be at the peril of the trustees. The contractor cannot prevent the effect of this notice as to any payments that may mature after it is given, but its effect upon payments that have matured before it is given, but which have not been made, is to be determined by the rights of the contractor in reference to them. If he is still entitled to demand their payment from the owner, such payment is intercepted by the notice, but if he has already assigned them to a third party the notice will be inoperative to prevent their payment to such party. (Code Civ. Proc., sec. 1184; Bates v. Santa Barbara County, 90 Cal. 543; First Nat. Bank v. Perris Irr. District, 107 Cal. 55.)

The provision in the contract for the payment of ninety per cent of the value of materials used and labor performed “as the work progresses," with the condition that, before any payment should be made, the superintendent of construction should, not oftener than once a month, furnish an “estimate" of such labor and materials, “with the amount due thereon," rendered [590]*590such instalment of the contract price due and payable immediately upon the acceptance of the work by the trustees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Surety Co. v. Lafferty
43 S.W.2d 460 (Court of Appeals of Texas, 1931)
Fairbanks v. Crump Irrigation & Supply Co.
291 P. 629 (California Court of Appeal, 1930)
Wilson v. New Castle City
152 A. 102 (Supreme Court of Pennsylvania, 1930)
Los Angeles City School District v. Tucker
278 P. 507 (California Court of Appeal, 1929)
Dakota Trust Co. v. City of Hankinson
205 N.W. 990 (North Dakota Supreme Court, 1925)
General Electric Co. v. American Bonding Co. of Baltimore
182 P. 444 (California Supreme Court, 1919)
Hammond Lumber Co. v. Fanta
178 P. 503 (California Supreme Court, 1919)
Southern California E. Co. v. McDonald
173 P. 760 (California Supreme Court, 1918)
Sweeney v. Board of Trustees of Auburn School District
165 P.2d 42 (California Court of Appeal, 1917)
Miles v. Ryan
157 P. 5 (California Supreme Court, 1916)
Welles v. Portuguese-American Bank
211 F. 561 (Ninth Circuit, 1914)
Diamond Match Co. v. Silberstein
131 P. 874 (California Supreme Court, 1913)
Spengler v. Stiles-Tull Lumber Co.
48 So. 966 (Mississippi Supreme Court, 1909)
Valley Lumber Co. v. Struck
80 P. 405 (California Supreme Court, 1905)
Newport Wharf & Lumber Co. v. Drew
74 P. 697 (California Supreme Court, 1903)
French v. Powell
68 P. 92 (California Supreme Court, 1902)
Long Beach School District v. Lutge
62 P. 36 (California Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
58 P. 187, 125 Cal. 585, 1899 Cal. LEXIS 907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newport-wharf-lumber-co-v-drew-cal-1899.